Airside D concrete work is building up at TPA

Just a couple of months after Airside D's structural steel started going up, crews are working around the clock creating some truly concrete results across the worksite.

Concrete platforms inside the steel framework have begun appearing on all levels of the building. The concrete is placed onto metal decking that has been reinforced with steel rebar on each floor.

The structural steel has now moved onto the sixth of 19 separate assembly sequences. A second crane was brought onsite in mid-July to help move the more than 7,300 steel members that will comprise the new Airside terminal.

Meanwhile, more workers have completed the building's foundation and have been placing concrete for the rest of Airside D's ground floor and the apron for aircraft across the worksite. Much of that work has been done overnight to mitigate risk and take advantage of cooler temperatures, which allow for better quality control for the concrete.

The existing apron is being demolished panel by panel and crushed onsite to be recycled into the properly sized aggregate (think different sizes of gravel) as that is used as six inches of underlayment for the new concrete.

The ground floor slab-on-grade of Airside D is eight inches of concrete placed over this recycled aggregate while the apron concrete, which needs to withstand the pressure from aircraft that can weigh several hundred tons, is 18 inches thick. When the project is completed, workers will end up placing almost 85,000 cubic yards of concrete for the apron alone.

The dry weather earlier this summer has kept all the work on schedule, with no major disruptions so far.

Other parts of the project that have reached milestones lately:

  • The final steel and concrete guideway beams for the future Airside shuttles have been placed across the support piers to the steel supports for the shuttle station. Workers are now creating running surfaces for the shuttles and infrastructure for the baggage delivery system.
  • Water and sewage pipes are being buried across the worksite with plans for connecting to city water later this year.
  • Elevators and escalators are being fabricated for eventual installation across the building.
  • A slightly new route for Bessie Coleman Boulevard is being cleared to connect the road with the future Airside D truck court underneath the shuttle guideway.
  • Precast concrete panels to sheath the outside of the building are scheduled to be installed in September.

TPA broke ground on Airside D in December 2024, with construction scheduled to be open to the public in 2029. The design-build team for the project is led by construction company Hensel Phelps, with architecture and engineering company HNTB Corporation, in association with Gensler.

To sign up for TPA's Airside D monthly newsletter and get more information about future business opportunities, click here.

Click on an image below to enlarge and download it:

Tampa International Airport - Hillsborough County Aviation Authority published this content on August 04, 2026, and is solely responsible for the information contained herein. Distributed via Public Technologies (PUBT), unedited and unaltered, on August 04, 2026 at 15:15 UTC. If you believe the information included in the content is inaccurate or outdated and requires editing or removal, please contact us at [email protected]