07/17/2025 | News release | Distributed by Public on 07/17/2025 17:46
The Public Works department will begin asphalt improvements in the Green Meadows subdivision starting on Mon., July 21. The daily work will occur between the normal work hours of 8 a.m.-5 p.m. The purpose of the work is to create smoother, safer roads, enhance curb appeal, and extend the life of our neighborhood streets. The road work is anticipated to be completed within 3 weeks, but the timeline is subject to change.
Work will proceed in the following order:
1. Canada Wild
2. Old West Trail (portion)
3. Firebush Way
4. Feathergrass Drive (portion)
Residents should:
If you have any questions or concerns, please contact our Assistant Director of Public Works, Scott Smith, at 512 364-2762.