Weekly Lane Closure Advisory on the I-285/I-20 West Interchange Project.

For Immediate Release
Friday, May 2, 2025
Contact:
mediarequests@dot.ga.gov
Cobb, Douglas, and Fulton Counties
Interstate Lane Closure Advisory for the I-285/I-20 West Interchange Project
Weather permitting, the Georgia Department of Transportation (Georgia DOT) and its construction partners will temporarily close interstate lanes for geotechnical boring. They will also conduct rolling lane closures with police and a crash truck on weeknights at the following locations to install signage on the median wall of the I-285/I-20 West Interchange project.

This project will reconstruct and widen several interstate system-to-system ramps at the I-285/I-20 West Interchange and add a combination of collector-distributor lanes or connecting lanes, and auxiliary lanes along I-20 west and I-285 north of the interchange.

WHEN/WHERE:

Weekend Nighttime Closures

Saturday, May 3, through Sunday, May 4, 9 p.m. to 11 p.m. (Nightly)
Single, left-lane, and left-shoulder closure at the following location:
  • I-285 northbound from State Route (SR) 139/Martin Luther King Jr. Drive (mile marker (MM) 9.2) to the I-20 Interchange (MM 10.1)
Saturday, May 3, through Sunday, May 4, 11 p.m. to 7 a.m. (Nightly)
Double, left-lane, and left-shoulder closure at the following location:
  • I-285 northbound from SR139/Martin Luther King Jr. Drive (MM 9.2) to the I-20 Interchange (MM 10.1)
Weeknight Closures

Monday, May 5, through Tuesday, May 6, 9 p.m. to 11 p.m. (Nightly)
Single, left-lane, and left-shoulder closure at the following location:
  • I-285 northbound from SR 139/Martin Luther King Jr. Drive (MM 9.2) to the I-20 Interchange (MM 10.1)
Monday, May 5, through Tuesday, May 6, 11 p.m. to 5 a.m. (Nightly)
Double, left-lane, and left-shoulder closure at the following location:
  • I-285 northbound from SR 139/Martin Luther King Jr. Drive (MM 9.2) to the I-20 Interchange (MM 10.1)
Monday, May 5, through Thursday, May 8, 9 p.m. to 5 a.m. (Nightly)
Rolling left-lane closure at the following locations:
  • I-285 northbound from SR 154/166/Langford Parkway/Campbellton Road (MM 3.8) to Atlanta Road (MM 16.2)
  • I-285 southbound from South Atlanta Road (MM 16.2) to SR 154/166/Langford Parkway/Campbellton Road (MM 3.8)
  • I-20 eastbound from Lee Road (MM 42.5) to Joseph E. Lowery Boulevard (MM 54.4)
  • I-20 westbound from the McDaniel Street underpass (MM 56.2) to Thornton Road (MM 44.3)
Wednesday, May 7, 9 p.m. to 5 a.m.
Single right-lane and right shoulder closure at the following location:
  • SR 70/Fulton Industrial Boulevard northbound from Shirley Drive to Wendell Drive
Advisory: Exact time may change due to weather conditions. There may be intermittent traffic pacing and lane and ramp closures that occur within the work zone in addition to this notice. Motorists are advised to expect delays, exercise caution, and reduce their speed while traveling through work zones, stay alert, and watch for workers. Before heading out, get real-time information on work status and traffic conditions. Call 511, visit 511ga.org, or download the Georgia 511 app.

For additional project information, visit https://0013918-gdot.hub.arcgis.com/.
Follow Us
Like Us
Visit Us
See Us
Watch Us
The information you provide to the Georgia Department of Transportation will be used solely by GDOT. The Department does not sell or offer a subscriber's personal information to third parties for marketing purposes. To no longer receive this e-news letter, please select "unsubscribe from this list" below.
Copyright © 2025 Georgia Department of Transportation, All rights reserved.

Our mailing address is:
Georgia Department of Transportation
Office of Communications
600 West Peachtree Street N.W.
Atlanta, GA 30308

Want to change how you receive these emails?
You can update your preferences or unsubscribe from this list
Georgia Department of Transportation published this content on May 02, 2025, and is solely responsible for the information contained herein. Distributed via Public Technologies (PUBT), unedited and unaltered, on May 03, 2025 at 01:37 UTC. If you believe the information included in the content is inaccurate or outdated and requires editing or removal, please contact us at support@pubt.io