Bangladesh’s Rooppur begins supplying nuclear electricity to grid

State-owned Power Grid Bangladesh, which is the South Asian nation's only distributor of electric power, reported that Unit 1 of the Rooppur nuclear power plant fed electricity into the grid for the first time on Tuesday, November 17, with the initial output reaching 350 MW and lasting between 8 and 10 hours.

The occasion was marked by Bangladesh's minister of science and technology, Fakir Mahbub Anam, who spoke to reporters at the site, on the Padma River in Ishwardi Upazila, about 100 miles northwest of Dhaka. He announced, "We have become the 33rd country in the world to produce and generate nuclear power."

Test runs and safety checks: The steps taken November 17 were test run for grid synchronization for Bangladesh's first nuclear power plant, providing an opportunity for an engineering check of voltage, frequency, the turbine, and other systems before commercial operations begin.

Tests and safety checks will continue at various capacity levels during the next several months, according to the plant's managing director, Zahedul Hasan. Following these checks-if results are determined to be satisfactory-the Rooppur facility will require approval from the Bangladesh Atomic Energy Regulatory Authority before the next phase of operational trials can proceed.

Rooppur timeline: The Russian-built and -financed facility houses two VVER-1200s, each designed to generate 1,200 MW. Russia and Bangladesh signed an agreement in 2011 to build the plant, followed by a formal contract in 2015, However, plans for a nuclear power plant at Rooppur date as far back as the early 1960s.

Construction of the first unit at Rooppur began in 2017, and construction of the second unit began the following year. The first unit achieved criticality this past October. It is expected to reach full capacity early next year and to begin commercial operations after about 10 months of trial runs. At that point, Rooppur-1 will be operated by Nuclear Power Plant Company Bangladesh Ltd., taking over from the Russian contractor, Rosatom subsidiary Atomstroyexport.

Fuel loading of Rooppur-2 is expected to be complete by June 2027.

ANS - American Nuclear Society published this content on November 19, 2026, and is solely responsible for the information contained herein. Distributed via Public Technologies (PUBT), unedited and unaltered, on November 19, 2026 at 14:21 UTC. If you believe the information included in the content is inaccurate or outdated and requires editing or removal, please contact us at [email protected]