The Connecticut Department of Transportation (CTDOT) is announcing that Bridge Rehabilitation will be performed on I-291 in Windsor and South Windsor. This project is scheduled to occur on Thursday, June 18 and be completed on Friday, November 12, 2027. The project 0164-0245 consists of Paving, Safety Improvements, Joint reconstruction as well super and substructure repairs.
CTDOT Project No. 0164-0245 was awarded to McNamee Construction Corp. at a cost of $16,874,000.00 on May 5, 2026, and is scheduled to be completed November 12, 2027. This project is administered by the Bureau of Engineering and Construction, Office of Construction, District 1 in Rocky Hill.
LANE CLOSURE/DETOUR INFO
There will be a lane reduction on I-291 westbound over the CT River between Exit 2 to 1D starting June 18 through the summer season. Traffic will be reduced to one 11-foot-wide lane with associated traffic control signing patterns will guide motorists through the work zone.
Motorists should be aware that modifications or extensions to this schedule may become necessary due to weather delays or other unforeseen conditions. Motorists are advised to maintain a safe speed when driving in this area.