At 57th and Halsey: Concrete forming of sidewalks, installing pedestrian pole bases
At 47th and Halsey: Sawcutting for demolision and pipe installation, storm pipe installation
At 57th and Halsey: Pour sidewalks and corners
At 47th and Halsey: Install storm pipe, demolition of curb and sidewalks, install signal poles and wiring