Earnings Release Highlights

- Commercialized AI infrastructure at scale, signing a 15-year, 245 MW IT lease with Fluidstack at the River Bend campus, representing $7.0 billion in base-term contract value.
- Refined portfolio structure and streamlined capital allocation framework through the sale of a 310 MW portfolio of four natural gas-fired power plants, which closed in February 2026, and the launch and public listing of American Bitcoin Corp., a majority-owned Bitcoin accumulation subsidiary.
- Reduced cost of capital and strengthened financial flexibility through capital formation initiatives including (i) a new $200 million revolving credit facility with Two Prime and the upsizing of the Coinbase revolving credit facility to $200 million, bringing total credit capacity to $400 million at a weighted average cost of capital of 8.5% and (ii) up to 85% loan-to-cost in project-level financing for River Bend, expected to be funded by J.P. Morgan as lead left loan underwriter and loan structurer, and Goldman Sachs & Co. LLC, both of whom are expected to serve as loan underwriters2.
- Designed and deployed next-generation data center architecture at Vega, a 205 MW Tier I data center featuring a proprietary, rack-based, direct-to-chip liquid cooling system that enables ASIC compute deployments at densities of up to 180 kilowatts per rack.

MIAMI, FL, February 25, 2026 - Hut 8 Corp. (Nasdaq, TSX: HUT) ("Hut 8" or the "Company"), an energy infrastructure platform integrating power, digital infrastructure, and compute at scale to fuel next-generation, energy-intensive use cases, today reported its financial results for the fourth quarter and full year of 2025.

Asher Genoot, CEO of Hut 8, said: "Over the past two years, we have rebuilt Hut 8 around a power-first strategy centered on high-velocity origination, disciplined greenfield development, first-principles infrastructure design, and capital-efficient execution. In 2025, this work translated into tangible growth and commercial progress across our platform."

"River Bend demonstrates the strength of our model and our ability to execute with blue-chip counterparties. As AI continues to drive incremental power demand, our focus is on converting this early success into a repeatable development flywheel: advancing projects across our multi-gigawatt pipeline to deliver stable and predictable long-term cash flows supported by creditworthy counterparties."

"2026 is about execution. We aim to advance River Bend for delivery beginning in Q2 2027 while accelerating conversion across our broader pipeline. With enhanced capital allocation clarity following the carveout of our legacy ASIC compute business and the sale of our 310-megawatt portfolio of power generation assets, we believe we are positioned to scale with greater discipline, compound long-term value for shareholders, and build an enduring, generational business at the intersection of energy and technology."

2025 Highlights

Power

- Generated $23.2 million in full-year revenue from Power Generation and Managed Services.
- Entered into a definitive share purchase agreement to sell the Company's 310 MW portfolio of natural gas-fired power plants in Ontario (the "Portfolio") to TransAlta Corporation, concluding a multi-phase program through which Hut 8 stabilized and strengthened the Portfolio following its acquisition out of bankruptcy, including the securing of five-year capacity contracts with the Ontario Independent Electricity System Operator. The Company intends to redeploy capital from the transaction, which closed in February 2026, for general corporate purposes, including the execution of the Company's data center development pipeline.
- Announced plans to develop four new sites with more than 1,500 MW of total capacity across the United States, including 330 MW of utility capacity at the Company's River Bend campus in Louisiana. The expansion positions the Company to meet growing demand from energy-intensive use cases while scaling and diversifying its platform across strategic energy markets.

Digital Infrastructure

- Generated $9.6 million in full-year revenue from Colocation services. An additional $57.3 million of Colocation revenue, including reimbursements, from the Company's share of the unconsolidated King Mountain Joint Venture is recognized in the "Equity in earnings of unconsolidated joint venture" line item.
- Launched a partnership with Anthropic and Fluidstack to accelerate the deployment of hyperscale AI infrastructure in the United States, under which Hut 8 will develop and deliver at least 245 MW and up to 2,295 MW of AI data center infrastructure.
- Signed a 15-year, $7.0 billion lease with Fluidstack for 245 MW of IT capacity at River Bend, with the lease payments and related pass-through obligations for the base term financially backstopped by Google. The agreement grants Fluidstack a Right of First Offer for up to an additional 1,000 MW of IT capacity at future expansion phases at River Bend, subject to the expansion of power at the site.
- Energized Vega, a 205 MW data center that commercializes a next-generation Tier 1 form factor for ASIC compute, featuring a proprietary, rack-based, direct-to-chip liquid cooling system designed by Hut 8 to support ASIC deployments at densities of up to 180 kilowatts ("kW") per rack.

Compute

- Generated $202.3 million in full-year revenue from ASIC Compute, primarily through the Company's majority-owned subsidiary, American Bitcoin Corp. ("American Bitcoin"); AI Cloud through the Company's wholly owned Highrise AI subsidiary; and Traditional Cloud solutions delivered under the Hut 8 Canada brand.
- Launched and completed the public listing of American Bitcoin, creating a dedicated, majority-owned Bitcoin accumulation vehicle that can scale independently and provide Hut 8 stockholders with long-term exposure to potential Bitcoin upside.

Capital Strategy and Balance Sheet

- Established a balance sheet and capital structure designed to support disciplined execution across the Company's development pipeline, providing the financial flexibility to advance projects while maintaining selectivity and capital efficiency. This foundation is supported by: (i) approximately $1.4 billion of cash and Bitcoin held in reserve as of December 31, 2025, including $899.3 million attributable to Hut 8 and $472.6 million attributable to American Bitcoin; (ii) the launch of a $1.0 billion at-the-market ("ATM") program; (iii) revolving credit facilities with Two Prime and Coinbase with up to $400 million of borrowing capacity at a weighted average cost of capital of 8.5%; and (iv) up to 85% loan-to-cost in project-level financing for River Bend, expected to be funded by J.P. Morgan (NYSE: JPM) as lead left loan underwriter and loan structurer, and Goldman Sachs & Co. LLC (NYSE: GS), both of whom are expected to serve as loan underwriters2.
- Deepened institutional alignment, supporting growth in institutional ownership from approximately 55% at year-end 2024 to approximately 70% at year-end 2025.

Development Pipeline

- Development pipeline totaling 8,500 MW1 as of December 31, 2025, including 5,185 MW of Energy Capacity Under Diligence, 1,755 MW1 of Energy Capacity Under Exclusivity, 1,230 MW of Energy Capacity Under Development, and 330 MW of Energy Capacity Under Construction.

Key Performance Indicators

As of

December 31,

​ ​ ​

2025

​ ​ ​

2024

Energy Capacity Under Diligence

5,185 MW

8,599 MW

Energy Capacity Under Exclusivity

1,755 MW1

2,768 MW

Energy Capacity Under Development

1,230 MW

- MW

Energy Capacity Under Construction

330 MW

205 MW

Energy Capacity Under Management(3)

1,020 MW

815 MW

1.

Excludes 1,000 MW of potential expansion capacity at River Bend (subject to the expansion of power at the site), for which Fluidstack holds a ROFO under the River Bend lease

2.

Subject to the negotiation and execution of definitive transaction agreements and customary closing conditions.

3.

Comprises all Power assets: Power Generation, Managed Services, Digital Infrastructure, ASIC Compute, Traditional Cloud, and non-operational sites

Select Fourth Quarter 2025 Financial Results

Revenue for the three months ended December 31, 2025 was $88.5 million, compared to $31.7 million in the prior year period, and consisted of $5.0 million in Power revenue, $1.6 million in Digital Infrastructure revenue, $81.9 million in Compute revenue, and nil in Other revenue. As American Bitcoin is a consolidated subsidiary, all revenue generated through our Managed Services agreement, ASIC Colocation agreement, and Shared Services agreement with American Bitcoin is eliminated in consolidation.

Net loss for the three months ended December 31, 2025 was $301.8 million, compared to net income of $152.0 million in the prior year period. Net loss for the period included $401.9 million of primarily unrealized losses on digital assets, compared to $308.2 million of primarily unrealized gains on digital assets in the prior year period.

Adjusted EBITDA for the three months ended December 31, 2025 was $(347.8) million, compared to $310.6 million in the prior year period. Adjusted EBITDA for each period includes the impact of the gains and losses on digital assets described above. A reconciliation of Adjusted EBITDA to the most comparable GAAP measure, net income, and an explanation of this measure has been provided in the table included below in this press release.

Select Full Year 2025 Financial Results

Revenue for the twelve months ended December 31, 2025 was $235.1 million, compared to $162.4 million in the prior year period, and consisted of $23.2 million in Power revenue, $9.6 million in Digital Infrastructure revenue, $202.3 million in Compute revenue, and nil in Other revenue. As American Bitcoin is a consolidated subsidiary, all revenue generated through our Managed Services agreement, ASIC Colocation agreement, and Shared Services agreement with American Bitcoin is eliminated in consolidation.

Net loss for the twelve months ended December 31, 2025 was $248.0 million, compared to net income of $331.4 million in the prior year period. Net loss for the period included $220.0 million of primarily unrealized losses on digital assets, compared to $509.3 million of primarily unrealized gains on digital assets in the prior year period.

Adjusted EBITDA for the twelve months ended December 31, 2025 was $(135.4) million, compared to $555.7 million in the prior year period. Adjusted EBITDA for each period includes the impact of the primarily unrealized gains and losses on digital assets described above. A reconciliation of Adjusted EBITDA to the most comparable GAAP measure, net income, and an explanation of this measure has been provided in the table included below in this press release.

All financial results are reported in U.S. dollars.

Conference Call

The Company will host a conference call and webcast to review the results today at 8:30 a.m. ET. To register for the webcast, use the following link: https://app.webinar.net/DlYvdNZd4aN.

Supplemental Materials and Upcoming Communications

The Company expects to make available on its website materials designed to accompany the discussion of its results, along with certain supplemental financial information and other data. For important news and information regarding the Company, including investor presentations and timing of future investor conferences, visit the Investor Relations section of the Company's website, hut8.com/investors, and its social media accounts, including on X and LinkedIn. The Company uses its website and social media accounts as primary channels for disclosing key information to its investors, some of which may contain material and previously non-public information.

Analyst Coverage

A full list of Hut 8 Corp. analyst coverage can be found at hut8.com/investors/stock-info/.

About Hut 8

Hut 8 Corp. is an energy infrastructure platform integrating power, digital infrastructure, and compute at scale to fuel next-generation, energy-intensive use cases. We take a power-first, innovation-driven approach to developing, commercializing, and operating the critical infrastructure that underpins the breakthrough technologies of today and tomorrow. Our platform spans 710 megawatts of energy capacity under management, 330 megawatts of energy capacity under construction, and 1,230 megawatts of energy capacity under development across 15 sites in the United States and Canada: five ASIC compute, hosting, and Managed Services sites in Alberta, New York, and Texas; five cloud and colocation data centers in British Columbia and Ontario; one non-operational site in Alberta; one site under construction in Louisiana; and three sites under development across Texas and Illinois. For more information, visit hut8.com and follow us on X at @Hut8Corp.

Hut 8 Corp. published this content on February 25, 2026, and is solely responsible for the information contained herein. Distributed via EDGAR on February 25, 2026 at 11:40 UTC. If you believe the information included in the content is inaccurate or outdated and requires editing or removal, please contact us at [email protected]