10/15/2025 | Press release | Distributed by Public on 10/15/2025 10:36
For Immediate Release:
Wednesday, Oct. 15, 2025
Contact:
Matthew Glines, Project Engineer, 605-220-6798
HARTFORD, S.D. - Beginning on Thursday, Oct. 16, 2025, traffic will be shifted onto the new pavement and bridge on Western Avenue over Interstate 90 at exit 387 (Hartford), marking the completion of phase one of construction. Two lanes of traffic will remain open on the new pavement on Western Avenue with a 10-foot width restriction in place. A temporary westbound off-ramp will be utilized during construction of the permanent off-ramp.
Phase two construction will begin immediately and will include building the second half of the bridge and Western Avenue. Work will continue through the fall and winter as weather allows.
In addition, overnight closures are scheduled to take place on I-90 for bridge removal work:
The prime contractor for this $12.6 million project is D & G Concrete Construction Inc. of Sioux Falls, S.D. The overall project completion date is June 2026.
Construction Project Page:
Find the latest information on the project website at https://dot.sd.gov/projects-studies/construction-projects/interstate-90-exit-387-hartford.
Sign Up for Text Notifications:
For updates on major traffic changes, subscribe to a free text-in service. To subscribe, simply text the keyword I90Exit387 to 605-566-4041. Subscribers can unsubscribe at any time.
About SDDOT:
The mission of the South Dakota Department of Transportation is to provide a safe and efficient public transportation system.
For the latest on road and weather conditions, road closures, construction work zones, commercial vehicle restrictions, and traffic incidents, please visit https://sd511.org or dial 511.
Read more about the innovative work of the SDDOT at https://dot.sd.gov.
-30-