Sections of streets will undergo various stages of resurfacing that will affect traffic flow in those areas. Specific streets affected, and for what work, are listed below. These jobs are part of the City's 2026 road paving projects and publicized weekly.
Projects happening from March 3-6
The following will involve alternate lanes or full road closures from 7 am to 6 pm.
Merry Oaks Ct. from Ironwood Circle to the end - Lowering structures
Silverwood Ct. from Ironwood Circle to the end - Lowering structures
Birkdale Dr. from Muirfield Dr. to Cardinal Ridge Dr. - Lowering structures
Cedar Bend Ct. from Poplar Grove Trail to the end - Lowering structures
All of Ironwood Circle - Lowering structures
Oak Bend Trail from Poplar Grove Trail to Old Oak Ridge Rd. - Lowering structures
Olympic Ct. from Birkdale Dr. to the end - Lowering structures
Spyglass Dr. from Cardinal Ridge Dr. to Muirfield Dr. Lowering structures
Adonica Ln. from Giovanni Way to Champagne Dr. - Lowering structures
Bald Eagle Dr. from Hanberry Dr. to the end - Lowering structures
Champagne Dr. from Giovanni Way to Adonica Ln. - Lowering structures
Giovanni Way from Merlot Way to the end - Lowering structures
Hanberry Dr. from Horse Pen Creek Rd. to the end - Lowering structures
All of Merlot Way - Lowering structures
Patrick James Way from Giovanni Way to Merlot Way - Lowering structures
Technology Dr. from Bryan Park Rd. to the end - Lowering structures
Lake Hermon Dr. from Corporate Park Dr. to Technology Dr. - Lowering structures
Brushy Creek Dr. from Slilverbrook Dr. to Woodhollow Rd. - Lowering structures
Crystal Hill Ct. from Woodhollow Rd. to the end - Lowering structures
New Market Ct. from Woodhollow Rd. to the end - Lowering structures
Oakville Dr. from Silverbrook Dr. to the end - Lowering structures
Silverbrook Ct. from Silverbrook Dr. to the end - Lowering structures
Silverbrook Dr. from McLeansville Rd. to Taylors Landing Ave. - Lowering structures
Woodhollow Ct. from Woodhollow Rd. to the end - Lowering structures
Woodhollow Rd. from Birch Creek Rd. to the end - Lowering structures
Motorists are encouraged to use alternate routes to avoid work areas, follow detour signs, and adhere to traffic flagger directions.
Work schedules for each job depend on weather conditions and material/equipment availability.
Visit https://www.greensboro-nc.gov/RoadProjects to learn more about lane and road closures and subscribe to receive email notifications about upcoming work on City streets.