Project: U.S. Route 160/Missouri Route 13/Missouri Route 248 Roundabout North of Reeds Spring
What: U.S. Route 160/Missouri Route 13/ Missouri Route 248 north of Reeds Spring traffic pattern changing to new roundabout configuration.
When: Work will begin at 7:00 pm Wednesday, May 14. Traffic will be in the new configuration by 6:00 am Thursday, May 15.
Details: U.S. Route 160/Missouri Route 13/ Missouri Route 248 north of Reeds Spring in new roundabout configuration as crews continue working on the next phase of the project.
Traffic Impacts:
Weather and/or construction delays will alter the work schedule.
Project Information:
Prime contractor: Capital Paving & Construction, Columbia.
Total project cost: $1.6 million.
Project completion date: June 19, 2025.
END
For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest