Uranium Energy Corp.

03/10/2026 | Press release | Distributed by Public on 03/10/2026 15:01

Uranium Energy Corp Reports Results for Second Quarter of Fiscal 2026 (Form 8-K)

Uranium Energy Corp Reports Results for Second Quarter of Fiscal 2026

Uranium Sales at $101 per Pound - Demonstrating the Strength of UEC's Unhedged Strategy

$818 Million of Liquid Assets, and No Debt(1)

Advancing the Largest U.S. Uranium Resource Base, Providing Multi-Decade Production Scalability Aligned with U.S. Policy Support and Anticipated Structural Supply Deficits

Building America's Only Vertically Integrated Uranium Fuel Supply Chain from Mining to Refining and Conversion

Fiscal Q2 2026 Operational Highlights:

New Uranium Production Capacity Constructed in Wyoming and Texas: Four new field-tested header houses were completed at Christensen Ranch in-situ recovery ("ISR") operations, and construction of Burke Hollow ISR project was finalized, positioning both for scalable production growth. Expansion is ready for operations pending regulatory approvals.

Maintaining Low-Cost Production Profile: During the second fiscal quarter of 2026, 45,743 pounds of uranium concentrate was produced at a Total Cost per Pound(2) of $44.14 (Cash Cost per Pound(2) $39.66), driven by only two active header houses at Christensen Ranch. Since commissioning, Total Cost per Pound(2) has been $37.28, including Cash Cost per Pound(2) of $30.52 across 244,321 pounds, highlighting sustained operational efficiency.

Burke Hollow ISR Project is Operationally Ready: Completed construction of America's newest ISR production facility. The Texas team is preparing for startup, awaiting the state regulator's final approval of the Drilling and Completion Report for the waste disposal well as per standard protocol in starting a new ISR operation.

Christensen Ranch Expansion Expected to Deliver Scalable Production: The majority of production has been from two active header houses. Four new header houses have been completed and three additional header houses are being constructed, with production expected to commence on receipt of state regulatory approval.

Irigaray Plant Fully Optimized - Started 24/7 Operations: A full refurbishment of the calciner was completed allowing the start of 24/7 operations at the Irigaray Central Processing Plant ("CPP"). Accordingly, drying and drumming of in-process inventory has resumed during the quarter.

Expediting Development at Third New ISR Uranium Project: Delineation drilling continued at the fully permitted Ludeman ISR Project's first wellfield, supporting multiple header houses. Engineering of the satellite ion-exchange plant and manufacturing of ion-exchange vessels is progressing.

Accelerating Plans for Sweetwater including First Wellfield Development: A 200-hole delineation drilling program on the first wellfield at Sweetwater commenced on March 2, 2026. Engineering for mill refurbishment has been initiated. Installation of 23 cased monitor wells and the coring program for advanced metallurgical testing was completed during the quarter.

Roughrider Pre-Feasibility Progressing: Core drilling is over 30% complete to support the pre-feasibility study ("PFS") for the world class Roughrider Project in the Athabasca Basin of Saskatchewan, Canada. At the same time, UEC is working with SaskPower towards a Definition Phase Agreement for a high-voltage power connection to the project.

United States Uranium Refining & Conversion Corp ("UR&C"): To support an expedited plan, various work tracts intensified, including government discussions, the feasibility study with Fluor Corporation ("Fluor"), expansion of the size of the project technical and licensing teams, and a siting study.

Fiscal Q2 2026 Financial Highlights:

Robust Balance Sheet: $818 million in liquid assets(1), including cash of $486 million, with no debt at quarter-end.

Demonstrated Strength of Unhedged Strategy: Sales at $101 per pound, substantially above the average uranium spot price of $80.76 per pound(3) for the quarter, resulting in revenue of $20.2 million and gross profit of $10.0 million from the sales of 200,000 pounds U₃O₈ from UEC's physical portfolio.

Strong Inventory Position: 1,456,000 pounds of U₃O₈ at January 31, 2026, valued at $144 million at market prices(1), excluding 244,321 pounds of precipitated uranium and dried and drummed U3O8 at the Irigaray CPP.

U.S. Uranium Policy Developments:

Presidential Proclamation - Section 232 Critical Minerals Investigation: On January 14, 2026, President Trump issued a Presidential Proclamation directing negotiations under Section 232 to address national security risks associated with imports of processed critical minerals and their derivative products, including uranium. The investigation concluded that the U.S. is overly reliant on foreign processing capacity and lacks secure domestic supply chains following ore extraction, including conversion into oxide concentrates and metal forms.

Uranium was formally added to the U.S. Geological Survey Critical Minerals List in November 2025 and is explicitly covered by the investigation. Negotiators are tasked with pursuing supply chain agreements, including potential minimum import price mechanisms, with a status report due July 13, 2026, after which additional trade remedy measures may be considered.

Corpus Christi, TX, March 10, 2026 - Uranium Energy Corp (NYSE American: UEC, the "Company" or "UEC") is pleased to announce that it has filed its Quarterly Report on Form 10-Q for the quarter ended January 31, 2026.

Amir Adnani, President and CEO, stated:

"This quarter we reached a significant milestone for UEC with completing the construction of Burke Hollow, the newest ISR uranium mine in the U.S. We are very proud of our team, many of whom have been involved in this project since its discovery in 2012.

We expanded our ISR production capacity in Wyoming and South Texas, which are awaiting final regulatory approvals. With the unprecedented growth in the sector, our industry is experiencing regulatory growing pains. This level of activity has not been seen in the U.S. in over fifteen years. A coordinated industry working group has been established to engage constructively with state regulators to support responsible and timely production expansion approvals. UEC is actively involved in advancing these collaborative efforts while maintaining our commitment to operational excellence and environmental stewardship.

In parallel, we ramped up efforts on feasibility, siting and licensing at United States Uranium Refining & Conversion Corp, positioning UEC to address the national security gap in America's nuclear fuel supply chain. Our objective remains clear: to build the only vertically integrated U.S. nuclear fuel supply chain platform with uranium mining to domestic conversion capability.

During the quarter, we sold uranium at pricing over 25% of the quarterly average, which demonstrates the advantage of our unhedged approach to inventory management in a strengthening uranium market.

With $818 million in liquid assets(1) and no debt at the end of the quarter, UEC maintains one of the strongest balance sheets in the sector. Combined with the largest uranium resource base in the United States, we are uniquely positioned to scale production and respond quickly to evolving U.S. policy initiatives, including potential Section 232 remedies and long-term national security procurement requirements."

Powder River Basin, Wyoming, Hub-and-Spoke ISR Operations

Hub: Irigaray CPP; Spokes: Christensen Ranch and Ludeman

As of January 31, 2026, accumulated production from Christensen Ranch was approximately 244,000 pounds of precipitated uranium and dried and drummed U3O8 at the Irigaray CPP resulting in Total Cost per Pound(2) at $37.28, including Cash Cost per Pound(2) of $30.52.

UEC continued to develop new production areas at Christensen Ranch during the quarter. Delineation drilling expanded in wellfield 12 and 8 and 10-extensions. Mine development advanced further with well installation in wellfield 10-extension and 12, as well as installation of the monitor well ring in wellfield 10-extension. Additionally, construction was completed on four new header houses in wellfield 11, with three additional header houses being installed in wellfield 12 and 10-extension.

In parallel with activities at the Christensen Ranch mine, process upgrades at the Irigaray CPP continued in the second quarter of fiscal 2026, including refurbishment of the calciner to increase throughput of dried yellowcake. Updates included components as recommended by the manufacturer to increase operational efficiency. As a result, drying and packaging is now running with 24/7, two shift operations.

At Ludeman, the Company's third new ISR project located 10 miles northeast of Glenrock, Wyoming, delineation drilling was ~80% completed at the end of the fiscal quarter. This work will assist wellfield pattern design currently underway.

South Texas Hub-and-Spoke ISR Operations

Hub: Hobson CPP; Spoke: Burke Hollow

A major milestone was achieved with the construction completion of Burke Hollow. Drilling, casing, and underreaming of wells in the initial production area within the first wellfield is complete. The wellfield is comprised of 129 injection and recovery wells that have been tested for mechanical integrity and will provide initial feed to the ion-exchange ("IX") plant.

The buildout of the satellite IX plant, including IX columns, IX resin, and water treatment systems with an overall capacity of 2,500 gallons per minute was completed. IX is a filtration system which removes liquid uranium from groundwater before it is dried and processed into U3O8 at the Hobson CPP. Additionally, all bulk chemicals including oxygen, carbon dioxide, and others have been delivered in preparation for startup of UEC's hub and spoke operations in South Texas.

In December 2025 the Drilling and Completion Report for the waste disposal well was submitted to the Texas Commission on Environmental Quality ("TCEQ") for their review. The waste disposal well will facilitate production operations, as well as restoration at the completion of mining activities.

As the TCEQ completes its review, which is standard procedure for commencing a new ISR operation, UEC has carried out pre-operational inspections of the wellfield, IX plant, and disposal well. With the increased level of industry activity, there is regulatory backlog, which has led to slower than normal review times for submissions. To further improve the efficiency of startup, the Company has continued with training for key operational processes.

Sweetwater, Wyoming, Hub-and-Spoke Development

Our first milestone in the FAST-41 process was completed in the second fiscal quarter with the submission of the Sweetwater Plan of Operations for ISR operations to the Bureau of Land Management ("BLM") on November 14, 2025. BLM finalized their completeness review of the submission on March 3, 2026, the second milestone in the FAST-41 process. The next steps are meetings with BLM to determine the level of National Environmental Policy Act review that will be necessary for final approval of the project on federal lands.

The installation of 23 cased monitor wells and the coring program for advanced metallurgical testing was completed during the quarter. We commenced a 200-hole delineation drilling program in the first wellfield at Sweetwater on March 2, 2026.

Wood Group has been engaged to conduct the assessment of refurbishment requirements for the Sweetwater Plant for both conventional and ISR operations. Wood commenced this work on March 2, 2026.

Roughrider Project, Saskatchewan

As part of the Pre-Feasibility Study, UEC started a 34,000-meter conversion core drilling program, including targets across the West Zone, East Zone and Far East Zone, aiming to convert inferred estimated resources into the indicated category at the Roughrider Project. Of the planned drilling more than 30% has been completed.

UEC has engaged Tetra Tech Canada Inc. to provide lead technical services for the preparation of the PFS for the Roughrider Project. Key trade-off studies, including the proposed mine access have been completed and are in alignment with the Initial Assessment study completed in November 2024. Concurrently, UEC is working with SaskPower towards a Definition Phase Agreement for a high-voltage power connection to the Roughrider Project.

The Company continues to advance Roughrider through technical and environmental studies, community engagement and assessing opportunities to further de-risk the project. The processes of updating the environmental baseline work and Indigenous engagement should support a future Environmental Impact Assessment required for uranium production.

United States Uranium Refining & Conversion Corp

During the quarter, UR&C, a wholly owned subsidiary of UEC, progressed a feasibility study with its contractor, Fluor for a state-of-the-art American uranium refining and conversion facility.

In support of the feasibility study, a detailed siting study was initiated for the planned facility, and the review of various sites across the U.S. is underway. All sites are undergoing a rigorous evaluation with respect to site and civil characteristics, environment and permitting requirements, logistics, utility infrastructure, and the available workforce.

Several key technical personnel were added to the UR&C team, as well as Fluor's engineering team. Additionally, Fluor began preparing for licensing of the facility with the placement of key licensing and permitting personnel.

Conference Call Details

A conference call will be held at 11:00 a.m. ET (8:00 a.m. PT) on Tuesday, March 10, 2026, to discuss the Company's results, upcoming catalysts and current market conditions. To participate, please use one of the following methods:

Webinar: Click Here

North America (toll-free): 1-877-270-2148

International: 1-412-902-6510

An accompanying presentation will be available on UEC's website at www.uraniumenergy.com and a replay of the event will be available following the presentation.

Uranium Energy Corp. published this content on March 10, 2026, and is solely responsible for the information contained herein. Distributed via EDGAR on March 10, 2026 at 21:01 UTC. If you believe the information included in the content is inaccurate or outdated and requires editing or removal, please contact us at [email protected]