Traffic Impacts Related to The I-285/I-20 West Interchange Project
|
|
Weather permitting, Georgia Department of Transportation (Georgia DOT) and its construction partners will temporarily close interstate lanes for geotechnical borings and utility location in preparation for upcoming construction, nightly at the following locations of the I-285/I-20 West Interchange project.
This project will reconstruct and widen several interstate, system-to-system ramps at the I-285/I-20 West Interchange and add a combination of collector-distributor lanes or connecting lanes, and auxiliary lanes along I-20 west and I-285 north of the interchange.
|
|
WHEN/WHERE:
Daytime Closures
Tuesday, July 22, through Thursday, July 24, 10:30 a.m. to 12 p.m. (Daily)
Traffic pacing operation at the following location:
-
I-285 southbound from South Cobb Drive (mile marker (MM) 14.8) to the I-20 Interchange (MM 10)
Nighttime Closures
Monday, July 21, through Friday, July 25, 7 p.m. to 6:30 a.m. (Nightly)
Single, right-lane, and right-shoulder closure at the following location:
-
Six Flags Parkway from Lee Industrial Boulevard (MM 0) to South Service Road (MM 1)
Monday, July 21, through Friday, July 25, 8 p.m. to 5 a.m. (Nightly)
Single, right-lane, and right-shoulder closure at the following locations:
-
Harwell Road from Collier Drive (MM 0) to Amhurst Drive (MM 1)
-
Delmar Lane from Arlington Drive (MM .05) to Harwell Road (MM 1.5)
-
Fairburn Road from Argus Circle (MM 1) to Fairlane Drive (MM 2)
-
Collier Drive from Harwell Road (MM 1) to Collier Court (MM 2)
Monday, July 21, through Friday, July 25, 8 p.m. to 5 a.m. (Nightly)
Single, right-lane, and right-shoulder closure at the following locations:
-
State Route (SR) 70/Fulton Industrial Boulevard southbound from Wendell Drive (MM 2) to Shirley Drive (MM 2.5)
-
SR 139/Martin Luther King Jr. Drive northbound from Old Gordon Road (MM 5) to Adamsville Drive (MM 6)
Monday, July 21, through Friday, July 25, 9 p.m. to 5 a.m. (Nightly)
Single, right-lane, and right-shoulder closure at the following locations:
-
I-20 westbound from the Anderson Avenue underpass (MM 53.6) to Riverside Parkway (MM 47)
-
I-285 southbound from US 278/State Route 8/Donald Lee Hollowell Parkway (MM 11.8) to SR 139/Martin Luther King Jr. Drive (MM 9.6)
-
I-285 northbound from Cascade Road (MM 7.2) to Bolton Road (MM 12.6)
Monday, July 21, through Friday, July 25, 9 p.m. to 5 a.m. (Nightly)
Alternating, single, right-lane, and right-shoulder closure, and single, left-lane, and left-shoulder closure at the following location:
-
I-20 eastbound from Riverside Parkway (MM 47) to the I-285 Interchange (MM 50.5)
Monday, July 21, through Friday, July 25, 11 p.m. to 5 a.m. (Nightly)
Double, right-lane, and right-shoulder closure at the following location:
-
I-20 eastbound from Riverside Parkway (MM 47) to the I-285 Interchange (MM 50.5)
|
|
|
Advisory: Exact time may change due to weather conditions. There may be intermittent traffic pacing and lane and ramp closures that occur within the work zone in addition to this notice. Motorists are advised to expect delays, exercise caution, reduce their speed while traveling through work zones, stay alert, and watch for workers. Before heading out, get real-time information on work status and traffic conditions. Call 511, visit 511ga.org, or download the Georgia 511 app.
|
|
|