11/07/2024 | Press release | Distributed by Public on 11/07/2024 19:13
Published on November 7, 2024
The City of Huntsville hired Britt Demolition and Recycling, Inc., for the demolition of the former City Hall located at 308 Fountain Circle. City Hall relocated to its new location at 305 Fountain Circle in May.
The 240-day contract is $1,243,000.
The first 2-3 months of the project will focus on environmental abatement inside the building. There will be no impact on the annual Tinsel Trail in Big Spring Park or any other holiday activities in the park.
The building will be dismantled by mechanical means and will not be imploded. The former City Hall opened in 1965 and closed earlier this year.
The contractor will leave the site ready for the future Big Spring Park East Expansion project.