02/23/2026 | Press release | Distributed by Public on 02/23/2026 14:00
DUPONT - On the heels of opening the new southbound Interstate 5 exit 119 to Steilacoom-DuPont Road, crews are making final preparations to fully open the state's third diverging diamond interchange. The new I-5 overpass will provide access between DuPont and Joint Base Lewis-McChord in Pierce County. Demolition of the old overpass is currently scheduled for April 3-4, and will require two overnight full closures of both north and southbound I-5.
At 8 p.m. Friday, March 20, the southbound I-5 exit to Steilacoom-DuPont Road will close. At 6 a.m. Saturday, March 21, the new Steilacoom-DuPont Road on-ramp to southbound I-5 will open. At that time, crews will close the 1957 overpass to all traffic. Northbound I-5 travelers using exit 119 will begin using the new interchange.
Additional information is available via the Washington State Department of Transportation online open house.
Some of the work needed to fully open the new diverging diamond interchange could be delayed due to rain, snow or cold weather. WSDOT will update travelers of any changes.
The permanent closure of the 1957 overpass is a significant safety improvement. Moving traffic to the new interchange will eliminate an at-grade railroad crossing. The new overpass is built to modern design standards, reducing the potential for overhead bridge strikes.
People who walk, bicycle or roll will use a barrier-separated shared-use path on the new overpass. This 12-foot-wide path connects JBLM to DuPont.
Overnight Friday and Saturday, April 3-4, both directions of I-5 will detour through exit 119 at Steilacoom-DuPont Road.
Once the original overpass is removed, crews can finish widening I-5 to extend the high occupancy vehicle (HOV) lanes.
Those HOV lanes will open this summer as part of the I-5 Mounts Road to Steilacoom-DuPont Road Corridor Improvements project.