05/08/2025 | Press release | Distributed by Public on 05/08/2025 05:35
Soluna Announces Monthly Business Update
ALBANY, NY, May 8, 2025 - Soluna Holdings, Inc. ("Soluna" or the "Company"), (NASDAQ: SLNH), a developer of green data centers for intensive computing applications, including Bitcoin mining and AI, announced its April 2025 project site-level operations, developments, and updates.
The Company has provided the following Corporate and Site Updates.
Key Company Metrics:
The monthly metrics are now available here.
Corporate Highlights:
● | Term Sheet Signed for Power for New 120MW Wind-Powered Data Center "Project Hedy" in Texas - Expected to expand Soluna's presence in ERCOT and strengthen commitment to sustainable computing. Learn more here. | |
● | Land Secured for 166MW Project Kati - Marks one of the Company's largest renewable-powered computing sites in development. Read more here. | |
● | Term Sheet Signed for Power for New 100MW Wind-Powered "Project Ellen" Planned to Power AI & Bitcoin Workloads - Designed to meet rising demand for clean, high-performance computing infrastructure. Details here. | |
● | Blockware Deal Expands Hosting at Project Dorothy 2 - New agreement grows Bitcoin hosting capacity at Soluna's flagship Texas site. Learn more here. | |
● | New Blog - The Soluna team explores the sustainable AI landscape and the competitive advantages of Renewable Computing. Read our latest blog here. |
Key Project Updates:
Project Dorothy 1A (25 MW, Bitcoin Hosting) / Project Dorothy 1B (25 MW, Bitcoin Prop-Mining):
● | The site has experienced several abnormally severe weather events that have impacted availability for the month. | |
● | Preparations are underway to implement active cooling measures for power infrastructure in advance of the summer heat and 4CP period. |
Project Dorothy 2 (Under Construction, 48 MW, Bitcoin Hosting):
● | Customer deployments are ongoing for Phase 1 with multiple buildings online and hashing. | |
● | Substantial completion of construction for Phase 1 will be achieved in the next three weeks. | |
● | Progress on Phase 2 is accelerating as all buildings have been erected, and electrical installation is underway. | |
● | Building materials are arriving on site for installation on Phase 3. |
Project Sophie (25 MW, Bitcoin Hosting with Profit Share, AI Hosting):
● | The site has continued to operate very well during optimal weather conditions. | |
● | The team achieved a new peak hashrate of 1 EH/s at the site following recent deployments. | |
● | A 3.3MW fleet upgrade will take place over the next two weeks to expand existing customers. |
Project Kati (Under Development, 166 MW, Bitcoin Hosting and AI):
● | The Phase 1 (83 MW) substation upgrade is complete. | |
● | The construction bid process for Phase 1 (83 MW) of Bitcoin Hosting will be concluded soon. | |
● | Long lead equipment, including medium voltage switchgear, transformers, and busway orders have been secured. |
Customer Success:
● | Soluna has completed deployment of the first 350 next-generation S21+ miners of the recently contracted new partnership with Blockware. The initial deployment will target 5 MWs of S21+ machines and is expected to continue to ramp into June at the new Dorothy 2 site. | |
● | Project Dorothy 2 contracting continues for May-September 2025; 48 MWs with new partners are in the final stages of negotiation. | |
● | Partnership growth and expansion at Project Sophie. This would be our 3rd partnership expansion with this hyperscale partner. |
View Soluna's recent AMA here.
Soluna's glossary of terms can be found here.