09/21/2026 | Press release | Distributed by Public on 09/20/2026 18:12
GAYLORD, Mich. - The Michigan Department of Transportation (MDOT) will invest $297,311 to make repairs to the substructure and deck of the M-55 bridge over US-127 near Houghton Lake. Crews will return in spring 2027 to seal the concrete surfaces on the bridge.
County:
Roscommon
Highways:
M-55
US-127
Closest community:
Houghton Lake
Start date:
Thursday, Oct. 1, 2026
Estimated end date:
Sunday, Nov. 15, 2026
Traffic restrictions:
This work will require lane closures on M-55 with traffic shifts, as well as temporary closure of the westbound M-55 loop ramp to southbound US-127. During this ramp closure, westbound M-55 traffic will be permitted to turn left onto southbound US-127, just west of the loop ramps. The project will also require lane and shoulder closures on US-127.
Safety benefit:
This project will extend the service life and preserve the structural integrity of this bridge.