PGE - Portland General Electric Company

12/16/2025 | Press release | Distributed by Public on 12/16/2025 12:29

Massive turbine shut off valve replaced at Round Butte Hydroelectric Facility

PORTLAND, Ore. - Portland General Electric (PGE) and The Confederated Tribes of Warm Springs (CTWS) are undertaking a complex project to replace the original turbine shut off valves at their jointly owned Round Butte Hydroelectric Facility. This critical infrastructure upgrade demonstrates PGE's and CTWS's commitment to maintaining reliable, clean hydroelectric power generation while supporting the continued safe operation of this critical regional resource.

"These are the original turbine shut off valves that were installed when the facility was first built in 1964," said Jordan Messinger, PGE principal project manager. "After more than six decades of reliable service, we are replacing the valves to support the facility's continued safe and efficient operation for decades to come."

Located about eight miles southwest of Madras, Oregon, the Round Butte facility forms Lake Billy Chinook with its 440-foot-tall earthen dam. The powerhouse contains three Francis turbine units with a combined capacity of 350 MW and supplies water to the Deschutes River.

The 140 ton, 15-foot-wide turbine shut off valves are the primary safety mechanism for controlling water flow to the turbines. These critical components enable emergency shut off capabilities and make it possible for operators to let water out of the turbines during maintenance operations.

The project's journey began in early 2019 with initial funding and the selection of an engineering consultant. Phase one construction kicked off in July 2025, and Messinger said the replacement project should be completed by February 2026. Next July, the team will begin installing the other two turbine shutoff valves and that will be completed the following February. The project budget is about $55 million.

"We've assembled a team of specialized engineers and industry professionals with the expertise needed to handle every aspect of this project," said Messinger. "From installation to operation, we're going to make sure everything we do meets our rigorous standards for safety and reliability."

Messinger and his team have overcome several significant challenges in the years leading up to construction. First and foremost are the valves themselves - the valve body and disc alone weigh about 140 tons and must be lowered into the powerhouse as a single unit. When fully installed, the total system weight reaches approximately 250 tons. Another challenge is an incredibly limited pool of global manufacturers capable of designing and fabricating valves of this size. It took two years to design, fabricate, and test the new valves in Europe before they could be transported to the dam.

Despite the challenges, Messinger and his team successfully installed the first of three turbine shutoff valves in November.

"This upgrade represents a significant investment in PGE's renewable generation resources and the local economy," said Messinger. "Together with CTWS, we're supporting native fish populations through science-backed initiatives, providing clean electricity to over 150,000 homes, and maintaining a certified low-impact facility that employs 33 local residents across central Oregon communities."

With a 60-year lifespan, these new valves will help lower operations and maintenance costs - savings that will benefit all PGE customers - while enabling Round Butte Dam to continue generating carbon-free energy well into the future.

PGE - Portland General Electric Company published this content on December 16, 2025, and is solely responsible for the information contained herein. Distributed via Public Technologies (PUBT), unedited and unaltered, on December 16, 2025 at 18:29 UTC. If you believe the information included in the content is inaccurate or outdated and requires editing or removal, please contact us at [email protected]