The City of Fort Lauderdale is working with M & M Asphalt Maintenance Inc. to resurface NW 69th Street between NW 32nd Avenue and NW 31st Way in Palm Aire Village West. This project includes:
Construction will begin on Wednesday, April 22, 2026, and is expected to be completed on Friday, April 24, 2026. Work will take place daily between 8 a.m. and 5 p.m. Construction is expected to begin at NW 32nd Avenue and head east toward NW 31st Way. This schedule is subject to change based on inclement weather or other unforeseen circumstances.
Traffic Impacts
We apologize in advance for any inconvenience and thank our neighbors for their patience during construction.
For more information or questions, contact:
Winzer King, City of Fort Lauderdale Project Manager II
954-828-6195 or [email protected]