ST. JOSEPH, Mo. - The Missouri Department of Transportation has contracted Herzog Contracting Corp. to replace the approaches to the Pigeon Creek Bridge and Bee Creek Bridge and resurface a section of Interstate 29 from Pigeon Creek in Buchanan County (mile marker 39.8) to the Platte County line (mile marker 31). Work is scheduled to begin on Monday, April 6.

Crews will begin work rebuilding the outside shoulder of the interstate at the Pigeon Creek and Bee Creek approaches. Crews will then replace the approaches on the southbound bridges then move to the northbound bridges.

Once the approaches are complete, crews are scheduled to resurface I-29 beginning in August 2026.

Traffic Impacts: I-29 will be narrowed to one lane with an 11-foot width restriction in place. Motorists should expect delays.

The resurfacing is scheduled to be completed by mid-October 2026.

All work is weather-permitting, and schedules are subject to change. MoDOT asks drivers to work with us by always buckling up, keeping your phones down, slowing down and moving over in work zones. Know before you go and check what work zones you might encounter at traveler.modot.org.

Get project and work zone news straight to your email by signing up for eUpdates. Information is also available 24/7 by calling 888-ASK-MODOT (275-6636) or visiting www.modot.org/northwest.

Facebook | X | Instagram

Take the Challenge! Buckle Up/Phone Down

###

State of Missouri published this content on March 24, 2026, and is solely responsible for the information contained herein. Distributed via Public Technologies (PUBT), unedited and unaltered, on March 24, 2026 at 19:14 UTC. If you believe the information included in the content is inaccurate or outdated and requires editing or removal, please contact us at [email protected]