01/08/2025 | Press release | Distributed by Public on 01/08/2025 07:11
|
• |
Self-mined Bitcoin: 145 Bitcoins.
|
|
• |
Mining Rig Manufacturing and R&D:
|
|
o |
SEALMINER A1: Mass production of approximately 3.7 EH/s of mining rigs remains on track with 0.3 EH/s powered on, 0.3 EH/s delivered for installation, 0.6 EH/s in-transit to data centers and 2.5 EH/s in production.
|
|
o |
SEALMINER A2:
|
|
o |
Production of approximately 35 EH/s of mining rigs through Q3 2025 remains on track. First trial batch of Air cooling rigs are expected to be delivered to our mining datacenters for testing in January 2025.
|
|
o |
~29,000 units (~7 EH/s out of the 35 EH/s) of SEALMINER A2s allocated for external sale (both Air cooling and Hydro cooling), have been ordered by customers, including the full receipt of related down payments from customers. These mining rigs are expected to begin shipment in March through Q2 2025.
|
|
o |
SEALMINER A3:
|
|
o |
SEAL03 initial tape-out sample wafers with an expected chip efficiency of 10 J/TH are expected in Q1 2025.
|
|
o |
SEALMINER A4:
|
|
o |
SEAL04 R&D remains on track to achieve industry leading efficiency of 5 J/TH with anticipated initial tape-out in Q3 2025.
|
|
• |
HPC/AI:
|
|
o |
Discussions are ongoing with multiple development partners and potential end users for selected sites.
|
|
o |
Bitdeer AI cloud services powered by NVIDIA DGX SuperPod with H100 systems maintained an average utilization rate of approximately 90% for the month.
|
|
o |
Co-hosted VLM Bootcamp with NVIDIA for participants to explore and create with VLM via Bitdeer AI Studio.
|
|
• |
Hosting:
|
|
o |
Client-hosted machines decreased by 2,000 units while overall hashrate increased by 0.8 EH/s due to higher efficiency machines hosted by clients.
|
|
• |
Infrastructure:
|
|
o |
Tydal, Norway, 40 MW phase 1 expansion has completed installation of transformers, with delivery and installation of electrical equipment currently in progress. The energization is currently pending for regulatory approval.
|
|
o |
Rockdale, Texas, USA, 100 MW hydro-cooling conversion is on track for phased completion during Q1 2025.
|
|
o |
Jigmeling, Bhutan, 500 MW construction is on track with the primary substation expected to be completed by Q1 2025.
|
|
o |
Massillon, Ohio, USA, 221 MW substation construction started and is expected to be completed in Q3 2025. Building design is completed and construction is underway, expected to be completed in phases between Q3 and Q4 2025.
|
|
o |
1.1 GW of new power capacity is on track to come online in 2025.
|
|
• |
Financing:
|
|
o |
Full repayment of the outstanding principal balance of US$10 million of the senior secured notes issued to sellers in the previously announced acquisition of TROLL HOUSING AS and TYDAL DATA CENTER AS.
|
Metrics
|
Dec 2024
|
Nov 2024
|
Dec 2023
|
Total hash rate under management1 (EH/s)
|
21.6
|
20.7
|
21.0
|
- Proprietary hash rate
|
8.9
|
8.8
|
8.4
|
• Self-mining
|
8.5
|
8.2
|
6.7
|
• Cloud Hash Rate
|
0.0
|
0.2
|
1.7
|
• Delivered but not hashing
|
0.4
|
0.4
|
-
|
- Hosting
|
12.7
|
11.9
|
12.6
|
Mining machines under management
|
175,000
|
178,000
|
215,000
|
- Self-owned2
|
85,000
|
86,000
|
86,000
|
- Hosted
|
90,000
|
92,000
|
129,000
|
Bitcoins mined (self-mining only)
|
145
|
150
|
434
|
Bitcoin held
|
594
|
443
|
43
|
|
• |
Self-mining refers to cryptocurrency mining for the Company's own account, which allows it to directly capture the high appreciation potential of cryptocurrency.
|
|
• |
Cloud Hash Rate offers hash rate subscription plans and shares mining income with customers under certain arrangements. The Cloud Hash Rate stated above reflects the contracted hash rate with customers at month-end. However, throughout the month, the Cloud Hash Rate may transition to Self-mining hash rate if customers opt to not make their monthly electricity payments for various reasons.
|
|
• |
Hosting encompasses a one-stop mining machine hosting solution including deployment, maintenance, and management services for efficient cryptocurrency mining.
|
|
• |
Cooling system will be delivered and installed in phases in Q1 2025.
|
|
• |
Planning for phased energization between January and March 2025.
|
|
• |
Installation of the transformers has been completed, with the delivery and installation of electrical equipment currently in progress. Additionally, the procurement and delivery of containers and hydro-cooling systems are underway, and drainage systems construction is ongoing.
|
|
• |
Tydal, Norway Phase 1 40 MW expansion pending regulatory approval. Energization of the full 175 MW site is reasonably expected to be no later than mid-2025.
|
|
• |
Substation construction is underway and is expected to be completed in Q3 2025.
|
|
• |
Building design is completed and construction has begun earlier than expected, estimated to be completed in phases between Q3 and Q4 2025.
|
|
• |
Estimated energization timeline remains on track for mid-to-late 2025.
|
|
• |
Construction of transformer and container foundations in progress and will be completed in phases, with the last phase expected by the end of February 2025.
|
|
• |
132kb/140MW and 220kv/360MW substation designs are completed with construction anticipated to be ready by the end of Q1 2025.
|
|
• |
Orders for the procurement of transformers and electrical equipment have been placed, with delivery and installation work to be completed in phases over Q1 and Q2 2025.
|
|
• |
Procurement and delivery of containers and hydro-cooling systems are in progress, with completion in phases by the end of Q1 2025.
|
Site / Location
|
Capacity (MW)
|
Status
|
Timing4
|
Electrical capacity
|
|||
- Rockdale, Texas
|
563
|
Online
|
Completed
|
- Knoxville, Tennessee
|
86
|
Online
|
Completed
|
- Wenatchee, Washington
|
13
|
Online
|
Completed
|
- Molde, Norway
|
84
|
Online
|
Completed
|
- Tydal, Norway
|
50
|
Online
|
Completed
|
- Gedu, Bhutan
|
100
|
Online
|
Completed
|
Total electrical capacity
|
8955
|
||
Pipeline capacity
|
|||
- Tydal, Norway Phase 1
|
40
|
In progress
|
Pending Regulatory Approval
|
- Tydal, Norway Phase 2
|
135
|
In progress
|
Mid 2025
|
- Massillon, Ohio
|
221
|
In progress
|
Mid-to-late 2025
|
- Clarington, Ohio Phase 1
|
266
|
In progress
|
Q3 2025
|
- Clarington, Ohio Phase 2
|
304
|
Pending approval
|
Estimate 2026
|
- Jigmeling, Bhutan
|
500
|
In progress
|
Mid-to-late 2025
|
- Rockdale, Texas
|
179
|
In planning
|
Estimate 2026
|
Total pipeline capacity
|
1,645
|
||
Total global electrical capacity
|
2,540
|
|
• |