Knife River Corporation Updates Progress on East Century Avenue Reconstruction

Dear Residents,

We would like to provide an update on the progress of the ongoing reconstruction of East Century Avenue.

Temporary Roadway

The temporary gravel roadway is expected to remain in place until approximately mid-August. We remind all travelers, both drivers and pedestrians, to continue following all traffic control signage and remain alert while navigating the work zone.

Underground Utilities

With the majority of watermain installation completed, crews are now focused on the new storm sewer. This work is currently underway near Roosevelt Drive and is progressing eastward at a steady pace.

East Century Ave

All underground utility work from the western project limit to just past Stonewall Drive is now complete. Base rock has been placed up to Patriot Drive, and concrete operations will begin in this section in the coming days.

Contact Information

For any inquiries or concerns regarding this project, please email Andrew Osborn or call 701-989-4959.

We understand that road construction can be disruptive to your daily routine, we appreciate your understanding and cooperation during this period of improvement. These enhancements aim to create a safer and more efficient transportation network for your community.

Sincerely,

Andrew Osborn

Public Relations Coordinator Knife River Corporation

City of Bismarck, ND published this content on June 23, 2025, and is solely responsible for the information contained herein. Distributed via Public Technologies (PUBT), unedited and unaltered, on June 23, 2025 at 16:51 UTC. If you believe the information included in the content is inaccurate or outdated and requires editing or removal, please contact us at [email protected]