2025 Road Repair Project

The 2025 Road Repair Project will bring preventative maintenance to a variety of locations throughout the City.

Work will consist of the following:

Milling and repaving

  • Harkins Slough Road from Green Valley Road to Struve Slough Bridge

  • Loma Prieta Avenue from Green Valley Road to Airport Boulevard

  • Kilburn Street from Ford Street to West 5th Street

Slurry Seal (surface treatment)

  • Harkins Slough Road from Ohlone Parkway to Blackbird Circle

  • Green Valley Road from Main Street to Carey Avenue

  • Freedom Boulevard from Alta Vista Avenue to Main Street

  • Ford Street from Rodriguez Street to Walker Street

Schedule

Construction will begin Monday, October 13th, and is expected to last 1-2 weeks depending on weather. Work will be done Monday-Friday 7:00AM-6:00Pm.

Funding

Funding for this project comes from the Road Repair and Accountability Act (SB1) and Measure D.

City of Watsonville, CA published this content on October 09, 2025, and is solely responsible for the information contained herein. Distributed via Public Technologies (PUBT), unedited and unaltered, on October 09, 2025 at 18:02 UTC. If you believe the information included in the content is inaccurate or outdated and requires editing or removal, please contact us at [email protected]