Project Update | April 25, 2025

W. Club Boulevard Corridor Utility Rehabilitation Project Two-Week Look Ahead

April 25, 2025

The City appreciates your ongoing patience with the work associated with this project. Additional information regarding this project can be found at: www.durhamnc.gov/3705.

April 28 - May 2, 2025
Work continues on W. Club Boulevard between Hillandale Road and Alabama Avenue and includes restoration on the 2400 and 2500 blocks.

Work begins on W. Club Boulevard between Alabama Avenue and Oval Drive and includes installing 12" waterlines.

May 5-9, 2025
Work continues on W. Club Boulevard between Alabama Avenue and Oval Drive and includes installing 12" waterlines.

Road closure information
An active temporary road closure remains in place on W. Club Boulevard between Hillandale Road and Alabama Avenue and will move to between Alabama Avenue and Oval Drive.