McKinney National Airport (TKI) is currently extending Runway 18/36 by 500 feet at the north end. Earthwork is underway to build up the grade, and wick drains are being installed to accelerate soil settlement. We anticipate a settlement period of approximately nine months before pavement construction can begin for the runway extension.
From February 2025 through August 2026, several operational changes will affect airport operations:
|
Runway 18 |
Runway 36 |
---|---|---|
TORA |
5,962' |
6,462' |
TODA |
5,962' |
6,462' |
ASDA |
6,462' |
6,462' |
LDA |
6,462' |
5,962' |
PPR Instructions:
Any aircraft departing RWY 18 needing more than 5,962 TORA/TODA can request an additional 1,000 ft north of the relocated threshold by calling 972-547-3430 at least 2 hours prior to their departure time.