Traffic Impacts Related to The I-285/I-20 West Interchange Project
|
|
This project will reconstruct and widen several interstate, system-to-system ramps at the I-285/I-20 West Interchange and add a combination of collector-distributor (CD) lanes or connecting lanes and auxiliary lanes along I-20 west and I-285 north of the interchange.
What: Weather permitting, the Georgia Department of Transportation (Georgia DOT) contractors will temporarily close traffic lanes at the areas identified below to perform roadwork activities on the I-285/I-20 West Interchange project.
|
|
Lane Closure(s)
|
Roadway
|
Activity
|
Start Date
|
End Date
|
Times
|
|
I-285 Northbound
|
|
Cascade Road to Bolton Road
|
Alternating, single, left-lane, and left-shoulder closure, and single, right-lane, and right-shoulder closure
|
Monday, October 5
|
Monday, October 12
|
9 p.m. - 5 a.m. Nightly
|
|
Cascade Road to Bolton Road
|
Alternating, double, left-lane, and left-shoulder closure, and double, right-lane, and right-shoulder closure
|
Monday, October 5
|
Monday, October 12
|
11 p.m. - 5 a.m.
Nightly
|
|
I-285 Southbound
|
|
US 78/Donald Lee Hollowell Pkwy to SR 139/MLK Jr. Drive
|
Alternating, single, left-lane, and left-shoulder closure, and single, right-lane, and right-shoulder closure
|
Monday, October 5
|
Monday, October 12
|
9 p.m. - 5 a.m.
Nightly
|
|
US 78/Donald Lee Hollowell Pkwy to SR 139/MLK Jr. Drive
|
Alternating, double, left-lane, and left-shoulder closure, and double, right-lane, and right-shoulder closure
|
Monday, October 5
|
Monday, October 12
|
11 p.m. - 5 a.m.
Nightly
|
|
SR 280/South Cobb Drive to the I-20 Interchange
|
Pacing operation, all lanes and shoulders
|
Monday, October 5
|
Thursday, October 8
|
10:30 a.m. - 12 p.m. Daily
|
|
I-20 Westbound
|
|
SR 139/MLK Jr. Drive to the I-285 Interchange
|
Pacing operation, all lanes and shoulders
|
Monday, October5
|
Thursday, October 8
|
10:30 a.m. - 12 p.m. Daily
|
|
Anderson Avenue underpass to Riverside Parkway
|
Alternating, single, left-lane, and left-shoulder closure, and single, right-lane, and right-shoulder closure
|
Monday, October 5
|
Monday, October 12
|
9 p.m. - 5 a.m. Nightly
|
|
Anderson Avenue underpass to Riverside Parkway
|
Alternating, double, left-lane, and left-shoulder closure, and double, right-lane, and right-shoulder closure
|
Monday, October 5
|
Monday, October 12
|
11 p.m. - 5 a.m. Nightly
|
|
I-20 Eastbound
|
|
Riverside Parkway to the I-285 Interchange
|
Alternating, single, left-lane, and left-shoulder closure, and single, right-lane, and right-shoulder closure
|
Monday, October 5
|
Monday, October 12
|
9 p.m. - 5 a.m.
Nightly
|
|
Riverside Parkway to the I-285 Interchange
|
Alternating, double, left-lane, and left-shoulder closure, and double, right-lane, and right-shoulder closure
|
Monday, October 5
|
Monday, October 12
|
11 p.m. - 5 a.m.
Nightly
|
|
Other Locations
|
|
SR 70/Fulton Industrial Boulevard SB from Wendell Drive to Shirley Drive
|
Single, right-lane, and right-shoulder closure
|
Monday, October 5
|
Saturday, October 10
|
8 p.m. - 5 a.m.
Nightly
|
|
SR 139/MLK Jr. Drive NB from Old Gordon Road to Adamsville Drive
|
Single, right-lane, and right-shoulder closure
|
Monday, October 5
|
Saturday, October 10
|
8 p.m. - 5 a.m.
Nightly
|
DETOURS
|
|
I-20 Westbound to I-285 Northbound ramp closure
|
Overnight closure and detour (Map)
Motorists traveling on I-20 westbound will continue through the interchange and exit to SR 70/Fulton Industrial Blvd (Exit 49), turn left onto SR 70/Fulton Industrial Blvd, then turn left onto the I-20 eastbound ramp, and then exit right onto I-285 northbound (Exit 51B).
|
Wednesday, October 7
|
Friday, October 9
|
9 p.m. until 5 a.m.
Nightly
|
|
I-20 Eastbound to I-285 Northbound ramp closure
|
Overnight closure and detour (Map)
Motorists traveling on I-20 eastbound will exit to I-285 southbound (Exit 51A), continue straight onto SR 139/Martin Luther King Jr. Drive (Exit 9), turn left onto SR 139/Martin Luther King Jr. Drive, and then turn right onto the loop ramp to I-285 northbound.
|
Monday, October 12
|
Friday, October 16
|
9 p.m. until 5 a.m.
Nightly
|
Georgia Power will conduct intermittent traffic pacing on October 10 from 7 a.m. to 4 p.m. at following locations:
1. I-20 Eastbound: From Thornton Rd (Exit 44) to I-285
2. I-20 Westbound: From Joseph E Lowery Blvd (Exit 55) to I-285
3. I-285 Northbound: From SR 154 (Exit 5) to I-20
4. I-285 Southbound: From Atlanta Rd (Exit 16) to I-20
This is to string new power lines across the interstate. If postponed due to inclement weather, the work will take place on October 11 from 7 a.m. to 4 p.m. Drivers should expect delays and plan alternative routes.
Looking for more information about the adjacent I-285 Westside Rebuild projects?
Click here to visit the project website, learn more about the project, and view upcoming closures: https://i285w-pavement-reconst-gdot.hub.arcgis.com/
|
|
|