What: Weather permitting, the Georgia Department of Transportation (Georgia DOT) construction partners will temporarily close interstate lanes at the locations below for the I-285/I-20 East Interchange project. The project will reconstruct the interstate system-to-system ramps at the I-285/I-20 East Interchange and add a combination of collector-distributor (CD), or connecting lanes, and auxiliary lanes along I-20 east of the interchange and I-285 north of the interchange.
Where/When: Traffic impacts on the I-285/I-20 Interchange project from Friday, February 6, 2026, through Friday, February 13, 2026.
DAYTIME CLOSURES:
Friday, February 6, through Friday, February 13, from 9 a.m. to 2 p.m.
-
I-20 Eastbound: Single, right- or left-lane and shoulder closure from Wesley Chapel Road (MM 69.5) to Panola Road (MM 71.3)
-
I-20 Eastbound: Single, right- or left-lane and shoulder closure from Columbia Drive (MM 66.8) to Wesley Chapel Road (MM 69.5)
-
I-20 Eastbound: (connecting lanes or CD lanes): Single, right- or left-lane and shoulder closure from I-285 Interchange (MM 67.3) to Wesley Chapel Road (MM 69.5)
Friday, February 6, through Friday, February 13, from9 a.m. to 4 p.m.
-
I-20 Westbound: Wesley Chapel exit ramp: Alternating, double, right- or left-lane closures & traffic pacing
Friday, February 6, through Friday, February 13, from9 a.m. to 4 p.m.
-
Hillandale Drive at DeKalb Medical Parkway: Flagging operation
Friday, February 6, through Friday, February 13, from 9 a.m. to 4 p.m.
-
Miller Road over I-20: Flagging operation
Friday, February 6, through Friday, February 13, from 9 a.m. to 4 p.m.
-
Chupp Way & Fairington Road: Flagging operation
OVERNIGHT CLOSURES AND TRAFFIC PACING:
Friday, February 6, through Friday, February 13, from 7 p.m. to 5 a.m.
-
I-20 Eastbound: Single to double, right- or left-lane and shoulder closure from Wesley Chapel Road (MM 69.5) to Panola Road (MM 71.3)
-
I-20 Eastbound (connecting lanes or CD lanes): Single to double, right- or left-lane and shoulder closure from I-285 Interchange (MM 67.3) to Wesley Chapel Road (MM 69.5)
-
I-20 Eastbound: Single to double, right- or left-lane and shoulder closure from Columbia Drive (MM 66.8) to Wesley Chapel Road (MM 69.5)
-
I-20 Eastbound to I-285 Northbound, single to double, right or left lane, left- and right-lane closure
-
I-20 Eastbound: Single, right-lane closure on Wesley Chapel off-ramp
-
I-20 Eastbound: Single to double, right- or left-lane closure from Panola Road (MM 71.3) to Fairington Road Overpass
Friday, February 6, through Friday, February 13, from 8p.m. to 5 a.m.
-
I-285 Southbound: Single to double, left- or right-lane closure from interchange to Columbia Drive
-
I-285 Southbound: Single to double, right-lane and shoulder closures from Glenwood to interchange
-
I-285 Northbound: Single to double, left- or right-lanes and shoulder closure from Columbia to interchange
-
I-285 Northbound: Single to double, left- or right-lanes and shoulder closure from interchange to Glenwood
Friday, February 6, through Friday, February 13, from 9 p.m. to 5 a.m.
-
I-20 Westbound: Single to double, left-lane closure from Wesley Chapel Road (MM 69.5) to Columbia Drive (MM 66.8)
-
I-20 Westbound: Alternating, single, left- and right-lane and shoulder closure from Panola Road (MM 71.4) to Wesley Chapel Road (MM 68.5)
-
I-20 Westbound: Single to double, right- or left-lane closure from Fairington Road Overpass to Panola Road (MM 71.3)
|
|
Activity
|
Start Date
|
End Date
|
Times
|
|
I-20 Westbound
|
-
I-20 from Panola Road to Wesley Chapel Road
|
Single to double, right- or left-lane and shoulder closures
|
February 6
|
February 13
|
9 p.m. - 5 a.m.
|
-
I-20 from Wesley Chapel to Columbia Drive
|
Single to double, left-lane closure
|
February 6
|
February 13
|
9 p.m. - 5 a.m.
|
-
I-20 Westbound closure from Fairington Road Overpass to Panola Road (MM 71.3)
|
Single to double, right- or left-lane closure
|
February 6
|
February 13
|
9 p.m. - 5 a.m.
|
|
I-20 Eastbound
|
-
I-20 from Wesley Chapel Road to the Panola Road
|
Single, right-lane and shoulder closure
|
February 6
|
February 13
|
9 a.m. - 2 p.m.
|
-
I-20 connecting (CD) lanes from the I-285 Interchange to Wesley Chapel Road
|
Single, right-lane and shoulder closure
|
February 6
|
February 13
|
9 a.m. - 2 p.m.
|
-
I-20 from Columbia Drive to Wesley Chapel
|
Single, right- or left-lane and shoulder closure
|
February 6
|
February 13
|
9 a.m. - 2 p.m.
|
-
I-20 from Wesley Chapel Road to Panola Road
|
Single to double, right-or left-lane and shoulder closure
|
February 6
|
February 13
|
7 p.m. - 5 a.m.
|
-
I-20 connecting (CD) lanes from the I-285 Interchange to Wesley Chapel Road
|
Single to double, right- or left-lane and shoulder closure
|
February 6
|
February 13
|
7 p.m. - 5 a.m.
|
-
I-20 Columbia Drive to Wesley Chapel Road
|
Single to double, right- and left-lane and shoulder closure
|
February 6
|
February 13
|
7 p.m. - 5 a.m.
|
-
I-20 From Wesley Chapel Road to Panola Road
|
Traffic shift in all eastbound lanes
|
February 6
|
February 13
|
7 p.m. - 5 a.m.
|
-
I-20 Eastbound to I-285 Northbound
|
Single to double, right or left lane, left- and right-lane closures
|
February 6
|
February 13
|
7 p.m. - 5 a.m.
|
-
I-20 Eastbound closure on Wesley Chapel off-ramp
|
Single, right-lane closure
|
February 6
|
February 13
|
8 p.m. - 5 a.m.
|
-
I-20 Eastbound closure from Panola Road (MM 71.3) to Fairington Road Overpass
|
Single to double, right- or left-lane closure
|
February 6
|
February 13
|
7 p.m. - 5 a.m.
|
|
I-285 Southbound
|
|
|
|
|
-
I-285 Southbound from interchange to Columbia Drive
|
Single to double, left- or right-lane closure
|
February 6
|
February 13
|
8 p.m. - 5 a.m.
|
-
From Glenwood Road to the I-20 Interchange
|
Single to double, and right-lane and shoulder closures
|
February 6
|
February 13
|
8 p.m. - 5 a.m.
|
|
I-285 Northbound
|
|
|
|
|
-
From Columbia Drive to the I-20 Interchange
|
Single to double, left- or right-lanes, and shoulder closure
|
February 6
|
February 13
|
8 p.m. - 5 a.m.
|
-
From interchange to Glenwood
|
Single to double, left- or right-lanes and shoulder closure
|
February 6
|
February 13
|
8 a.m. - 6 p.m.
|
|
Flagging/Pacing Operation
|
|
|
|
|
|
Miller Road over I-20
|
Flagging operation
|
February 6
|
February 13
|
9 a.m. - 4 p.m.
|
|
Hillandale Drive at DeKalb Medical Parkway
|
Flagging operation
|
February 6
|
February 13
|
9 a.m. - 4 p.m.
|
|
Chupp Way at Fairington Road
|
Flagging operation
|
February 6
|
February 13
|
9 a.m. - 4 p.m.
|
|
|
|
Advisory: Exact time may change due to weather conditions. Motorists are advised to expect delays, exercise caution, and reduce their speed while traveling through work zones, stay alert, and watch for workers. Before heading out, get real-time information on work status and traffic conditions. Call 511, visit 511ga.org, or download the Georgia 511 app.
|
|
|