10/09/2025 | News release | Distributed by Public on 10/09/2025 09:27
Cummins Highway Update: October 2025
Cummins Highway Update: October 2025
October 6, 2025 - October 10, 2025
Begin installing raised crosswalks (Wood to Itasca)
Begin paving the bike lane (Wood to Itasca)
Install curb and sidewalk at the intersection with Itasca
Finish installing curbs between Savannah and Corman
Install curb between Favre and Brockton
October 13, 2025 - October 17, 2025
Begin reconstruction of Woodhaven/Cummins intersection. Detour Plan:Between the hours of 7 am and 3:30 pm, Woodhaven Street will be closed to general traffic (residents and drivers who need to access properties on Woodhaven Street will still be able to enter/exit)
Finish installing raised crosswalks (Wood to Itasca)
Continue paving the bike lane and
Install new curb and sidewalk at the western corner of the Ridlon Road intersection
Finish installing curbs between Richmere and Bismarck
October 20, 2025 - October, 24, 2025
Prepare road for paving at (milling) intersection at Wood/Harvard and side street intersections
Pave the road between Wood/Harvard to roundabout at Weybosset/Greenfield
Continue paving the bike lane (Wood to Itasca)
Install curbs between Bismarck and Woodhaven
Install curbs between Brockton and Favre
Install permanent signage
October 27, 2020 - October 31, 2025
Pour concrete for remaining driveways and pedestrian ramps
Work on signalized intersections
Fill in material for planters and green infrastructure
Last updated: October 9, 2025
Published by:Public Works
City of Boston, MA published this content on October 09, 2025, and is solely responsible for the information contained herein. Distributed via Public Technologies (PUBT), unedited and unaltered, on October 09, 2025 at 15:27 UTC. If you believe the information included in the content is inaccurate or outdated and requires editing or removal, please contact us at [email protected]