BRADLEY COUNTY I-75 [15.35-19.309] from MM 31 to MM 35 (McMinn County Line) resurfacing: The contractor will continue paving operations. This work will require temporary lane closures in both directions, which will occur Sunday nights through Friday nights 8 PM to 6 AM. Motorists should exercise caution and pay attention to construction signage. The speed limit will be reduced during paving operations. [Wright Brothers Construction Company, Inc./Chattanooga West/CNY261]
BRADLEY COUNTY SR-306 (LOWER RIVER RD.) Utility Work both directions from LM 6.65 to LM 6.86: Flagger assisted lane closures on SR-2 (Lee Hwy) Between in the area of Eads Bluff Rd. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 12/18/2025, with a rain date of 12/22/2025, from 9 am - 2 pm [2024-791]
BRADLEY COUNTY SR-40 [5.1-9.7] from Lyles Rd. to Bradley-Polk County Line resurfacing: During this reporting period, the contractor will continue final pavement marking work on SR-40. Temporary lane closures will be necessary during daytime hours on weekdays while work is performed. Motorists should use caution when traveling through the work zone and be aware of equipment in the area. [APAC - Atlantic, Inc./Cleveland/CNZ020]
BRADLEY COUNTY SR-60 widening from the 4-lane north of I-75 (LM 17.2) to SR-306 (LM19.9): During this reporting period, the contractor will perform punch list work on SR-60 in Bradley County. Intermittent lane closures may be necessary while work occurs. [Summers-Taylor, Inc./Cleveland/CNV130]
BRADLEY COUNTY SR-74 (SPRING PLACE RD.) Utility Work both directions from LM 11.07 to LM 11.14: Flagging assisted lane closures on SR-74 (Spring Place Rd) between Clayton LN and Durkee RD SE. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 12/18/25 through 06/18/2026 from 9 am - 2 pm [2025-736]
BRADLEY COUNTY SR-74 [11.445-11.83] from Whaley Road to SR-60 APD-40 drainage improvements: During this reporting period, the contractor will continue storm drain installation and grading work on SR-74. Intermittent flagging operations and shoulder closures will be necessary periodically. Motorists should use caution and reduce speed when traveling through the work zone. Officer Street will be temporarily closed at the intersection of SR-74 while a new storm drainage pipe is installed under the roadway. Pickens Street will be utilized as a detour for local traffic during this closure. [APAC - Atlantic, Inc./Cleveland/CNZ243]
CAMPBELL, COFFEE, DAVIDSON, DICKSON, GILES, GREENE, HAYWOOD, KNOX, MCMINN, SHELBY, AND WILLIAMSON COUNTY The installation of Weigh-in-Motion technology at 28 sites on various Interstate and State Routes: No Region 2 Lane Closures this week on CNX913.
[Davis H. Elliot Construction Company, Inc./Maint - R2/CNX913]
COFFEE COUNTY I-24 (MM 117) construction of an overpass carrying Wattendorf Memorial Highway/AEDC Road, including grading, drainage, retaining walls, and paving: Drivers can expect short-term flagging operations for trucks entering and exiting the work zone on Wattendorf Highway. Please use caution when traveling through the work zone.
[Jones Bros. Contractors, LLC/Tullahoma/CNZ029]
COFFEE COUNTY SR-55 construction from First Avenue (LM 2.0) to SR-16 (US-41A, N. Jackson St, LM 2.6) in Tullahoma: Phase 1 of roadway widening and bridge replacement on SR-55 (Wilson Ave.) will continue this week. The contractor may use temporary lane shifts to complete storm structure installations. Phase 1 traffic shift has reduced lanes from 3 to 2 from Cedar Lane to near Grau Lane in order to continue bridge replacement and storm drainage work. There will be daily lane closures on SR-55 for paving activities. Flagging operations will be utilized on SR-55 from 8 AM to 4 PM daily.
[Dement Construction Company, LLC/Tullahoma/CNX912]
CUMBERLAND COUNTY I-40 Utility Work, both directions from MM 318.8 to MM 329.1: Law Enforcement assisted rolling roadblock between Exit 322 eastbound and Exit 329 westbound. Message boards, signage, and law enforcement vehicles will be present. Motorists should be aware of personnel and equipment, reduce speed, and be prepared to stop. 12/21/25 between 6:00 am and 9:00 am, weather contingent. (2025-823]
CUMBERLAND COUNTY SR-24 [15.056-15.56] from Crossville city limits to Seventh-Day Adventist Church and School bridge replacement: The Contractor has closed SR-24 at LM 15.06 to LM 15.6. This closure will remain in place for the duration of the project. The posted detour is along SR-462 and SR-1. The contractor will be working on general clearing activities and utility work initially. Once initial work is completed, the Contractor will proceed with the replacement of the bridge over the Obed River. Motorists should use caution and utilize the posted detour. RESTRICTIONS: Both lanes of SR-24 are closed from LM 15.06 to LM 15.6. [Mid-State Construction Company, Inc./Crossville/CNZ206]
CUMBERLAND COUNTY SR-28 (US-127 S.) Utility Work both directions from LM .44 to LM 5.94: Northbound and Southbound Lane closures on SR-28 (HWY 127 S.) between Lowes Gap Rd. and Willard Brown Rd. Motorists should reduce speed and be prepared to stop. Arrow board/message boards, flaggers, and barrels/cones will be present, 10/30/25 through 02/25/2026 from 9 am - 2 pm. [2025-659]
CUMBERLAND COUNTY SR-28 (US-127 S.) Utility Work both directions from LM .44 to LM 5.94: Northbound and Southbound Lane closures on SR-28 (HWY 127 S.) between Lowes Gap Rd. and Willard Brown Rd. Motorists should reduce speed and be prepared to stop. Arrow board/message boards, flaggers, and barrels/cones will be present, 10/30/25 through 02/25/2026 from 9 am - 2 pm. [2025-659]
CUMBERLAND COUNTY SR-28 (US-127) bridge construction and paving from north of I-40 (LM 17.8) to near Potato Farm Road (LM 22.7): The contractor continues grading activities throughout the project limits. Temporary lane closures and/or periodic traffic stoppages will be necessary for construction activities. The contractor has scheduled paving operations beginning on the north end of the project on the proposed alignment. The contractor has closed North Grace Hill Drive at the existing intersection of SR-28 (US-127) for construction activities. Motorists should utilize South Grace Hill Drive as the detour with appropriate signs. Traffic has been moved to a temporary alignment on Plateau Road and a permanent alignment on Potato Farm Road. Flaggers and advanced warning signs will accompany any closures. Motorists should use caution when traveling through the work zone as traffic patterns change.
[Jones Bros. Contractors, LLC/Crossville/CNV009]
CUMBERLAND COUNTY SR-392 (MILLER AVE.) Utility Work both directions from LM 0.64 to LM 0.61: Flagging assisted lane closures on SR-392 (Miller Ave) between West Ave and 10th St. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 12/19/2025 from 9 am - 2 pm [2025-889]
CUMBERLAND AND FENTRESS COUNTY SR-28 (US-127) widening from near N. Lowe Rd (LM 29.2) to north of SR-62 (LM 1.9): The contractor has shifted traffic to phase 2 on the newly constructed portions of SR-28 LM 0.90 to 1.98 in Fentress County. Work will proceed with the existing alignment of SR-28. Flaggers are being used intermittently as needed to control traffic through the work zone. Motorists are encouraged to use caution, be aware of new traffic signs and pavement markings, and watch for construction equipment and personnel throughout the project.
[Jones Bros. Contractors, LLC/Cookeville/CNV300]
DEKALB COUNTY SR-26 (US-70) grading, drainage, and construction of retaining walls and paving from near SR-53 (LM 2) to near SR-96 (LM 6.1): The contractor continues grading and construction activities throughout the project. Temporary lane closures and periodic traffic stoppages will be necessary for construction activities, and motorists should be prepared to stop while traveling through the work zone. Motorists are encouraged to obey the posted speed limit and to watch for construction equipment and personnel adjacent to the roadway. The West End of Old Liberty Road will be closed to through traffic due to construction activities. Motorists and EMS will need to use the East entrance of Old Liberty Road to gain access and follow detour signs. [Twin K Construction/Cookeville/CNV012]
FENTRESS COUNTY SR-62 [5.79-5.81] from west of SR-28 (US-127) to SR-28 (US-127) storm drain installation: The contractor will be closing a lane on SR-62 from LM 5.79 to LM 5.81 just west of SR-28 (US-127) to install a storm drain. The closure will occur daily from 6 AM to 5 PM beginning 12/15/25 to 12/22/25. Flaggers will be used to control traffic. Motorists are advised to pay attention to signs and flaggers, using caution as they travel through the work zone.
[Jones Bros. Contractors, LLC/Livingston/CNV300]
HAMILTON COUNTY I-124 (US-27) from I-24 Interchange to South of the Tennessee River Bridge: Daily lane closures are possible between 9 AM and 3:30 PM as the contractor works along the ramps and 4th Street. Motorists are advised to reduce speed in the work zone and watch for flaggers assisting with traffic control. [Stansell Electric Company, Inc./Chattanooga East/CNY900]
HAMILTON COUNTY I-75 at I-24 Interchange Reconstruction Phase 2: Nightly Lane closures will regularly occur on this project, 9 PM to 6 AM, on I-75 North and South between Exit 1 (East Ridge) and Exit 3A (East Brainerd Road/ SR-320) and on I-24 East and West from Germantown Road to Spring Creek Road, MM182 to MM185, for various construction activities. These closures may temporarily reduce traffic to a single lane. Uniformed police officers will be present in these work zones to assist with traffic management and to enforce traffic laws. (Note: nighttime lane closures from 8 PM to 6 AM are scheduled on I-24 East and West between Germantown Road and the I-75 interchange for placement of asphalt paving on Sunday (12/21) and Monday (12/22). On Saturday, December 20th from 8 AM to 8 PM the contractor will also have daytime closures on the outside lanes and ramps of I-24 East and West to finish paving. Ramp closures include I-24 WB exit 183 and I-24 EB exit 183. At times, traffic may be temporarily reduced to a single lane during nighttime work while this paving is taking place. As crews pave traffic lanes, it may be necessary to temporarily close entrance and exit ramps along I-24 for crews to safely perform their work. Message boards and detours will be posted to guide traffic to the next available ramp. As soon as fresh paving has cured sufficiently to support traffic, these ramps will be reopened. The contractor plans to continue paving North and South Terrace. This work will continue until Tuesday (12/23). Various lane closures and detours will be implemented for the Terrace work as it progresses. Further information on this work as it progresses. Most of the remaining work items on this project are temperature and weather sensitive. If any of them are canceled due to inclement conditions, they will be rescheduled to take place on the next available day when adequate conditions exist. It may also be necessary to do short duration (15 to 30 minutes) rolling roadblocks during the day or night for patching potholes, clearing debris or repairing guardrail, attenuators, etc. Portions of the left lane on North and South Terrace between Germantown Road and Spring Creek Road will remain closed for the installation of drainage structures, sanitary sewers, retaining and noise wall construction. [Wright Brothers Construction Company, Inc./Maj Prj - Blevins/DB2101]
HAMILTON COUNTY I-75 at the Hamilton Place Mall interchange: The SR-153 southbound ramp to I-75 northbound has been reduced to one lane. Traffic shifts have been implemented on I-75 northbound, Shallowford Road entrance ramps, and Shallowford Road exit ramps and the Hamilton Place Mall exit ramp. Hamilton Loop Road is closed for retaining wall construction and storm drainage installation between the intersections near Markman's Jewelers and Texas Roadhouse. The speed limit has been reduced on I-75 throughout the project limits. Nightly lane closures are permitted from 8 PM to 6 AM. Motorists should use caution, paying attention to construction signage and watching for construction vehicles and personnel. [Summers-Taylor, Inc./Chattanooga West/CNX358]
HAMILTON COUNTY SR-2 (LEE HWY.) Utility Work both directions from LM 1.61 to LM 7.0: Flagger-assisted lane closures on SR-2 (Lee Hwy) near Sam Smith RD, Eldridge Rd, and Grasshopper RD. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 12/15/2025 through 01/30/2026 from 9 am - 2 pm. [2024-799]
HAMILTON COUNTY SR-2 (LEE HWY.) Utility Work both directions from LM 18.80 to LM 18.86: : Flagger-assisted lane closures on SR-2 (Lee Hwy) between McCutcheon Rd and Elm Dr. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 10/2/25 through 12/19/25 from 9 am - 2 pm. [2024-338]
HAMILTON COUNTY SR-2 (LEE HWY.) Utility Work both directions from LM 18.80 to LM 18.86: This is nighttime work. Flagger-assisted lane closures on SR-2 (Lee Hwy) between McCutcheon Rd and Elm Dr. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 12/19/2025 through 12/21/2025 from 9 pm to 5 am [2024-338]
HAMILTON COUNTY SR-29 [20.72-25.756] from SR-111 to Old Dayton Pk. Resurfacing: The contractor is resurfacing US-27, requiring temporary lane closures throughout the project length. The contractor's schedule is 7 AM to 7 PM and is weather-dependent. Some work may be completed at night to facilitate the project schedule. [Rogers Group, Inc./Chattanooga West/CNZ034]
HAMILTON COUNTY SR-317 (Apison Pike) improvement project from SR-321 (Ooltewah-Ringgold Road) to east of Layton Lane: Lane closures and flagging operations will be required on SR-317 during daytime hours. [Wright Brothers Construction Company, Inc./Chattanooga East/CNT336]
HAMILTON COUNTY SR-319 (HIXSON PK.) Utility Work both directions at LM 7.45: Flagging assisted lane closures on SR-319 (Hixson Pike) between Cassandra Smith Rd and Windbrook Dr. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 12/04/25 through 12/18/25 from 9 am - 2 pm. [2025-838]
MARION COUNTY SR-108 [2.8-3.24] slide mitigation: The contractor will be performing slide mitigation operations, including grading, drainage, and paving on SR-108 in Marion County at LM 2.8. The roadway will be reduced to one lane controlled by temporary traffic signals. The project completion date is 08/31/2027. Please use caution when driving through the work zone. [Wright Brothers Construction Company, Inc./Dunlap/CNZ226]
MARION COUNTY SR-2 [17.2-17.3] from 17.2 to 17.3 construction: The contractor will be performing grading and drainage operations on SR-2 in Marion County near LM 17.25. This work will require a lane shift for the EB traffic; the WB traffic will be unaffected. Please slow down and use caution when driving through the work zone. [Talley Construction Company, Inc./Dunlap/CNZ244]
MCMINN COUNTY I-75 [0-2.06] from MM 35 (Bradley County Line) to MM 37 resurfacing: The contractor will continue paving operations. This work will require temporary lane closures in both directions, which will occur Sunday nights through Friday nights 8 PM to 6 AM. Motorists should exercise caution and pay attention to construction signage. The speed limit will be reduced during paving operations. [Wright Brothers Construction Company, Inc./Chattanooga West/CNY261]
MCMINN COUNTY I-75 [2.06-4.32] from MM 37 to MM 39.5 resurfacing: The contractor will continue paving operations. This work will require temporary lane closures in both directions, which will occur Sunday nights through Friday nights 8 PM to 6 AM. Motorists should exercise caution and pay attention to construction signage. The speed limit will be reduced during paving operations. [Wright Brothers Construction Company, Inc./Chattanooga West/CNZ109]
MCMINN COUNTY SR-39 construction of a bridge over Middle Creek (LM 13.4): During this reporting period, the contractor will be flagging the roadway to perform work. This flagging operation will only occur during daytime hours. [Whaley Construction, LLC/Chattanooga East/CNX069]
POLK COUNTY SR-68 over SR-40 the construction of bridges: During this reporting period the contractor will continue construction on SR-68 North bridge. All SR-68 traffic is using the existing SR-68 South bridge while construction occurs on the new SR-68 North bridge. All SR-40/SR-68 interchange traffic will utilize the SR-68 South interchange ramps. A temporary 3-way stop has been implemented at the intersection of the SR-40 interchange ramp and SR-68. Motorists are encouraged to slow down when entering the construction zone and look out for new stop signs on SR-68 near the SR-40/SR-68 interchange. [Wright Brothers Construction Company, Inc./Cleveland/CNZ042]
PUTNAM COUNTY SR-136 construction from north of the SR-111 interchange to south of the I-40 interchange: The contractor continues grading activities throughout the project. Temporary lane closures and/or periodic traffic stoppages will be necessary for construction activities. Motorists are encouraged to use caution while traveling through the work zone and be aware of construction personnel and equipment adjacent to the roadway. [Rogers Group, Inc./Cookeville/CNV284]
PUTNAM COUNTY SR-24 (CROSSVILLE HWY.) Utility Work both directions from LM 35.35 to LM 38.09: Eastbound and Westbound Lane closures on SR-24 (Crossville Hwy.) between E. Wilder Ave. and Walker Farm Rd. Motorists should reduce speed and be prepared to stop. Arrow board/message boards, flaggers, and barrels/cones will be present, 11/06/25 through 05/06/2026 from 9 am - 2 pm. [2025-521]
PUTNAM COUNTY SR-84 (CALFKILLER HWY.) Utility Work both directions from LM 1.0 to LM 8.0: Flagger-assisted lane closures on SR-84 (Calfkiller Hwy) from the White County line to Hidden Acres Road. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 04/24/25 through 01/30/25 from 8 am - 3 pm. [2023-577]
REGION 2 Dynamic Message Sign (DMS) Life Cycle Replacement: Rolling roadblocks on December 15th, on Interstate 24 West, Mile Marker 156, in Marion County, rolling roadblocks are scheduled to reset DMS Board across the interstate. Delays are expected 8 pm to 5 am.
[Davis H. Elliot Construction Company, Inc./Chattanooga East/CNX413]
REGION 2 preventative and unscheduled maintenance of Chattanooga SmartWay Intelligent Transportation System: The contractor may have short-term shoulder and/or lane closures to perform preventative or unscheduled maintenance to the local SmartWay Intelligent Transportation System. At least one travel lane will always remain open to traffic. The contractor will have daytime outside shoulder closures on Bradley I-75 between MM 25 and MM 33.
[Lumin8 Transportation Technologies, LLC/Chattanooga East/CNX270]
REGION 2 The on-call cable barrier repair on various Interstate and State Routes: The contractor will have short-term shoulder and/or lane closures in order to perform force account cable barrier rail repair. These closures will take place on the interstate nightly Sunday through Thursday from 7 PM to 6 AM as needed and daily Monday through Friday. At least one travel lane will remain open to traffic at all times. Typically, only shoulder closures will be used in the median, but lane closures will be employed as needed. [LU, Inc./McMinnville/CNZ205]
REGION 2 The on-call guardrail repair and new guardrail installation on various Interstate and State Routes: The contractor will have short-term shoulder and/or lane closures in order to perform guardrail repair. These closures will take place on the interstate nightly Sunday through Thursday from 7 PM to 6 AM and daily Monday through Friday on state routes. At least one travel lane will remain open to traffic at all times on the interstate, and flaggers will be present on state routes during any work that is performed. [Reynolds Fence and Guardrail, Inc./McMinnville/CNZ112]
REGION 2 The sweeping on various Interstate and State Routes: Sweeping operations are planned throughout Region 2 this reporting period. Sweeping operations are mobile operations along the inside and outside shoulders with impacts to adjacent traffic lanes. These operations will occur at night between 8 PM and 6 AM for interstates and high traffic state routes, while daytime sweeping can be anticipated between 9 AM to 3 PM for lower traffic state routes.
[Sweeping Corporation of America, Inc./Chattanooga West/CNY210]
REGION 2 Various Interstate and SRs - Cable Barrier Repair: The contractor will have short-term shoulder and/or lane closures in order to perform cable barrier rail repair. These closures will take place on the interstate nightly Sunday through Thursday from 7 PM to 6 AM as needed and daily Monday through Friday. At least one travel lane will remain open to traffic at all times. Typically, only a shoulder closure will be used in the median, but lane closures will be employed as needed.
[LU, Inc./McMinnville/CNY183]
RHEA COUNTY SR-29 [14.66-19.879] from Boofer Lane to Metzger LN Resurfacing: Paving is complete. The contractor may have some cleanup work to complete. This may require temporary lane closures from 7AM to 6PM or mobile operations. Motorists should use caution while traveling on this route and pay attention to all construction signage.
[Rogers Group, Inc./Chattanooga West/CNY118]
WARREN COUNTY SR-1 (SPARTA HWY.) Utility Work both directions at LM 16.79: Flagging assisted lane closures on SR-1 (Sparta HWY) at the Ty Brooke Ln and Sparta Hwy exchange. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 12/18/2025 from 9 am - 2 pm With a rain date of 12/19/2025 [2025-884]
WHITE COUNTY SR-111 (SPENCER HWY.) Utility Work both directions at LM 6.99: Flagging assisted lane closures on SR-111 (Spencer Highway) between River Chase Dr. and Iris Dr. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 12/18/2025 from 9 am - 2 pm with a rain date of 12/19/2025 [2025-879]
RESTRICTIONS
CAMPBELL, COFFEE, DAVIDSON, DICKSON, GILES, GREENE, HAYWOOD, KNOX, MCMINN, SHELBY, AND WILLIAMSON COUNTY - CNX913:
CUMBERLAND COUNTY - CNZ206: Both lanes of SR-24 are closed from LM 15.06 to LM 15.6.
###