09/18/2025 | Press release | Distributed by Public on 09/18/2025 09:51
Where: Missouri Route 171 at Missouri Route 96 in Jasper County west of Carthage
When: 7 a.m., Thursday, Sept. 25 through Friday, Sept. 26
What: Contractor crews pouring concrete for the deck of the new Route 96 bridge over Route 171
Traffic Impacts:
Weather and/or scheduling conflicts could alter the work schedule.
This work is part of the project to replace the Route 96 bridge over Route 171 with a new bridge that is slightly higher and 12 feet longer than the current bridge. The $2.8 million project is scheduled to be completed by November 19, 2025.
For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest
Follow MoDOT's Southwest District: Facebook | X | Instagram | YouTube
Take the Challenge! Buckle Up/Phone Down