07/09/2026 | News release | Distributed by Public on 07/09/2026 11:14
Portland Bureau of Transportation (PBOT) crews have installed and activated new traffic signals as part of the N Rosa Parks Way & Greeley Avenue Crossing & Signal Project.
Starting next week, our contractor will begin final steps to complete the project. They will rebuild corner ramps, driveway approaches, and sidewalk near the intersection. They will work on one corner at a time starting at the northeast corner. Each corner will take approximately one week to complete.
Following the concrete work, our contractor will repair pavement and install final striping. All work should be complete in the next one to two months.
Pedestrians should expect detours around the work areas. People driving and biking should travel cautiously through the work zone. Transit users should check TriMet for impacts on nearby bus stops.
Thank you for your patience as we near completion on this project.