Planned street paving work started on May 5, 2025 on University Ave. and will continue for three weeks. Expect delays on University Ave. from Middlefield Rd. to Chaucer St. with the contractor maintaining the two-way traffic. Please note that bikes and cars will have to share a lane.
•May 5 - 9: Pavement milling and crack sealing
•May 12 - 16: Paving and raising of utility valves
•May 19 - 23: Striping

Signage is posted noting commuters of this work and notices were handed out to residents and businesses directly impacted. Please use alternative routes, if possible.

Tagged as:
City of Palo Alto, CA published this content on May 05, 2025, and is solely responsible for the information contained herein. Distributed via Public Technologies (PUBT), unedited and unaltered, on May 05, 2025 at 21:32 UTC. If you believe the information included in the content is inaccurate or outdated and requires editing or removal, please contact us at support@pubt.io