01/23/2026 | News release | Distributed by Public on 01/23/2026 15:17
The calendar change to 2026 not only marked the beginning of a new year but also the start of the final stretch toward completion of the City of Columbia Utilities ' McBaine Water Treatment Plant Improvement Project.
Contractor Bowen Engineering began construction on the project in September 2024. With construction progressing as scheduled, the City is on track to complete the project in August.
The City expects the project to restore the plant's capacity to treat 32 million gallons of water per day. It includes rehabilitation and replacement projects that will enhance the facility's performance and extend its service life.
Here are updates on key elements of the improvement project.
Clarifier Trains
Each of the four clarifier trains has two aspects:
City Utilities has restored Train 1 with all-new equipment, pumps and weirs and expects it to be fully back in service at the beginning of April. Train 1 is the third of the four trains that the City has restored.
Crews removed all old equipment from the basins to repair the concrete, then rebuilt them from the ground up. They then refitted the primary basins with clarifiers and weirs. Crews also replaced the clarifiers in the secondary basins with baffle curtains. Baffles slow water flow, allowing particles to settle before filtration.
Chemical Building
The City expects the new chemical building to be operational by mid-April. The building will not only store chemicals but also house feed systems for chlorine gas, liquid ammonium sulfate and fluoride.
Other projects at the water treatment plant include:
For construction updates, residents can follow the City Utilities blog at the BeHeard McBaine Water Treatment Plant Improvement Project page.
For background on the water treatment plant improvement project, visit the City's McBaine Water Treatment Plant Improvement Project page.