BLOOMINGTON, IL - The City of Bloomington provides regular updates on resurfacing work throughout the construction season. The most recent update is included below.
For more information on roadwork in the City of Bloomington, visit https://www.bloomingtonstreets.com, e-mail [email protected] or call 309-434-2225 during regular business hours. Residents can also sign up for e-mail or text updates for Bloomington Streets by visiting https://www.bloomingtonil.gov/subscribe and subscribing to Bloomington Streets.
FY24 Resurfacing (Phase 2)
Lake Dr, Summit to Tanner
-
Installation of the speed hump has been completed
-
Pavement striping for the speed hump has been scheduled
Colton Ave, Empire to Emerson
-
Installation of the 3 speed humps has been completed
-
Pavement striping for the 3 speed humps has been scheduled
FY25 Resurfacing
G.E. (General Electric) Rd, west of Hershey to Towanda Barnes
Stage 1: (west of Hershey to Airport)
-
Removal of the concrete surface (milling) for all eastbound and westbound lanes has been completed
-
Pavement removal for concrete patches and joint repairs has been completed
-
Installation of the asphalt binder course for all eastbound and westbound lanes has been completed
-
Installation and final adjustment of the underground utility castings has been completed
Stage 2: (Airport to Towanda Barnes)
-
Installation of Pipe Underdrain along Constitution Trail, between Airport Rd. and Crimson Ln., has been completed
-
Removal of the concrete surface (milling) for all eastbound and westbound lanes has been completed
-
Pavement removal for concrete patches and joint repairs for all eastbound and westbound lanes has been completed
-
Installation of the asphalt binder course for all eastbound and westbound lanes has been completed
-
Installation and final adjustment of the underground utility castings has been scheduled for the week of July 7
Fort Jesse Rd, Hershey to Kaisner
Stage 1: (Hershey to Airport)
-
Removal and replacement of the storm sewer inlets has been completed
-
Removal and replacement of the concrete items (curb & gutter and ADA ramps) has been completed
-
Removal of the concrete surface (milling) has been scheduled for the week of July 7
Stage 2: (Airport to Kaisner)
-
Removal and replacement of the storm sewer inlets has been completed
-
Removal and replacement of the concrete items (curb & gutter and ADA ramps) is in progress
-
Removal of the concrete surface (milling) has been scheduled for the week of July 7
Ridgewood Terrace, Main to the cul-de-sac
-
Removal and replacement of the concrete items (curb & gutter) has been scheduled to start the week of July 7th
-
Removal of the underground utility castings has been scheduled
FY26 Resurfacing
E. Oakland Ave, west of Prospect through Hershey
-
Removal and replacement of the storm sewer inlets is in progress
-
Removal and replacement of the concrete items (curb & gutter and ADA ramps) is in progress
-
Removal of the underground utility castings has been scheduled
Prospect Rd, Oakland to Empire
Stage 1: (Oakland to Washington)
-
The limits and layout of the work zone has been requested
Contact: Katherine Murphy Communications & External Affairs Mgr. Phone: Desk: 309-434-2241 Cell: 309-434-8546 Email: [email protected]
Contact: Jim Karch Director of Engineering Phone: 309-434-2225 E-mail: [email protected]