Roadway
|
Activity
|
Start Date
|
End Date
|
Times
|
|
|
I-285 Northbound
|
|
|
Cascade Road to Bolton Road
|
Single, right-lane, and right-shoulder closure
|
Monday, March 2
|
Saturday, March 7
|
9 p.m. - 5 a.m. Nightly
|
|
|
Cascade Road to Bolton Road
|
Double, right-lane, and right-shoulder closure
|
Monday, March 2
|
Saturday, March 7
|
11 p.m. - 5 a.m.
Nightly
|
|
|
I-285 Southbound
|
|
|
US 78/Donald Lee Hollowell Pkwy to SR 139/MLK Jr. Drive
|
Single, right-lane, and right-shoulder closure
|
Monday, March 2
|
Saturday, March 7
|
9 p.m. - 5 a.m.
Nightly
|
|
|
US 78/Donald Lee Hollowell Pkwy to SR 139/MLK Jr. Drive
|
Alternating, double, right-lane, and right-shoulder closure, and double, left-lane, and left-shoulder closure
|
Monday, March 2
|
Saturday, March 7
|
11 p.m. - 5 a.m.
Nightly
|
|
|
SR 280/South Cobb Drive to the I-20 Interchange
|
Pacing operation, all lanes and shoulders
|
Monday, March 2
|
Thursday, March 5
|
10:30 a.m. - 12 p.m. Daily
|
|
|
I-20 Westbound
|
|
|
Anderson Avenue underpass to Riverside Parkway
|
Single, left-lane, and left-shoulder closure
|
Monday, March 2
|
Friday, March 6
|
9 p.m. - 5 a.m. Nightly
|
|
|
Anderson Avenue underpass to Riverside Parkway
|
Double, left-lane, and left-shoulder closure
|
Monday, March 2
|
Friday, March 6
|
11 p.m. - 5 a.m. Nightly
|
|
|
Anderson Avenue underpass to Riverside Parkway
|
Pacing operation, all lanes and shoulders
|
Monday, March 2
|
Friday, March 6
|
11 p.m. - 5 a.m. Nightly
|
|
|
SR 139/MLK Jr. Drive to the I-285 Interchange
|
Pacing operation, all lanes and shoulders
|
Monday, March 2
|
Thursday, March 5
|
10:30 a.m. - 12 p.m. Daily
|
|
|
Ramp from I-285 southbound to I-20 westbound at Fairburn Road overpass
|
Single, right-lane, and right-shoulder closure
|
Monday, March 2
|
Friday, March 6
|
9 p.m. - 5 a.m. Nightly
|
|
|
I-20 Eastbound
|
|
|
Riverside Parkway to the I-285 Interchange
|
Single, right-lane, and right-shoulder closure
|
Monday, March 2
|
Saturday, March 7
|
9 p.m. - 5 a.m.
Nightly
|
|
|
Other Locations
|
|
|
SR 70/Fulton Industrial Boulevard SB from Wendell Drive to Shirley Drive
|
Single, right-lane, and right-shoulder closure
|
Monday, March 2
|
Saturday, March 7
|
8 p.m. - 5 a.m.
Nightly
|
|
|
SR 139/MLK Jr. Drive SB from Old Gordon Road to Adamsville Drive
|
Single, right-lane, and right-shoulder closure
|
Monday, March 2
|
Friday, March 6
|
8 p.m. - 5 a.m.
Nightly
|
|
|
ADVANCE NOTICE & DETOURS
|
|
I-20 Eastbound to I-285 Northbound ramp closure
|
Overnight closure and detour
Motorists traveling on I-20 eastbound will exit onto I-285 southbound (Exit 51A), continue to SR 139/Martin Luther King Jr. Drive (Exit 9), and enter I-285 northbound
|
Friday, March 13
|
Saturday, March 14
|
9 p.m. until 5 a.m.