By The Numbers:

1,493 tons of asphalt placed

370 square feet of sidewalk

160 lineal feet of curb and gutter

273 signs installed

Storm preparation

54 stormwater inspections

193 tons of trash removed

11.7 miles of sewer lines cleaned

386 trees trimmed

96 graffiti locations

2 police vehicles upfitted

232 vehicles serviced

2,615 parking citations issued

Tagged as:
City of Salinas, CA published this content on October 19, 2026, and is solely responsible for the information contained herein. Distributed via Public Technologies (PUBT), unedited and unaltered, on October 19, 2026 at 19:15 UTC. If you believe the information included in the content is inaccurate or outdated and requires editing or removal, please contact us at [email protected]