September Project Update: NE Halsey St. Safety & Access to Transit Project

News Article
Published
September 2, 2025 9:17 am

(September 2, 2025) Construction crews are continuing work on NE Halsey Street between NE 84th and NE 92nd avenues as part of the larger Portland Bureau of Transportation (PBOT) Safety and Access to Transit Project.

Throughout September, crews will be working on NE Halsey Street between NE 84th and NE 92nd avenues. Their work will include:

  • Clearing obstructions to make room for sidewalk construction
  • Installing new accessible curb ramps and driveway connections on the north side of NE Halsey Street between 85th and 92nd avenues
  • Building underground stormwater infrastructure to help reduce flooding, protect nearby properties and improve travel conditions for all users.

PBOT is working to reduce impacts on neighbors and businesses during construction. Community members should expect some traffic flagging on NE Halsey near active work areas. Crews will notify neighbors and businesses directly about any work that may temporarily affect property access.

For more detail, visit the construction schedule on the project website: NE Halsey Construction Schedule

City of Portland, OR published this content on September 02, 2025, and is solely responsible for the information contained herein. Distributed via Public Technologies (PUBT), unedited and unaltered, on September 02, 2025 at 23:27 UTC. If you believe the information included in the content is inaccurate or outdated and requires editing or removal, please contact us at [email protected]