Roadway Activity Report for the Lower East and Upper Cumberland (February 19 - 25, 2026)

BRADLEY COUNTY SR-60 widening from the 4-lane north of I-75 (LM 17.2) to SR-306 (LM19.9): During this reporting period, the contractor will perform punch list work on SR-60 in Bradley County. Intermittent lane closures may be necessary while work occurs.
[Summers-Taylor, Inc./Cleveland/CNV130]

BRADLEY COUNTY SR-74 (BROAD ST. N.W.) Utility Work both directions from LM .46 to LM .49: Flagging-assisted lane closures on SR-74 (Broad St.) Between Central Ave NW and 4th St. NW Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 02/19/2026 through 02/20/2026 from 9 am - 2 pm with a rain date of 02/20/2026 (2026-066)

BRADLEY COUNTY SR-74 (SPRING PLACE RD.) Utility Work both directions from LM 11.07 to LM 11.14: Flagging-assisted lane closures on SR-74 (Spring Place Rd) between Clayton LN and Durkee RD SE Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 12/18/25 through 06/18/2026 from 9 am - 2 pm [2025-736]

BRADLEY COUNTY SR-74 [11.445-11.83] from Whaley Road to SR-60 APD-40 drainage improvements: During this reporting period, the contractor will continue storm drain installation and grading work on SR-74. Intermittent flagging operations and shoulder closures will be necessary periodically. Motorists should use caution and reduce speed when traveling through the work zone.
[APAC - Atlantic, Inc./Cleveland/CNZ243]

COFFEE COUNTY I-24 TDOT Contractor both directions from MM 111.2 to MM 110.8: On Thursday night from 8 PM-5 AM, the contractor will close 1 lane of traffic in each direction so that they can take a roadway pavement core on I-24 inside the shoulder area.

CUMBERLAND COUNTY I-40 [304.4-306.6] from MM 304.4 to MM 306.6 bridge repair and resurfacing: The contractor has started working on the bridge repair on I-40 at MM 304.6. Motorists should use caution in the area. [Rogers Group, Inc./Crossville/CNZ290]

CUMBERLAND COUNTY SR-1 (SPARTA HWY.) TDOT Bridge Inspection eastbound at LM 6.35: A routine inspection of the US 70 bridge over the Caney Fork River at log mile 6.35 is scheduled for Monday, February 23, from 8 AM until 2:30 PM. This work will require closure of the eastbound lane. Flaggers will be present to direct traffic through the work zone, so please approach the bridge with caution, obey temporary traffic control devices, be prepared to stop, and be alert to the presence bridge inspection personnel, vehicles and equipment.

CUMBERLAND COUNTY SR-1 (SPARTA HWY.) TDOT Bridge Inspection eastbound at LM 7.05: A routine inspection of the US 70 bridge over Beam Creek at log mile 7.05 is scheduled for Tuesday, February 24, from 8 AM until 2:30 PM. This work will require closure of the eastbound lane. Flaggers will be present to direct traffic through the work zone, so please approach the bridge with caution, obey temporary traffic control devices, be prepared to stop, and be alert to the presence bridge inspection personnel, vehicles and equipment.

CUMBERLAND COUNTY SR-1 (US-70 E.) TDOT Bridge Inspection eastbound at LM 21.95: A routine inspection of the US 70 bridge over Daddys Creek at log mile 21.95 is scheduled for Wednesday, February 25, from 8 AM until 2:30 PM. This work will require closure of the eastbound lane. Flaggers will be present to direct traffic through the work zone, so please approach the bridge with caution, obey temporary traffic control devices, be prepared to stop, and be alert to the presence bridge inspection personnel, vehicles and equipment.

CUMBERLAND COUNTY SR-24 [0-0.16] from Putnam County Line to C189 bridge repair: The contractor has started working on the bridge repair on I-40 at MM 304.6 or SR-24 at LM 0.24. The contractor is working behind the guardrail. Once additional work begins, additional lane closures may be necessary. Motorists should use caution in the area.
[Rogers Group, Inc./Crossville/CNZ290]

CUMBERLAND COUNTY SR-24 [15.056-15.56] from Crossville city limits to Seventh-Day Adventist Church and School bridge replacement: The contractor has closed SR-24 at LM 15.06 to LM 15.6. This closure will remain in place for the duration of the project. The posted detour is along SR-462 and SR-1. The contractor will be working on general clearing activities and utility work initially. Once initial work is completed, the Contractor will proceed with the replacement of the bridge over the Obed River. Motorists should use caution and utilize the posted detour. RESTRICTIONS: Both lanes of SR-24 are closed at LM 15.06 to LM 15.6.
[Mid-State Construction Company, Inc./Crossville/CNZ206]

CUMBERLAND COUNTY SR-28 (US-127 S.) Utility Work both directions from LM .44 to LM 5.94: Northbound and southbound Lane closures on SR-28 (HWY 127 S.) between Lowes Gap Rd. and Willard Brown Rd. Motorists should reduce speed and be prepared to stop. Arrow board/message boards, flaggers, and barrels/cones will be present, 10/30/25 through 02/25/2026 from 9 am - 2 pm. [2025-659]

CUMBERLAND COUNTY SR-28 (US-127) bridge construction and paving from north of I-40 (LM 17.8) to near Potato Farm Road (LM 22.7): The contractor continues grading activities throughout the project limits. Temporary lane closures and/or periodic traffic stoppages will be necessary for construction activities. The contractor has scheduled to close Lawson Road at the intersection of Cline Road to install a drainage pipe beginning on 02/23/26. A detour has been posted to utilize Tabor Loop. Flaggers and advanced warning signs will accompany any closures. Motorists should use caution when traveling through the work zone as traffic patterns change.
[Jones Bros. Contractors, LLC/Crossville/CNV009]

CUMBERLAND COUNTY SR-299 (ROCKWOOD AIRPORT RD.) Utility Work both directions from LM 1.41 to LM 1.57: Northbound and Southbound Lane closures on SR-299 (Airport Road) at Golliher rd. near the airport Motorists should reduce speed and be prepared to stop. Arrow board/message boards, flaggers, and barrels/cones will be present, 02/16/2026 through 02/18/2026 with a rain date of 02/19/2026 from 9 am - 2 pm. [2025-925]

CUMBERLAND AND FENTRESS COUNTY SR-28 (US-127) widening from near N. Lowe Rd (LM 29.2) to north of SR-62 (LM 1.9): The contractor has shifted traffic to phase 2 on the newly constructed portions of SR-28 LM 0.90 to 1.98 in Fentress County. Work will proceed on the existing alignment of SR-28. Flaggers are being used intermittently as needed to control traffic through the work zone. Motorists are encouraged to use caution, be aware of new traffic signs and pavement markings, and watch for construction equipment and personnel throughout the project.
[Jones Bros. Contractors, LLC/Cookeville/CNV300]

DEKALB COUNTY SR-26 (US-70) grading, drainage, and construction of retaining walls and paving from near SR-53 (LM 2) to near SR-96 (LM 6.1): The contractor will continue normal working activities throughout the project limits. During this work, temporary lane closures are possible, and flaggers will be present. Motorists are encouraged to use caution while traveling through the work zone and should be aware of construction equipment adjacent to the roadway.
[Twin K Construction/Cookeville/CNV012]

FRANKLIN COUNTY SR-50 (LYNCHBURG HWY.) TDOT Maintenance westbound at LM 18.42: Turn lane construction will occur on Franklin SR-50 at LM 18.420. Traffic control in place starting Monday, 02/23/2026; the fast lane, westbound, will be closed off in the work zone.

HAMILTON COUNTY I-124 (US-27) from I-24 Interchange to South of the Tennessee River Bridge: Daily lane closures are possible between 9 AM and 3:30 PM as the contractor works along the ramps and 4th Street. Motorists are advised to reduce speed in the work zone and watch for flaggers assisting with traffic control. [Stansell Electric Company, Inc./Chattanooga East/CNY900]

HAMILTON COUNTY I-75 at I-24 Interchange Reconstruction Phase 2: Nightly Lane closures will regularly occur on this project, 9 PM to 6 AM, on I-75 North and South between Exit 1 (East Ridge) and Exit 3A (East Brainerd Road/ SR-320) and on I-24 East and West from Germantown Road to Spring Creek Road, MM182 to MM185, for various construction activities. These closures may temporarily reduce traffic to a single lane. Uniformed police officers will be present in these work zones to assist with traffic management and to enforce traffic laws. Nighttime lane closures from 8 PM to 6 AM are scheduled on I-24 East and West between Germantown Road and through the I-75 interchange for placement of permanent thermoplastic pavement markings, painting/texture coating of retaining/noise walls, and to work on various punch list items. This night work will continue weekly from Sunday through Thursday during the month of February. At times this work may require the temporary closure of exit or entrance ramps from I-24 West and East to North and South Terrace. During these nighttime hours from Sunday (2/22) to Thursday (2/26), the contractor will also need to temporarily close the I-24 West entrance ramp from Germantown Road and the I-24 East exit ramp (Exit 183) to Germantown Road to repair and repave shoulders along the ramps. Message boards, signs and detours will be provided to warn motorists of all these closures and to guide them to the next available exit or entrance ramp. The contractor will have daytime lane closures (9 AM to 3 PM) on North and South Terrace for various pavement repairs, milling and final pavement. This work is scheduled to take place Monday through Friday, weather permitting, and will occur weekly through February until completed. As this work on North and South Terrace progresses it will be necessary to temporarily close exit and entrance ramps from I-24 so that crews can safely pave these areas. Other short-term, temporary ramp closures may be needed in the future to complete small areas (i.e. ramp gore areas, shoulders, lane transitions, etc.) skipped during the normal full-width paving of the travel lanes. Message boards, signs and detours will be provided to warn motorists of these closures and to guide them to the next available exit or entrance ramp. The contractor plans to begin working on shifting and opening all lanes on I-75 North in their final alignment starting next week from Sunday (2/22) through Thursday (2/26). The first work will occur on I-75 North from south of the bridge over the CSX railroad (MM 2) to the East Brainerd Road interchange (MM 3). There will be nighttime lane closures (9 PM to 6 AM) on I-75 North, and during some of these nights the exit ramp from I-75 North to East Brainerd Road will have to be temporarily closed to safely remove conflicting lane lines and establish the new final traffic lane alignment. Message boards, signs and detours will be provided to warn motorists of these closures and to guide them to an available exit ramp detour from I-75 North to East Brainerd Road. Most of the remaining work items on this project are temperature and weather sensitive. If any of them are canceled due to inclement conditions, they will be rescheduled to take place on the next available day and time when adequate conditions exist. It may also be necessary to do short duration (15 to 30 minutes) rolling roadblocks during the day or night for patching potholes, clearing debris or repairing guardrail, attenuators, etc.
[Wright Brothers Construction Company, Inc./Maj Prj - Blevins/DB2101]

HAMILTON COUNTY I-75 at the Hamilton Place Mall interchange: The SR-153 southbound ramp to I-75 northbound has been reduced to one lane. Traffic shifts have been implemented on I-75 northbound, Shallowford Road entrance ramps, and Shallowford Road exit ramps and Hamilton Place Mall exit ramp. Hamilton Loop Road is closed for retaining wall construction and storm drainage installation between the intersections near Markman's Jewelers and Texas Roadhouse. The speed limit has been reduced on I-75 throughout the project limits. Nightly lane closures are permitted 8 PM to 6 AM. Motorists should use caution, paying attention to construction signage and watching for construction vehicles and personnel.
[Summers-Taylor, Inc./Chattanooga West/CNX358]

HAMILTON COUNTY SR-153 (STATE HWY. 153) Utility Work, both directions from LM 2.4 to LM 2.8: Flagging-assisted lane closures on SR-153 (SR HWY 153) at the jersey pike exchange. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 02/22/2026 with a rain date of 03/01/2026, from 6 am -11 am [2025-511)

HAMILTON COUNTY SR-2 (BROAD ST.) Utility Work both directions from LM 6.17 to LM 6.66: Flagging-assisted lane closures on SR-41 (Broad St.) between Williams St. and St. Elmo Ave. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 01/29/2026 to 02/18/2026 from 9 am - 2 pm [2025-907)

HAMILTON COUNTY SR-2 (DODDS AVE.) Utility Work both directions from LM 10.36 to LM 10.60: Flagging-assisted lane closures on SR-2 (Dodds Ave.) Between 14th St and 19th St. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 02/16/2026 through 02/18/2026 from 9 am - 2 pm (2026-068)

HAMILTON COUNTY SR-2 (LEE HWY.) Utility Work both directions from LM 18.80 to LM 18.86: Flagger-assisted lane closures on SR-2 (Lee Hwy) between McCutcheon Rd and Elm Dr. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 10/2/25 to 02/28/2026 from 9 am - 2 pm. [2024-338]

HAMILTON COUNTY SR-38 (BIRMINGHAM HWY.) Utility Work both directions from LM 2.50 to LM 2.59: Flagging-assisted lane closures on SR-11 (Birmingham HWY). near Modern Industries Pkwy. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 02/23/2026, with a rain date of 02/25/2026 from 9 am - 2 pm [2025-1001)

HAMILTON COUNTY SR-58 (HWY. 58) Utility Work both directions from LM 16.70 to LM 17.08: Flagging-assisted lane closures on SR-58 (Hwy 58) between Crowes Nest Dr and Sims rd. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 02/17/2026 from 9 am - 2 pm with a rain date of 02/20/2026 [2025-1017)

JACKSON COUNTY SR-135 (DODSON BRANCH HWY.) TDOT Maintenance northbound from LM 11.8 to LM 12.0: SR135 will be reduced to one lane due to a soil nail project starting 2/5/26 until the project is completed. Traffic signals are in place. Motorists are encouraged to slow down and use caution when in the area.

JACKSON COUNTY SR-53 [17.46-17.6] from south of Hurricane Branch to Near Hurricane Branch Lane culvert replacement: The contractor has begun vegetation clearing adjacent to the roadway. Flaggers may be used intermittently as needed to control traffic through the work zone. Motorists are encouraged to use caution, be aware of new traffic signs and pavement markings, and watch for construction equipment and personnel throughout the project. The contractor will completely close the road through the work zone beginning 03/04/26. Motorists will need to use the posted detour route on this date. [Cleary Construction, Inc./Livingston/CNZ250]

MARION COUNTY SR-108 [2.8-3.24] slide mitigation: The contractor will be performing slide mitigation operations, including grading, drainage and paving on SR-108 in Marion County at LM 2.8. The roadway will be reduced to one lane controlled by temporary traffic signals. The project completion date is 08/31/2027. Please use caution when driving through the work zone.
[Wright Brothers Construction Company, Inc./Dunlap/CNZ226]

MARION COUNTY SR-150 (US-41) Utility Work both directions from LM .28 to LM .43: Flagging-assisted lane closures on SR-150 (Hwy 41) in front of the jasper middle school. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 02/19/2026 from 9 am - 2 pm (2025-989)

MARION COUNTY SR-2 [17.2-17.3] from 17.2 to 17.3 construction: The contractor will be performing grading and drainage operations on SR-2 in Marion County near LM 17.25. This work will require a lane shift for the EB traffic, the WB traffic will be unaffected. Please slow down and use caution when driving through the work zone.
[Talley Construction Company, Inc./Dunlap/CNZ244]

MCMINN COUNTY SR-2 (US-HWY. 11) Utility Work both directions from LM 12.23 to LM 12.78: Flagging-assisted lane closures on SR-02 (Lee HWY) between Rocky Mt Rd. and Vo-Tech Drive Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 02/20/2026 from 9 am - 2 pm with a rain date of 02/23/2026 [2026-012)

MCMINN COUNTY SR-39 construction of a bridge over Middle Creek (LM 13.4): During this reporting period, the contractor will be flagging the roadway to perform work. This flagging operation will only occur during daytime hours.
[Whaley Construction, LLC/Chattanooga East/CNX069]

OVERTON COUNTY SR-111 (BYRDSTOWN HWY.) Utility Work both directions from LM 15.95 to LM 17.52: Flagging-assisted lane closures on SR-52 (Byrdstown Hwy) Between Garnet Mill Rd and Big Springs Rd. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 02/16/2026 through 02/27/2026 from 9 am - 2 pm (2026-033)

OVERTON COUNTY SR-111 (BYRDSTOWN HWY.) Utility Work both directions from LM 17.52 to LM 19.47: Flagging-assisted lane closures on SR-52 (Byrdstown Hwy) Between Big Springs Rd. and Wildwood Lane. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 02/16/2026 through 02/27/2026 from 9 am - 2 pm (2026-035)

OVERTON COUNTY SR-111 (BYRDSTOWN HWY.) Utility Work both directions from LM 19.46 to LM 21.01: Flagging-assisted lane closures on SR-52 (Byrdstown Hwy) between Big Springs Rd. and Eastport Dock Rd. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 02/16/2026 through 02/27/2026 from 9 am - 2 pm (2026-037)

OVERTON COUNTY SR-294 (E. MAIN ST.) Utility Work both directions from LM .0 to LM 14.72: Flagging-assisted lane closures on SR-294 (East Main St.) Between School Mountain rd. and Linder Mountain rd. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 02/16/2026 through 02/27/2026 from 9 am - 2 pm (2026-029)

OVERTON COUNTY SR-52 (E. MAIN ST.) Utility Work both directions from LM 11.24 to LM 11.28: Flagging-assisted lane closures on SR-52 (East Main St.) Between North Church St. and Myers St. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 02/16/2026 through 02/27/2026 from 9 am - 2 pm (2026-027)

OVERTON COUNTY SR-52 (E. MAIN ST.) Utility Work both directions from LM 11.45 to LM 12.12: Flagging-assisted lane closures on SR-52 (East Main St.) Between Oak St. and W. Main St. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 02/16/2026 through 02/27/2026 from 9 am - 2 pm (2026-029)

OVERTON COUNTY SR-85 (HILHAM HWY.) Utility Work both directions from LM 10.13 to LM 11.10: Flagging-assisted lane closures on SR-85 (Hilham HWY) between Windle Community Rd and Hawkins Rd. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 02/18/2026 through 02/22/2026 from 9 am - 2 pm (2025-471)

POLK COUNTY SR-33 (HWY. 411) Utility Work both directions from LM 0.0 to LM 2.84: Flagger-assisted lane closures on SR-33 (411 Hwy) between Waters Rd and Liberty Church Rd. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present 02/23/2026 through 03/20/26 from 8 am - 3 pm. [2026-063]

POLK COUNTY SR-68 over SR-40: The construction of bridges: During this reporting period, the contractor will begin construction on the SR-68 South bridge. All SR-68 traffic will use the newly constructed SR-68 North bridge while construction occurs on the new SR-68 South bridge. All SR-40/SR-68 interchange traffic will utilize the SR-68 North interchange ramps. A temporary 3-way stop has been implemented at the intersection of the SR-40 interchange ramp and SR-68. Motorists are encouraged to slow down when entering the construction zone and look out for new stop signs on SR-68 near the SR-40/SR-68 interchange.
[Wright Brothers Construction Company, Inc./Cleveland/CNZ042]

PUTNAM COUNTY I-40 TDOT Maintenance both directions from MM 286 to MM 304.3: A rolling operation to do shouldering is scheduled to start Monday 2/23/26 from 7:30AM-3:00PM. This will affect the inside lane both eastbound and westbound. Motorists are encouraged to use caution and slow down when in the area.

PUTNAM COUNTY I-40 [303.6-304.2] from MM 303.6 to MM 304.2 bridge repair and resurfacing: The contractor has started working on the bridge repair on I-40 at MM 304.6. Motorists should use caution in the area. [Rogers Group, Inc./Crossville/CNZ290]

PUTNAM COUNTY SR-136 construction from north of the SR-111 interchange to south of the I-40 interchange: The contractor will continue normal working activities throughout the project limits. During this work, temporary lane closures are possible, and flaggers will be present. Motorists are encouraged to use caution while traveling through the work zone and should be aware of construction equipment adjacent to the roadway. [Rogers Group, Inc./Cookeville/CNV284]

PUTNAM COUNTY SR-24 (CROSSVILLE HWY.) Utility Work both directions from LM 35.55 to LM 38.09: Eastbound and westbound lane closures on SR-24 (Crossville Hwy.) between E. Wilder Ave. and Walker Farm Rd. Motorists should reduce speed and be prepared to stop. Arrow board/message boards, flaggers, and barrels/cones will be present, 11/06/25 through 05/06/2026 from 9 am - 2 pm. [2025-521]

REGION 2 The on-call cable barrier repair on various Interstate and State Routes.: The contractor will have short-term shoulder and/or lane closures in order to perform cable barrier rail repair. These closures will take place daily, Monday through Friday, during daylight hours on the interstates and some major divided highway state routes. There may also be nightly Sunday through Thursday from 7 PM to 6 AM, rarely and only as needed. At least one travel lane will remain open to traffic at all times. Typically, only a shoulder closure will be used in the median, but lane closures will be employed as needed. [LU, Inc./McMinnville/CNZ205]

REGION 2 The on-call guardrail repair and new guardrail installation on various Interstate and State Routes: The contractor will have short term shoulder and/or lane closures in order to perform guardrail repair. These closures will take place on the interstate nightly Sunday through Thursday from 7 PM to 6 AM and daily Monday through Friday on state routes. At least one travel lane will remain open to traffic at all times on the interstate, and flaggers will be present on state routes during any work that is performed. [Reynolds Fence and Guardrail, Inc./McMinnville/CNZ112]

REGION 2 The random on-call attenuator repair on various Interstate and State Routes: The on-call attenuator repair contractor will have shoulder closures for repair work on an attenuator in the median in Hamilton County, SR-29 LM 2.9. They will also have shoulder closures for repair work in Bradley County SR-311 on the attenuator in the median at LM 4.218 near the intersection with Blackburn Rd. Work will occur during daylight hours from 6 AM to 6 PM on 02/19/26 with backup dates of 02/20/26 and 02/21/26 in case of inclement weather. [LU, Inc./McMinnville/CNZ118]

REGION 2 The sweeping on various Interstate and State Routes: Sweeping operations are planned throughout Region 2 this reporting period. Sweeping operations are mobile operations along the inside and outside shoulders with impacts to adjacent traffic lanes. These operations will occur at night between 8 PM and 6 AM for interstates and high traffic state routes, while daytime sweeping can be anticipated between 9 AM to 3 PM for lower traffic state routes. [Sweeping Corporation of America, Inc./Chattanooga West/CNY210]

REGION 2 Various Interstate and SRs - Cable Barrier Repair: The contractor will have short-term shoulder and/or lane closures in order to perform cable barrier rail repair for punch list operations. These closures will take place on the interstate nightly Sunday through Thursday from 7 PM to 6 AM as needed and daily Monday through Friday. At least one travel lane will remain open to traffic at all times. Typically, only a shoulder closure will be used in the median, but lane closures will be employed as needed. [LU, Inc./McMinnville/CNY183]

RHEA COUNTY SR-30 (DAYTON MTN. HWY.) Utility Work both directions from LM .13 to LM 2.22: Flagging-assisted lane closures on SR-30 (Dayton Mtn HWY) Between Walker Rd. and Tigues Creek Rd. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 01/12/2026 through 02/27/2026 from 9 am - 2 pm [2025-725]

WHITE COUNTY SR-111 [15.25-16.25] from O'Connor Rd to Old Kentucky Rd culvert replacement: The left lane of both the Northbound and Southbound side of SR-111 will be closed until further notice. At this time the contractor will be constructing median crossovers to allow for later work to be completed. Motorists are encouraged to use caution as they approach the work zone, and they should be prepared to stop. Motorists should also be aware of the speed limit reduction in place and follow all signs displayed.
[Rogers Group, Inc./Cookeville/CNZ902]

RESTRICTIONS

CUMBERLAND COUNTY - CNZ206: Both lanes of SR-24 are closed at LM 15.06 to LM 15.6.

###

State of Tennessee published this content on February 20, 2026, and is solely responsible for the information contained herein. Distributed via Public Technologies (PUBT), unedited and unaltered, on February 20, 2026 at 19:52 UTC. If you believe the information included in the content is inaccurate or outdated and requires editing or removal, please contact us at [email protected]