11/20/2026 | Press release | Distributed by Public on 11/20/2026 09:51
MANAGEMENT'S DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND RESULTS OF OPERATIONS
The following discussion should be read together with the unaudited consolidated financial statements and notes included in Item 1 of this report and the audited consolidated financial statements included in the Company's Annual Report on Form 10-K for the year ended December 31, 2025. This discussion contains forward-looking statements that involve risks and uncertainties; actual results may differ materially from those anticipated. See Item 1A, Risk Factors.
Executive Overview
HyOrc Corporation (the "Company" or "HyOrc") is an integrated clean energy infrastructure and technology company focused on commercialization of waste-to-methanol, distributed power generation, industrial heat recovery and related decarbonization technologies. Its business model combines equipment and engineering services, technology licensing, project development and potential participation in recurring renewable-fuel and power-generation revenues.
During the three months ended September 30, 2026, management concentrated on the commercial execution of its Portuguese renewable methanol platform, establishment of a project-level joint venture, advancement of grant-supported expansion, continued manufacturing and engineering, and development of financing and strategic partnerships. The Company remained in the transition from technology validation to commercial deployment; its principal reference projects had not yet commenced sustained commercial operation as of quarter-end.
A significant development during the quarter was approval of approximately €6.7 million of support under the European Union's Strategic Technologies for Europe Platform ("STEP") program for the proposed expansion of the Portuguese project. The award relates to a larger facility designed to process approximately 35 tons per day ("TPD") of refuse-derived fuel ("RDF") into approximately 8 metric tonnes per day of methanol. The approved grant relates to the Portuguese project and is not equivalent to unrestricted cash held by HyOrc Corporation; project implementation remains subject to funding conditions, counterpart contributions, permitting, procurement and execution.
During the quarter, the Company and MO.RE.DA. Oils, Lda. ("MO.RE.DA.") restructured their Portuguese project joint venture. The project vehicle, HyOrc Green Fuels, Lda., is structured as a 50/50 venture, and the Company holds an option, subject to due diligence, to acquire a 50% ownership interest in MO.RE.DA., with a decision deadline in mid-December 2026. The initial reference installation is designed for approximately 3 TPD RDF input and approximately 1 metric tonne per day of methanol output. This initial module is distinct from the 35 TPD RDF expansion project. Manufacturing and project preparations continued during the quarter; the initial module had not entered commercial production by September 30, 2026.
In parallel, management pursued commercial applications of its externally fired Organic Rankine Cycle ("ORC") power systems, including rail decarbonization through Project Phoenix, potential distributed generation for data centers and industrial customers in the United Kingdom, and additional waste-to-methanol opportunities. These initiatives remain at different stages of development and are not represented as contracted or operating revenues unless and until the applicable commercial and accounting conditions are satisfied.
From a financing perspective, during the quarter the Company completed a $115,000 Regulation S equity financing, issued $70,200 of convertible notes to Jefferson Street Capital LLC and Lambda Ventures LLC, entered into a $7.5 million Equity Purchase Agreement with Lambda Ventures LLC, and extended the maturity of its GS Capital Partners, LLC note to March 13, 2027.
Business Overview
HyOrc's principal renewable-fuels technology combines RDF conversion, gas conditioning and methanol synthesis. The Company intends to commercialize the technology initially through a modular reference facility in Portugal and subsequently through larger plants financed, where feasible, with project-level capital, infrastructure debt, grants and strategic investment. The Company also develops ORC-based power systems for external combustion, waste-heat recovery, transportation and stationary generation applications.
The Company seeks multiple revenue streams, including engineering and design services, equipment manufacturing and sales, licensing, operations and maintenance, project development, and participation in methanol or electricity production. The timing and scale of these revenues depend on commercial deployment, customer contracts, access to financing, regulatory approvals and operational performance.
Results of Operations
Three Months Ended September 30, 2026 Compared with Three Months Ended September 30, 2025
|
Three months ended Sept 30, 2026 |
Three months ended Sept 30, 2025 |
Change | ||||||||||
| Revenue | $ | 0 | $ | 0 | $ | 0 | ||||||
| Other income | 0 | 4,000 | (4,000 | ) | ||||||||
| Administrative and other expenses | 484,831 | 63,829 | 421,002 | |||||||||
| Interest expense | 124,049 | 0 | 124,049 | |||||||||
| Loan issuance costs | 5,000 | 0 | 5,000 | |||||||||
| Loss on change in fair value of derivative liability | 44,423 | 0 | 44,423 | |||||||||
| Loss on issuance of convertible notes and commitment shares | 57,690 | 0 | 57,690 | |||||||||
| Equity line commitment costs | 46,000 | 0 | 46,000 | |||||||||
| Loss on extinguishment of debt | 136,531 | 0 | 136,531 | |||||||||
| Net loss | $ | (898,524 | ) | $ | (59,829 | ) | $ | (838,695 | ) | |||
Revenues
The Company recognized no revenue for the three months ended September 30, 2026 or 2025. The Company's Porto methanol reference facility was not yet in commercial operation at quarter-end, and no operating methanol sales are attributable to that project. Other income of $4,000 in the third quarter of 2025 did not recur.
Operating Expenses
Administrative and other expenses were $484,831 compared with $63,829 for the third quarter of 2025. The increase was driven principally by non-cash stock-based compensation of $416,480 (2025: $0), comprising $296,000 for shares issued on January 7, 2026 and recorded in the quarter as an out-of-period adjustment (see Note 1 to the financial statements), $60,480 for shares issued to directors and the Chief Operating Officer on July 17, 2026, and $60,000 of director fees accrued for the quarter. Excluding stock-based compensation and depreciation of $524, administrative and other expenses were $67,827, compared with $63,829 in the prior-year quarter. Within this amount, investor relations and advertising increased to $18,833 (2025: $1,850) following the July financing and the launch of the Company's retail investor-awareness program, while legal and professional fees ($22,191; 2025: $24,479), general and administrative costs ($11,612; 2025: $11,582) and contractor fees ($9,000; 2025: $13,500) were comparable or lower.
Net Loss and Other Items
The net loss for the quarter was $898,524, compared with $59,829 for the third quarter of 2025. Charges relating to the Company's convertible notes and equity line totaled $413,693 for the quarter, most of which were non-cash:
| ● | interest expense of $124,049, of which $106,323 was non-cash amortization of debt discount and $17,726 was accrued coupon and one-time interest (including $7,683 relating to the first half of 2026, recorded as an out-of-period adjustment); | |
| ● | a loss on extinguishment of debt of $136,531 on the amendment of the GS Capital Partners, LLC note, reflecting the increase in the fair value of the conversion feature from the extended term, the $15,000 added to principal and the 250,000 shares that ceased to be returnable; | |
| ● | a day-one loss of $57,690 on the August 2026 notes, representing the excess of the fair value of the embedded conversion features over the proceeds allocated to them, together with the 250,000 commitment shares; |
| ● | a loss of $44,423 on remeasurement of the derivative liabilities, driven by the increase in the Company's share price to $0.085 at September 30, 2026; | |
| ● | equity line commitment costs of $46,000, consisting of 750,000 commitment shares and $10,000 of legal fees; and | |
| ● | loan issuance costs of $5,000 withheld at the August 2026 note closing. |
The net loss for the quarter included $303,893 of out-of-period adjustments relating to the first and second quarters of 2026. See Notes 1 and 10 to the financial statements.
Nine Months Ended September 30, 2026 Compared with Nine Months Ended September 30, 2025
|
Nine months ended Sept 30, 2026 |
Nine months ended Sept 30, 2025 |
Change | ||||||||||
| Revenue | $ | 24,000 | $ | 150 | $ | 23,850 | ||||||
| Other income | 0 | 15,559 | (15,559 | ) | ||||||||
| Administrative and other expenses | 943,550 | 158,018 | 785,532 | |||||||||
| Operating loss (revenue and other income less administrative and other expenses) | (919,550 | ) | (142,309 | ) | (777,241 | ) | ||||||
| Interest expense | 232,141 | 0 | 232,141 | |||||||||
| Loan issuance costs | 16,030 | 0 | 16,030 | |||||||||
| Loss on change in fair value of derivative liability | 26,607 | 0 | 26,607 | |||||||||
| Loss on issuance of convertible notes and commitment shares | 296,037 | 0 | 296,037 | |||||||||
| Equity line commitment costs | 46,000 | 0 | 46,000 | |||||||||
| Loss on extinguishment of debt | 136,531 | 0 | 136,531 | |||||||||
| Net loss | $ | (1,672,896 | ) | $ | (142,309 | ) | $ | (1,530,587 | ) | |||
Revenue for the nine months ended September 30, 2026 was $24,000, consisting entirely of commission income earned in the second quarter under legacy commercial arrangements in India with Vaigunth Enertek, a related party, compared with $150 of services income in 2025. That commission was earned on equipment sales by Vaigunth Enertek, including the 3-TPD gasification unit for the Assam municipality announced on May 25, 2026; the Company was not the seller of that equipment. No revenue has yet been generated by new commercial infrastructure projects. Other income of $15,559 in 2025 did not recur.
Administrative and other expenses increased to $943,550 from $158,018. Stock-based compensation accounted for $650,788 of the increase (2025: $0). Excluding stock-based compensation and depreciation, expenses increased to $292,238 from $158,018, principally due to legal and professional fees of $133,465 (2025: $88,983) relating to SEC reporting, the auditor's interim reviews, the convertible note financings and the Company's subsidiary and arbitration matters; investor relations and advertising of $54,102 (2025: $3,500); and $32,964 of operating expenses recorded in the second quarter of 2026.
Financing-related charges for the nine months totaled $753,346 (2025: $0), comprising interest expense of $232,141, losses on issuance of $296,037, the loss on extinguishment of $136,531, equity line costs of $46,000, net derivative remeasurement losses of $26,607 and loan issuance costs of $16,030. As a result, the net loss for the nine months was $1,672,896, compared with $142,309 for the same period of 2025.
Critical Accounting Estimates
The preparation of financial statements in accordance with U.S. GAAP requires management to make estimates that affect reported amounts. The estimates that management considers most critical, because they require significant judgment and changes could materially affect reported results, are:
| ● | Fair value of derivative liabilities. The embedded conversion features of the Company's convertible notes are measured at fair value each period using a Black-Scholes model with Level 3 inputs, principally expected volatility (263% at September 30, 2026), the Company's share price, and the conversion price based on 77% of the lowest traded price in the preceding 15 trading days. Higher volatility or share price increases the liability and the related losses. The same model was used to measure the amended GS note on extinguishment. See Note 10. | |
| ● | Recoverability of long-lived assets. The $2,320,000 Biliran geothermal plant has been offline since October 2024. Management's conclusion that no impairment is required is based on the opinion of external counsel regarding the Company's rights under the PFBT Agreement and its recovery strategy. Goodwill of $15,755,344 and patents of $3,604,558 are tested for impairment annually and when indicators arise. See Notes 1, 4 and 5. | |
| ● | Classification of financing instruments. Judgment is required to determine whether subscription receipts are liabilities or equity, whether debt amendments are modifications or extinguishments, and whether equity line costs may be deferred. See Notes 1, 9, 10 and 11. | |
Key Performance Indicators (KPIs)
Because the Company remains in a commercialization phase, management monitors technical, commercial and financing milestones alongside financial results. Milestones are not a substitute for GAAP financial measures and do not establish that a project has generated revenue.
| KPI | Status at September 30, 2026 | |
| SEC reporting | Reporting obligations ongoing; interim reviews of the March 31 and June 30, 2026 periods completed after quarter-end | |
| Porto initial reference module | Manufacturing, assembly and testing in progress in India; 3 TPD RDF input / approximately 1 metric tonne per day methanol output | |
| Portugal project vehicle | HyOrc Green Fuels, Lda. joint venture restructured with MO.RE.DA. during the third quarter; 50/50 project participation; option to acquire 50% of MO.RE.DA. subject to due diligence | |
| Portugal STEP expansion | Approximately €6.7 million grant approval; 35 TPD RDF / approximately 8 metric tonnes per day methanol design | |
| Technology validation | Bureau Veritas pilot verification previously completed; commercial performance demonstration pending | |
| Project Phoenix | UK project vehicle with GB Railfreight under development; TÜV SÜD certification pathway approved by the Board | |
| Bulgaria methanol project | Technical and commercial development and grant application activities during the third quarter (see Subsequent Events) | |
| Distributed power | Commercial discussions and project evaluation ongoing | |
| Financing | Regulation S equity, August 2026 notes, $7.5 million Equity Purchase Agreement and GS note extension completed |
Liquidity and Capital Resources
At September 30, 2026, HyOrc continued to rely on financing arrangements and limited operating revenue to support engineering, manufacturing, corporate overhead and project development. The Company had not established recurring cash flows from its principal renewable methanol projects. Liquidity remains a material consideration, and management expects additional capital will be required to complete commercialization and maintain operations.
Cash Flows and Working Capital
|
September 30, 2026 / nine months 2026 |
December 31, 2025 / nine months 2025 |
|||||||
| Cash and cash equivalents | $ | 63,321 | $ | 19,417 | ||||
| Working capital (deficit) | (950,810 | ) | 40,958 | |||||
| Net cash used in operating activities - nine months | (282,516 | ) | (377,546 | ) | ||||
| Net cash provided by (used in) investing activities - nine months | (168,776 | ) | 80,000 | |||||
| Net cash provided by financing activities - nine months | 495,196 | 143,961 | ||||||
Cash increased by $43,904 during the nine months ended September 30, 2026. The working capital deficit of $950,810 includes derivative liabilities of $724,850, which are non-cash and would be settled in shares if the notes are converted; excluding the derivative liabilities, the working capital deficit was $225,960. Current liabilities also include convertible notes with aggregate principal of $370,200 maturing between March and August 2027.
Net cash used in operating activities was $282,516, compared with $377,546 in 2025. The 2025 period included the settlement of $160,167 of trade payables and a $75,070 increase in receivables. Net cash used in investing activities of $168,776 consisted of payments to Vaigunth Enertek for the Porto processing unit ($165,000) and an office computer; in 2025, investing activities reflected an $80,000 reduction in plant and equipment. Net cash provided by financing activities was $495,196, consisting of convertible note proceeds of $302,970 and proceeds from share subscriptions and issuances of $192,226. The 2026 statement of cash flows presents the first six months on a corrected classification basis; see Note 1 to the financial statements.
Financing Activities
The Company has historically financed operations through equity issuances, convertible notes and other financing arrangements. During the quarter ended September 30, 2026:
| ● | Regulation S financing. On July 17, 2026, the Company issued 2,875,000 shares at $0.04 per share to a non-U.S. investor for gross proceeds of $115,000 (net $114,267), providing working capital for completion of the Porto pilot and associated manufacturing. | |
| ● | August 2026 notes. On August 3, 2026, the Company issued convertible notes of $35,100 each to Jefferson Street Capital LLC and Lambda Ventures LLC ($70,200 in aggregate) for a purchase price of $65,000, with a one-time interest charge of 12%, twelve-month maturities, and conversion beginning six months after issuance at 77% of the lowest traded price in the preceding 15 trading days. After legal fees withheld, the Company received $50,000. The arrangement contemplates two further tranches of approximately $50,000 each following the filing and the effectiveness, respectively, of a resale registration statement. The Company also agreed to issue 250,000 commitment shares. | |
| ● | Equity Purchase Agreement. On August 3, 2026, the Company entered into a $7.5 million Equity Purchase Agreement with Lambda Ventures LLC. Financing capacity under an equity line is not cash on hand: sales require an effective registration statement and are subject to volume and pricing limitations. The Board has determined that the facility will be used cautiously, preferably when trading volumes support efficient drawdowns, and that every drawdown requires prior Board approval. The Company agreed to issue 750,000 commitment shares. | |
| ● | GS Capital note extension. On September 13, 2026, GS Capital Partners, LLC agreed to extend the maturity of its $150,000 note to March 13, 2027, with $15,000 added to principal and the 250,000 returnable shares becoming non-returnable. The extension provides additional time to manage repayment while the Company prioritizes completion of Porto and its financing strategy. | |
| ● | Under the GS Capital Partners, LLC note, if the Company receives $2,000,000 or more in cash proceeds from any registration statement, including sales under the Equity Purchase Agreement, the holder may require up to 100% of those proceeds to be applied to repay the note. The Company intends to repay the GS Capital Partners, LLC note as soon as its financing permits. See Note 10 to the financial statements. |
At September 30, 2026, the Company's convertible notes had aggregate principal of $370,200, accrued interest of $17,726 and derivative liabilities of $724,850. The May 2026 notes became convertible on November 9, 2026. Conversions would be settled in shares at a discount to market and would dilute existing stockholders. See Note 10 to the financial statements.
Going Concern
The Company's recurring losses, working capital deficit and reliance on additional financing raise substantial doubt about its ability to continue as a going concern within one year after the date the financial statements are issued. Management's plans, including the financings described above, do not alleviate that substantial doubt. See Note 2 to the financial statements.
Funding Strategy and Capital Requirements
Management intends to match sources of financing to the underlying expenditure. Parent-company financing is expected to support engineering, corporate administration, intellectual property, SEC compliance and working capital, while larger renewable methanol plants are expected, where feasible, to rely on project-level financing, infrastructure capital, equipment finance, strategic investors and non-dilutive grant support. There can be no assurance that any anticipated financing will be available on acceptable terms or that grant conditions and counterpart-funding obligations will be satisfied.
The Portuguese expansion grant does not eliminate the need for counterpart funding. The first grant tranche is expected to be approximately €3 million and to require an equity contribution of approximately €800,000, currently contemplated as approximately €400,000 from the Company and approximately €400,000 from MO.RE.DA. The initial 3 TPD RDF reference module also requires funding for transport, installation, commissioning and working capital. These project obligations should be distinguished from the Company's corporate liquidity position.
Management is also targeting a listing on the Nasdaq Stock Market, currently by the end of March 2027, subject to securing financing for the associated professional, regulatory and listing costs, satisfying the applicable listing standards and market conditions. There can be no assurance that a listing will be achieved.
Commercial Development
Portugal: Porto Renewable Methanol Platform
During the quarter, management continued manufacturing and implementation planning for its first commercial modular waste-to-methanol reference facility near Porto, Portugal. The planned initial installation processes approximately 3 TPD of RDF to produce approximately 1 metric tonne per day of methanol, subject to feedstock quality, uptime and operating performance. Assembly of the gasification section into containerized skid modules progressed in India under the supervision of the Company's Chief Technology Officer, and the methanol synthesis section awaited delivery of catalyst and certain components. Site preparation, including a weather-protection roof, continued in Porto. The strategy is to complete as much assembly and testing as possible in India before shipment to reduce installation and commissioning risk. The plant was not commissioned at September 30, 2026.
The Company advanced the project structure with MO.RE.DA., including the restructuring of HyOrc Green Fuels, Lda. as a 50/50 Portuguese joint venture. The project site is associated with MO.RE.DA.'s operations in the Porto region. The project remains subject to applicable regulatory authorizations, installation, commissioning, financing and commercial arrangements. The Company intends to complete due diligence on MO.RE.DA. before deciding whether to exercise its option to acquire a 50% interest.
In July 2026, the Portuguese project received approval for approximately €6.7 million under the STEP program for a proposed expansion to approximately 35 TPD RDF input and approximately 8 metric tonnes per day methanol output. The grant is for the larger expansion project, not the initial 3 TPD RDF reference module, and grant approval should not be interpreted as receipt of unrestricted corporate cash or confirmation that all conditions for disbursement have been met. The Company continues to work on long-term methanol offtake relationships, including with PRIO BIO and Gunvor. Expressions of interest, letters of intent and non-binding term sheets do not constitute guaranteed sales or revenue.
Bulgaria: Waste-to-Methanol Development
During the quarter, the Company continued technical and commercial development of a proposed Bulgarian waste-to-methanol project with OnEnergy in connection with an application under the European Union Innovation Fund. HyOrc's scope included gasification, syngas conditioning and methanol synthesis engineering. No revenue was recognized from the project. See Subsequent Events below.
Project Phoenix: Rail Decarbonization
The Company continued developing Project Phoenix, a program to retrofit an existing locomotive using its external combustion and ORC-based power technology. Following the lack of progress on a previously anticipated infrastructure financing proposal, the Company began forming a dedicated UK joint venture vehicle with GB Railfreight ("GBRf") through which Project Phoenix can be financed and through which UK government funding programs, including Innovate UK, may be pursued. The Board approved a TÜV SÜD Independent Safety Assessment program of approximately €125,000, to be funded from Project Phoenix investment rather than existing working capital. The existing memorandum of understanding with GBRf is non-binding, and no grant award, completed retrofit or binding commercial order should be inferred from these discussions.
United Kingdom: Distributed Power Generation
The Company continued evaluating opportunities to apply its externally fired ORC technology to industrial, mining and data-center power requirements, including discussions with Platform Energy, a potential stationary power opportunity with Cornish Lithium, and a potential flare gas-to-power opportunity. Paid engineering work relating to integration of IPG's flameless combustor was confirmed. The Board has determined that the Company will not undertake unpaid demonstration projects; potential projects are to be structured as paid pilots. These discussions remained developmental as of quarter-end; commercial deployment depends on site-specific engineering, permitting, fuel arrangements, financing and binding customer contracts.
India: Engineering, Manufacturing and Government Opportunities
HyOrc India Private Limited remained an important component of the Company's engineering and manufacturing strategy. The Company continued evaluating Indian commercial opportunities, including modular ORC power systems and a prospective geothermal application with Oil and Natural Gas Corporation ("ONGC") in Ladakh. On September 2, 2026, representatives of the Rural Development Department of the Government of Tamil Nadu inspected the Company's manufacturing facility, following which the Company submitted an expression of interest for decentralized RDF-to-energy, syngas and methanol projects under a public-private partnership model. Subsequent government correspondence is discussed under Subsequent Events. Expressions of interest and proposals do not constitute awarded contracts or recognized revenue.
Technology Validation and Commercial Readiness
The Company continued to build upon the independent Bureau Veritas verification of its pilot RDF-to-methanol process completed earlier in 2026. That verification provides evidence of the process demonstrated under witnessed pilot conditions; it is not a guarantee of performance or economics for the planned Porto commercial installation. Sustained operation of the first reference module remains a principal next milestone. The Company's broader validation strategy includes independent engineering reviews, application-specific safety assessments, customer due diligence, operating data and commercial certification as required.
World Methanol Conference
The Company presented at the World Methanol Conference in Rotterdam on October 1, 2026, positioning HyOrc around its RDF and legacy-waste gasification platform and its ability to produce competitive green methanol, and engaged with industry participants regarding potential commercial applications and collaboration. These discussions did not result in binding commercial agreements.
Strategic Interest
During the quarter, the Company received an unsolicited approach from LAB7, operating within the Saudi Aramco innovation ecosystem, regarding possible investment and strategic collaboration, and held discussions with Hinterland LLC regarding a potential $500,000 convertible note investment. No investment from either party had been completed as of the date of this report.
Corporate Development and Capital Markets
During the quarter, the Company continued strengthening its reporting, financing and institutional engagement infrastructure. The Board resolved that all material decisions are to be documented through formal minutes and, where appropriate, written resolutions. The Company maintained its OTCQB market presence, continued its investor-awareness programs with Stonegate Capital Partners and SmallCapVoice, and pursued financing strategies intended to support commercialization and its longer-term objective of a national securities exchange listing. The Company's capital markets objectives do not assure a listing, transaction or financing outcome.
Management continued working with its independent registered public accounting firm on interim financial statement reviews and reporting matters. The reviews for the March 31 and June 30, 2026 periods were completed in October 2026, subsequent to the end of the quarter.
Industry Trends
Management believes that demand for lower-carbon liquid fuels, waste diversion, decentralized generation and industrial energy efficiency creates opportunities for technologies capable of converting RDF and waste heat into marketable energy products. The commercial outlook remains subject to fuel pricing, feedstock composition, environmental and waste regulations, certification standards, infrastructure costs and the availability of project finance.
Renewable methanol may be used in marine fuels and chemical applications, but the marketability and regulatory classification of methanol produced from RDF depend on feedstock composition, lifecycle greenhouse-gas accounting, product specifications and jurisdiction-specific requirements. Management intends to establish product quality and applicable sustainability credentials as projects are commissioned.
Subsequent Events
Completion of Interim Reviews
In October 2026, Suri & Co. completed its reviews of the Company's interim financial information for the periods ended March 31 and June 30, 2026 under PCAOB AS 4105. The Company filed amendments to its Quarterly Reports on Form 10-Q for those periods to disclose completion of the reviews. The financial statements in those reports were not changed.
Portugal Deployment Timetable
Subsequent to quarter-end, management's target for first commercial deployment of the Porto reference module shifted to the first quarter of 2027. The schedule remains subject to manufacturing completion, shipment, installation, permits, financing and commissioning.
Bulgaria: OnEnergy
On October 21, 2026, OnEnergy communicated a purported termination of the Company's participation in the proposed Bulgarian project following the unsuccessful EU Innovation Fund application for the wider three-stage project. HyOrc disputes the basis and validity of that position and has reserved its contractual and intellectual property rights. The parties have discussed restructuring their relationship or a mutually agreed termination of the existing agreement. No outcome is assumed.
McKinney Litigation Settlement
On November 2, 2026, the Company settled the litigation brought by Daniel S. McKinney and Coldway Limited, LLC. On November 4, 2026, the court entered a stipulation and order dismissing the action with prejudice, and no monetary payment is made by any party. See Part II, Item 1, and Note 12 to the financial statements.
Tamil Nadu
Following the September 2, 2026 inspection, the Kanniyakumari District Rural Development Agency issued a letter dated November 5, 2026 approving a detailed project report for syngas production from legacy solid waste and identifying approximately 50 cents of land near the Melasankarankuzhi waste collection center. The proposed project contemplates processing approximately 10 TPD of RDF and producing syngas for local industrial customers, subject to execution of a memorandum of understanding and detailed engineering. The project is not yet a source of recognized revenue.
Prewel Labs Syngas Testing
On October 30, 2026, Prewel Labs Pvt. Ltd. issued a test report on a syngas sample associated with the Company's 3 TPD RDF gasification pilot in Kanyakumari, Tamil Nadu. The reported composition by volume was carbon monoxide 39.88%, hydrogen 35.55%, carbon dioxide 20.86%, methane 1.05%, oxygen 1.17% and nitrogen 0.76%, with combined carbon monoxide and hydrogen of 75.43%, water content of 15 mg/m³ and tar content of 12 ppm. The sample was taken before membrane gas separation. These measurements characterize the particular sample tested, not continuous operating performance, commercial-scale methanol yield or satisfaction of downstream synthesis specifications.
Capital Markets Discussions
During October 2026, management explored potential business combinations with special purpose acquisition companies as a possible pathway to a Nasdaq listing. No definitive agreement has been executed, and there is no assurance that any transaction will be agreed or consummated. Management also continued preparing the registration statement associated with its equity financing arrangements.
Outlook
Management's near-term priority is to complete and commission the initial Porto renewable methanol reference installation, demonstrate sustained commercial operating performance, arrange financing and counterpart funding for the proposed expansion, and convert development-stage opportunities into binding revenue-generating projects. In parallel, management intends to continue Project Phoenix, distributed generation opportunities and selected international waste-to-methanol developments, while maintaining SEC reporting and corporate governance obligations.
The Company continues to face substantial execution, financing and liquidity risks. Its planned projects depend on technical performance, feedstock and product specifications, permitting, transport and construction schedules, partner performance, availability of counterpart financing and customer acceptance. Until operating projects begin generating sufficient cash flow, the Company expects to remain dependent on external capital and to face going-concern uncertainty as discussed in its financial statements.
Management believes the developments of the third quarter of 2026, particularly establishment of the Portuguese project structure and STEP grant approval, advanced its commercialization strategy. However, the ultimate financial contribution of these initiatives will depend on their successful funding, commissioning and operation.