Board-approved rule change, a new project-tracking portal, earlier meter approvals, and more flexible construction staging aim are part of sweeping changes to lower costs and shorten timelines for projects across Los Angeles.
LOS ANGELES (October 30, 2026) - Six months after Mayor Karen Bass issued Executive Directive 19 (ED 19) for City departments to streamline development services and support housing production, the Los Angeles Department of Water and Power (LADWP) is reporting significant progress on five major reforms designed to reduce costs and speed utility connections for new development.
The improvements include a Board-approved change that will have LADWP cover the cost of most underground power line extensions serving new development, the launch of the Power Connect customer portal, early conditional meter spot approvals, more flexible construction staging standards, and the creation of a builder advisory group. Together, these measures are expected to save customers millions of dollars, unlock property value, and shorten project timelines by three to six months.
Among the key measures that LADWP has delivered in the six months since Mayor Bass issued ED 19 are:
"Executive Directive 19 laid out a clear roadmap for transforming how LADWP approves and energizes new connections, directly supporting affordable housing, electrification, and economic development," said Allan Marks, President of the Board of Water and Power Commissioners. "We've listened to customers, builders and contractors about specific improvements they've long wanted to see. Today's progress shows that LADWP is delivering on those commitments with speed and effectiveness. These tangible changes are already yielding results in how we work with the building community to get things done for Los Angeles."
"We moved quickly to make lasting changes to how we connect new customers, and we're not stopping here," said LADWP Interim General Manager David W. Hanson. "There is more work to do, and we are committed to an efficient, modern process that serves builders, developers, and Los Angeles as a whole."
Since April, LADWP has also accomplished the following:
LADWP is already seeing projects move through the process more efficiently with a 10 percent reduction in late project totals compared to our 2026 peak. A backlog remains, and the Department is continuing to overhaul its New Business process end to end.
The improvements also support the city's clean energy goals. Faster, more affordable connections make it easier to add solar, energy storage, and EV charging across Los Angeles.
For more information, see LADWP.com/ED19.