Public Works Update - February 2026

Public Works Update - February 2026

Published on March 24, 2026

Here are the updates on publics works projects and initiatives for February 2026!

By the Numbers

  • 38.2 Tons of trash removed
  • 50 Trees trimmed
  • 1459 Potholes filled
  • 2080 square feet of sidewalks
  • 70,400 feet of sewer lines cleaned
  • 160 Lineal feet of curb and gutter
  • 108 Tons of asphalt
  • 178 Vehicles serviced
  • 60 Encroachment permits
  • 2 Miles of streetlights repaired
  • 1,849 parking citations issued

Project Updates

  • Boronda Road - under construction; completion date fall 2026
  • Garner Pacific - Construction to start in March
  • 2025 Sidewalk project - Under construction; completion April
  • 2026 Sidewalk project - In design; bidding April
  • 2026 Pavement project - In design complete; bidding June
  • Abbott sewer project - In design; bidding April
  • Lake Street Pump Station - Request for Proposals issued
  • Sanitary Sewer Spot Repairs - Under construction; completion April
  • Solar Panels Police Department - Under construction; completion March
  • Gas Line relocation City Hall - Under construction; completion April; peding information from PG&E
  • Sherwood Recreation Center - Under construction; Completion June
City of Salinas, CA published this content on March 24, 2026, and is solely responsible for the information contained herein. Distributed via Public Technologies (PUBT), unedited and unaltered, on March 24, 2026 at 21:28 UTC. If you believe the information included in the content is inaccurate or outdated and requires editing or removal, please contact us at [email protected]