DeKalb County...
Lane Closure Advisory for the I-285/I-20 East Interchange Project
What: Weather permitting, the Georgia Department of Transportation (Georgia DOT) construction partners will temporarily close interstate lanes at the locations below for the I-285/I-20 East Interchange project. The project will reconstruct the interstate, system-to-system ramps at the I-285/I-20 East Interchange and add a combination of collector-distributor (CD), or connecting lanes, and auxiliary lanes along I-20 east of the interchange and I-285 north of the interchange.

Where/When: Traffic impacts on the I-285/I-20 Interchange project from Friday, August 21, 2026, through Friday, August 28, 2026.
DAYTIME CLOSURES:
Friday, August 21, through Friday, August 28, from 9 a.m. to 2 p.m.
  • I-20 Eastbound: Single, right- or left-lane and shoulder closure from Columbia Drive (MM 66.8) to Wesley Chapel Road (MM 69.5)
  • I-20 Eastbound: Single, right- or left-lane and shoulder closure from Wesley Chapel Road (MM 69.5) to Panola Road (MM 71.3)
  • I-20 Eastbound: Single, right- or left-lane and shoulder closure from Panola Road (MM 71.4) to Fairington Road (MM 72.8)

Friday, August 21, through Friday, August 28, from 9 a.m. to 4 p.m.
  • Miller Road over I-20: Flagging operation

Friday, August 21, through Friday, August 28, from 9 a.m. to 4 p.m.
  • Chupp Way at Fairington Road: Flagging operation

OVERNIGHT CLOSURES AND TRAFFIC PACING:
Friday, August 21, through Friday, August 28, from 7 p.m. to 6 a.m.
  • I-20 Eastbound: Single to double, right- or left-lane and shoulder closure from Columbia Drive (MM 66.8) to Wesley Chapel Road (MM 69.5)
  • I-20 Eastbound (connecting lanes or CD lanes): Single to double, right- or left-lane and shoulder closure from I-285 Interchange (MM 67.3) to Wesley Chapel Road (MM 69.5)
  • I-20 Eastbound: Single to double, right- or left-lane and shoulder closure from Wesley Chapel Road (MM 69.5) to Panola Road (MM 71.3)
  • I-20 Eastbound to I-285 Northbound: Single, right- or left-lane, closure

Friday, August 21, through Friday, August 28, from 8 p.m. to 6 a.m.
  • I-285 Southbound: Single to double, right-lane and shoulder closures from Glenwood Road (MM 44.5) to interchange (MM 45.5)
  • I-285 Southbound: Single to double, left- or right-lane closure from interchange (MM 46.5) to Columbia Drive (MM 47.4)
  • I-285 Northbound: Single to double, left- or right-lanes and shoulder closure from interchange (MM 44.4) to Glenwood Road (MM 44.5)
  • I-285 Northbound: Single to double, left-, or right-lanes and shoulder closure from Columbia Drive (MM 47.2) to interchange (MM 47.4)

Friday, August 21, through Friday, August 28, from 9 p.m. to 6 a.m.
  • I-20 Westbound: Single to double, right- or left-lane closure from Fairington Road overpass to Panola Road (MM 71.3)
  • I-20 Westbound: Alternating, single to double, left- and right-lane and shoulder closure from Panola Road (MM 71.4) to Wesley Chapel Road (MM 68.5)
  • I-20 Westbound: Single to double, left-lane closure from Wesley Chapel Road (MM 69.5) to Columbia Drive (MM 66.8)

Ramp Closure:
Friday, August 21, through Friday, August 28, from 8 p.m. to 6 a.m.
  • I-20 Eastbound to Wesley Chapel Road exit ramp: Temporary closure. Traffic will be directed to the Panola Road exit ramp onto I-20 westbound to access Wesley Chapel Road.

Weekend Continuous Lane Closure:
Friday, August 21, 9 p.m. through Monday, August 24, 5 a.m.
  • I-20 Westbound: Continuous closure of two alternating lanes on I-20 WB between Fairington Road and Wesley Chapel Road
Activity Start Date End Date Times
I-20 Eastbound
  • I-20 from Columbia Drive to Wesley Chapel
Single, right- or left-lane and shoulder closure August 21 August 28 9 a.m. - 2 p.m.
  • I-20 from Wesley Chapel Road to the Panola Road
Single, right-lane and shoulder closure August 21 August 28 9 a.m. - 2 p.m.
  • I-20 from Panola Road to Fairington Road
Single, right- or left-lane and shoulder closure August 21 August 28 9 a.m. - 2 p.m.
I-20 Eastbound
  • I-20 from Columbia Drive to Wesley Chapel
Single to double, right- or left-lane and shoulder closure August 21 August 28 7 p.m. - 6 a.m.
  • I-20 connecting (CD) lanes from the I-285 Interchange to Wesley Chapel Road
Single to double, right- or left-lane
and shoulder closure
August 21 August 28 7 p.m. - 6 a.m.
  • I-20 Eastbound from Wesley Chapel to Panola
Single to double, right- or left-lane and shoulder closure August 21 August 28 7 p.m. - 6 a.m.
  • I-20 Eastbound to I-285 Northbound
Single, right- or left-lane August 21 August 28 7 p.m. - 6 a.m.
  • I-20 Eastbound to Wesley Chapel Road exit ramp
Ramp closure August 21 August 28 8 p.m. to 6 a.m.
I-285 Southbound
  • I-285 Southbound from Glenwood Road to interchange
Single to double, and right-lane and shoulder closures;
Single to double, left- or right-lane closure
August 21 August 28 8 p.m. - 6 a.m.
  • I-285 Southbound from interchange to Columbia Drive
Single to double, left- or right-lane closure August 21 August 28 8 p.m. - 6 a.m.
I-285 Northbound
  • I-285 Northbound from interchange to Glenwood Road
Single to double, left- or right-lanes and shoulder closure August 21 August 28 8 p.m. - 6 a.m.
  • I-285 Northbound from Columbia Drive to the I-20 interchange
Single to double, left- or right-lanes and shoulder closure August 21 August 28 8 p.m. - 6 a.m.
I-20 Westbound
  • I-20 from Fairington Road overpass to Panola Road
Single to double, right- or left-lane closure August 21 August 28 9 p.m. - 6 a.m.
  • I-20 from Panola Road to Wesley Chapel Road
Single to double, left- or right-lanes and shoulder closure August 21 August 28 9 p.m. - 6 a.m.
  • I-20 from Wesley Chapel Road to Columbia Drive
Single to double, right- or left-lane closure August 21 August 28 9 p.m. - 6 a.m.
  • I-20 Westbound from Fairington Road to Wesley Chapel Road
Alternating, double, right- or left-lane closure August 21 August 24 9 p.m. - 5 a.m.
Flagging Operation
  • Miller Road over I-20
Flagging operation August 21 August 28 9 a.m. - 4 p.m.
  • Fairington Road
Flagging operation August 21 August 28 9 a.m. - 4 p.m.
Advisory: Exact time may change due to weather conditions. Motorists are advised to expect delays, exercise caution, and reduce their speed while traveling through work zones, stay alert, and watch for workers. Before heading out, get real-time information on work status and traffic conditions. Call 511, visit 511ga.org, or download the Georgia 511 app.
Follow Us
Like Us
Visit Us
See Us
Watch Us
The information you provide to the Georgia Department of Transportation will be used solely by GDOT. The Department does not sell or offer a subscriber's personal information to third parties for marketing purposes. To no longer receive this e-news letter, please select "unsubscribe from this list" below.
Copyright © 2026 Georgia Department of Transportation, All rights reserved.

Our mailing address is:
Georgia Department of Transportation
Office of Communications
600 West Peachtree Street N.W.
Atlanta, GA 30308

Want to change how you receive these emails?
You can update your preferences or unsubscribe from this list
Georgia Department of Transportation published this content on August 21, 2026, and is solely responsible for the information contained herein. Distributed via Public Technologies (PUBT), unedited and unaltered, on August 22, 2026 at 08:20 UTC. If you believe the information included in the content is inaccurate or outdated and requires editing or removal, please contact us at [email protected]