Caltrans To Perform Next Traffic Lane Shift As Interstate 5 Anchor Pavement And Rehabilitation Project Continues

Caltrans To Perform Next Traffic Lane Shift As Interstate 5 Anchor Pavement And Rehabilitation Project Continues

Published: Apr 23, 2026

Construction Stage 8 Traffic Shift To Be In Place From May 15 Through August 2026

San Joaquin County - The California Department of Transportation (Caltrans) will soon be shifting all traffic lanes on Interstate 5 (I-5) between Hammer Lane and Eight Mile Road in Stockton as construction progresses to Stage 8 of the I-5 Anchor Pavement and Rehabilitation Project.

The Stage 8 traffic shift will begin the weekend of May 15-17, 2026, and will see three traffic lanes on northbound and southbound I-5 remain open during daytime hours, with alternating lane and ramp closures overnight. The northbound #1 (left) lane will be shifted behind k-rail and crossed-over to the newly-paved southbound I-5 left-median lane, with the #2 (middle) and #3 (right) lanes open on the northbound mainline.

Southbound motorists will travel in the #2 (left), #3 (middle), and the newly-paved right shoulder lane. (See illustration above). This Stage 8 traffic shift is expected to be in place through August 2026.

Construction Stage 8 is estimated to take 54 working days and will see work being performed on the #1 (left) lane of northbound I-5 between Eight Mile Road and Hammer Lane in Stockton.

I-5 Anchor Project - Completed Work So Far:

Caltrans and the contractor, Bay Cities Paving and Grading Inc., have already completed:

  • Stage 1 - Widening of the northbound and southbound median shoulders from 4 feet to 10 feet.
  • Stage 2 - Paving of the northbound I-5 right-hand shoulders.
  • Stage 3 - Replacement of the southbound I-5 damaged existing #3 lane (concrete) and right-hand HMA shoulder with new Continuously Reinforced Concrete Pavement (CRCP) between Eight Mile Road and Hammer Lane in Stockton.
  • Stage 4 - Replacement of the southbound I-5 damaged existing #2 (middle) lane with new Continuously Reinforced Concrete Pavement (CRCP) between Eight Mile Road and Hammer Lane in Stockton.
  • Stage 5 - Replacement of the southbound I-5 damaged existing #1 lane (concrete) with new Continuously Reinforced Concrete Pavement (CRCP) between Eight Mile Road and Hammer Lane in Stockton. Paving and striping of the on and off-ramps from SR-12/Flag City to Walnut Grove Road.
  • Stage 6 - Replacement of the northbound I-5 damaged existing #3 (right) lane and right-hand shoulder.
  • Stage 7 - Replacement of the northbound I-5 damaged existing #2 (middle) lane

The above listed traffic shifts and lane/ramps closures are required as part of the I-5 Anchor Pavement Project that will improve 34 miles of existing pavement and shoulders from Hammer Lane in Stockton to the San Joaquin/ Sacramento County line. The project will also overlay on- and off-ramps with asphalt concrete at Eight Mile Road, SR-12, Turner Road, Peltier Road, and Thornton Road/Walnut Grove Road. For project details visit https://dot.ca.gov/caltrans-near-me/district-10/district-10-current-projects/10-1e300.

Future Caltrans District 10 traffic advisories and social media posts will advise of all scheduled highway closures and can also be found at https://dot.ca.gov/caltrans-near-me/district-10/district-10-news.

All work is scheduled to begin as listed, but is subject to change due to traffic incidents, weather, availability of equipment, and/or materials and construction related issues. For the safety of workers and other motorists, please Be Work Zone Alert.

For information on Caltrans projects statewide, please visit Build.CA.gov.

Motorists should expect 5-to-10-minute delays and use alternate routes whenever possible. All work is scheduled to occur as listed but is subject to change due to traffic incidents, weather, availability of equipment/materials, and construction-related issues.

For the safety of workers and other motorists, please Be Work Zone Alert. Caltrans also reminds motorists to #KnowBeforeYouGo by checking QuickMaps on your mobile device or visit quickmap.dot.ca.gov for real-time highway conditions.

California Department of Transportation published this content on April 23, 2026, and is solely responsible for the information contained herein. Distributed via Public Technologies (PUBT), unedited and unaltered, on April 23, 2026 at 22:58 UTC. If you believe the information included in the content is inaccurate or outdated and requires editing or removal, please contact us at [email protected]