BRADLEY COUNTY SR-2 (S. LEE HWY.) Utility Work both directions from LM 8.12 to LM 8.14: Flagging-assisted lane closures on SR-02 (South Lee HWY) between Victory St. SW and Old Boyd Farm RD. SW Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 04/02/2026 through05/06/2026 from 9 am - 2 pm [2025-930]
BRADLEY COUNTY SR-60 widening from the 4-lane north of I-75 (LM 17.2) to SR 306 (LM19.9): During this reporting period, the contractor will perform punch list work on SR-60 in Bradley County. Intermittent lane closures may be necessary while work occurs.
[Summers-Taylor, Inc./Cleveland/CNV130]
BRADLEY COUNTY SR-74 (SPRING PLACE RD.) Utility Work both directions from LM 11.07 to LM 11.14: Flagging-assisted lane closures on SR-74 (Spring Place Rd) between Clayton LN and Durkee RD SE. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 12/18/25 through 06/18/2026 from 9 am - 2 pm [2025-736]
BRADLEY COUNTY SR-74 [11.445-11.83] from Whaley Road to SR-60 APD-40 drainage improvements: During this reporting period, the contractor will continue storm drain installation and grading work on SR-74. Intermittent flagging operations and shoulder closures will be necessary periodically. Motorists should use caution and reduce speed when traveling through the work zone.
[APAC - Atlantic, Inc./Cleveland/CNZ243]
CAMPBELL, COFFEE, DAVIDSON, DICKSON, GILES, GREENE, HAYWOOD, KNOX, MCMINN, SHELBY, AND WILLIAMSON COUNTY The installation of Weigh-in-Motion technology at 28 sites on various Interstate and State Routes: No Region 2 Lane Closures this week on CNX913. [Davis H. Elliot Construction Company, Inc./Maint - R2/CNX913]
CUMBERLAND COUNTY I-40 [304.4-306.6] from MM 304.4 to MM 306.6 bridge repair and resurfacing: The contractor continues nighttime work on I-40. Temporary lane closures will be utilized throughout the project limits for the proposed work on the shoulders. Traffic has been shifted along the project route. Typical work times are Sunday night through Friday morning from 7 PM to 6 AM. Motorists should use caution in the area. [Rogers Group, Inc./Crossville/CNZ290]
CUMBERLAND COUNTY SR-24 [0-0.16] from Putnam County Line to C189 bridge repair: The contractor continues working on the bridge repair on I-40 at MM 304.6 or SR-24 at LM 0.24. The Contractor has reduced SR-24 to one lane with temporary signals. Motorists should use caution in the area. [Rogers Group, Inc./Crossville/CNZ290]
CUMBERLAND COUNTY SR-24 [15.056-15.56] from Crossville city limits to Seventh-Day Adventist Church and School bridge replacement: The contractor has closed SR-24 at LM 15.06 to LM 15.6. This closure will remain in place for the duration of the project. The posted detour is along SR-462 and SR-1. The contractor will be working on general clearing activities and utility work initially. Once initial work is completed, the Contractor will proceed with the replacement of the bridge over the Obed River. Motorists should use caution and utilize the posted detour. RESTRICTIONS: Both lanes of SR-24 are closed at LM 15.06 to LM 15.6.
[Mid-State Construction Company, Inc./Crossville/CNZ206]
CUMBERLAND COUNTY SR-28 (US-127) bridge construction and paving from north of I-40 (LM 17.8) to near Potato Farm Road (LM 22.7): The contractor continues grading activities throughout the project limits. The contractor has scheduled to close Freedonia Road starting on 04/27/26. A detour will be posted to utilize Maynard Road. Temporary lane closures and/or periodic traffic stoppages will be necessary for construction activities. Flaggers and advanced warning signs will accompany any closures. Motorists should use caution when traveling through the work zone as traffic patterns change. [Jones Bros. Contractors, LLC/Crossville/CNV009]
CUMBERLAND AND FENTRESS COUNTY SR-28 (US-127) widening from near N. Lowe Rd (LM 29.2) to north of SR-62 (LM 1.9): The contractor has shifted traffic to phase 2 on the newly constructed portions of SR-28 LM 0.90 to 1.98 in Fentress County. Work will proceed on the existing alignment of SR-28. Flaggers are being used intermittently as needed to control traffic through the work zone. Motorists are encouraged to use caution, be aware of new traffic signs and pavement markings, and watch for construction equipment and personnel throughout the project.
[Jones Bros. Contractors, LLC/Cookeville/CNV300]
DEKALB COUNTY SR-26 (US-70) grading, drainage, and construction of retaining walls and paving from near SR-53 (LM 2) to near SR-96 (LM 6.1): The contractor is continuing work near the intersection of SR-26 and SR-53. During this work, lane closures may be used, and flaggers will be present to facilitate the flow of traffic through the work zone. Motorists are encouraged to use caution while traveling through the work zone and should be aware of construction equipment adjacent to the roadway. [Twin K Construction/Cookeville/CNV012]
DEKALB COUNTY SR-26 [15.9-20.3] from Near Old Snow Hill Road to West of Curtis Road resurfacing: The contractor is scheduled to begin sign installation and start concrete curb work within the project limits. During this work, the contractor will have daily lane closures set up to facilitate the work. Motorists should use caution through the work zone, and they should be prepared to stop or slow down as slow-moving traffic is encountered.
[Rogers Group, Inc./Cookeville/262008]
FRANKLIN COUNTY SR-16 (US-41A) Utility Work, both directions from LM 6.33 to LM 7.97: Flagger-assisted lane closures on SR-16 (Tullahoma HWY.) between Circle Dr and one-mile past Peabody Rd. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present 04/27/2026 through 05/01/2026 from 9 am to 2 pm [2025-992)
GRUNDY COUNTY SR-2 (US-41) TDOT Contractor, both directions from LM 5 to LM 7: TDOT contractor will be doing mechanical brush control along SR 2 up and down the mountain. They will be using a lane closure to perform this work. Start: Thursday, 4/23/26, from 8 AM to 4:30 PM. Finish: Friday 4/24/26 from 8 AM to 4:30 PM. What: The traffic control subcontractor will shut down the eastbound lane to remove brush going up the mountain and then proceed down the mountain westbound the next day.
HAMILTON COUNTY I-75 at I-24 Interchange Reconstruction Phase 2: In order to complete final punch list items on this project, the contractor is planning to have ramp and lane closures the night of Thursday, April 23, from 9 PM to 6 AM for replacing/improving lane markings on I-75 South and I-24 West. As part of this punch list work, it will be necessary to temporarily close the entrance ramp from East Brainard Road to I-75 South. The two (2) right (outside) lanes along I-75 South will also be closed, from East Brainard Road to Exit 2 (I-24 West). There will also be two (2) right (outside) lanes closed, along the I-24 West ramp and some outside lane closures along I-24 West to Exit 184 (South Moore Road). Message boards, signs and detours will be provided to warn motorists of all ramp closures and to guide them to the next available exit or entrance ramp. No other ramp/lane closures are scheduled for this period, but the contractor may utilize traveling/moving operations to restripe several small areas of traffic markings on I-75 North and I-24 East to complete the striping portion of the final punch list. It may also be necessary to do short-duration (15 to 30 minutes) rolling roadblocks during the day or night for patching potholes, clearing debris or repairing guardrail, attenuators, etc. [Wright Brothers Construction Company, Inc./Maj Prj - Blevins/DB2101]
HAMILTON COUNTY I-75 at the Hamilton Place Mall interchange: The SR-153 southbound ramp to I-75 northbound has been reduced to one lane. Traffic shifts have been implemented on I-75 northbound and I-75 southbound, Shallowford Road entrance ramps, and Shallowford Road exit ramps and Hamilton Place Mall exit ramp. Hamilton Loop Road is closed for retaining wall construction and storm drainage installation between the intersections near Markman's Jewelers and Texas Roadhouse. Beginning 04/27/26 through 4/30/26, the contractor will close 2 right lanes between 8 PM and 6 AM on I-75 SB from MM 8.8 to MM 6.6 for the installation of overhead signs. The contractor anticipates one night for closing two right lanes and one night for rolling roadblocks to mount the overhead signs. The remaining 2 nights are in case of adverse weather. The speed limit has been reduced on I-75 throughout the project limits. Nightly lane closures are permitted 8 PM to 6 AM. Motorists should use caution, paying attention to construction signage and watching for construction vehicles and personnel. [Summers-Taylor, Inc./Chattanooga West/CNX358]
HAMILTON COUNTY SR-148 (LOOKOUT MTN. SCENIC HWY.) Utility Work both directions at LM .10: Flagger-assisted lane closures on SR-148 (Scenic HWY) between west Bartram RD and Fleetwood Dr. West. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 03/02/2026 through 04/22/2026 from 9 am - 2 pm [2025-980]
HAMILTON COUNTY SR-2 (BRAINERD RD.) Utility Work both directions at LM 14.81: Flagger-assisted lane closures on SR-11 (Brainard rd.) from Greenway View Drive to Old Mission Rd. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present,04/16/2026 through 04/23/2026 with a rain date of 04/24/2026 through 04/27/2026 from 9 am - 2 pm [2026-165]
HAMILTON COUNTY SR-2 (BRAINERD RD.) Utility Work both directions at LM 14.82: Flagger-assisted lane closures on SR-2 (Brainard Rd.) between Greenway View Dr. and Old Mission rd. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 04/022026 through 04/15/2026 from 9 am - 2 pm [2025-870]
HAMILTON COUNTY SR-317 (APISON PK.) Utility Work both directions from LM 11.04 to LM 11.59: Flagger-assisted lane closures on SR-317 (Apison Pike) from Bates Road to McDonald Rd. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present,04/14/2026 through 04/16/2026, with a rain date of 04/17/2026 from 9 am - 2 pm [2026-140]
HAMILTON COUNTY SR-319 (HIXSON PK.) Utility Work both directions from LM 5.17 to LM 5.21: Flagger-assisted lane closures on SR-319 (Hixson Pike) from Austin Rd to Adams Rd. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 04/21/2026 through 05/02/2026 with a rain date of 05/03/2026 from 9 am - 2 pm [2026-673)
HAMILTON COUNTY SR-8 (SIGNAL MOUNTAIN BLVD.) Utility Work both directions from LM 16.28 to LM 16.32: Flagger-assisted lane closures on SR-08 (Signal Mtn Blvd) from Shoal Creek Rd to Palisades Dr Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present,04/16/2026 through 04/17/2026, from 9 am - 2 pm [2026-142)
HAMILTON COUNTY SR-8 (W. MAIN ST.) Utility Work both directions from LM 7.91 to LM 8.05: Flagger-assisted lane closures on SR-08 (West Main St) from Williams St. to Adams St. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 04/17/2026, with a rain date of 04/24/2026 from 9 am - 2 pm [2026-150)
JACKSON COUNTY SR-135 (DODSON BRANCH HWY.) TDOT Maintenance northbound at LM 10.7: SR 135 at the 10.7MM will continue to be reduced to one lane due to a slide area. Traffic lights are in place. Motorists are encouraged to reduce speed and use caution when in the area.
JACKSON COUNTY SR-53 [17.46-17.6] from south of Hurricane Branch to Near Hurricane Branch Lane culvert replacement: The contractor has completely closed the road through the work zone as of 03/04/26. Motorists need to use the posted detour route.
[Cleary Construction, Inc./Livingston/CNZ250]
MARION COUNTY I-24 TDOT Contractor eastbound from MM 141.5 to MM 148.6: Big Woody's Tree Service will be performing mechanical tree and brush removal 04/20/26 - 04/29/26 from 7 AM to 5 PM. Big Woody's will be closing the shoulder in the eastbound direction. Westbound will not be affected.
MARION COUNTY I-24 TDOT Contractor westbound from MM 156.4 to MM 141.1: Big Woody's Tree Service will be performing mechanical tree and brush removal 04/20/26 - 04/29/26 from 7 AM to 5 PM. Big Woody's will be closing the shoulder in the westbound direction. Eastbound will not be affected.
MARION COUNTY I-24 TDOT Contractor westbound from MM 162 to MM 161.4: Big Woody's Tree Service will be performing mechanical tree and brush removal 04/20/26 - 04/24/26 from 7 PM to 6 AM. Contractor SDM Traffic Plan will be closing Lane # 2 in the westbound direction. Eastbound will not be affected.
MARION COUNTY I-24 [137-138.2] from 137 to 138.2 Rockfall Mitigation on I-24 near MM 137: The contractor will be performing rockfall mitigation operations on I-24 WB beginning at MM 138.2 in Marion County. The middle lane, right lane, and right shoulder have been closed. 2 Lanes of traffic have been shifted to flow on the left shoulder and left lane. Blasting will also occur during the weekdays between 9 AM and 3 PM. Blasting operations will require a rolling roadblock. All lanes will be reopened to traffic by May 22, 2026. Work will continue off the road after May 22, and the project will be completed by July 31, 2026. [Summers-Taylor, Inc./Dunlap/N262018]
MARION COUNTY SR-108 [2.8-3.24] slide mitigation: The contractor will be performing slide mitigation operations, including grading, drainage, and paving on SR-108 in Marion County at LM 2.8. The roadway will be reduced to one lane controlled by temporary traffic signals. The project completion date is 08/31/2027. Please use caution when driving through the work zone.
[Wright Brothers Construction Company, Inc./Dunlap/CNZ226]
MARION COUNTY SR-2 [17.2-17.3] from 17.2 to 17.3 construction: The contractor will be performing grading and drainage operations on SR-2 in Marion County near LM 17.25. This work will require a lane shift for the EB traffic - the WB traffic will be unaffected. Please slow down and use caution when driving through the work zone. [Talley Construction Company, Inc./Dunlap/CNZ244]
MARION COUNTY SR-283 [2.69-8.11] from 2.69 to 8.11 resurfacing with Cold In-Place Recycling (CIR): The contractor will be performing resurfacing operations on SR-283 from near SR-27 (LM 2.69) to the Sequatchie County line (LM 8.11). This work will require a single lane closure controlled by flaggers. Please use caution when driving through the work zone.
[Road Worx, Inc./Dunlap/CNZ188]
MEIGS COUNTY SR-58 (STATE HWY. 58) Utility Work both directions from LM 14.53 to LM 15.67: Flagger-assisted lane closures on SR-58 (HWY 58) between Roberts Rd and Solomon Rd. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present 04/16/2026 through 04/22/2026, from 9 am to 2 pm [2026-734)
PICKETT COUNTY SR-111 (LIVINGSTON HWY.) Utility Work both directions from LM 1.46 to LM 2.52: Flagger-assisted lane closures on SR-111 (Livingston HWY) between Obey Park Rd and Cherrytree lane. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 03/16/2026 through 04/17/2026 from 9 am - 2 pm [2026-102]
POLK COUNTY SR-315 (TELLICO-RELIANCE RD.) Utility Work both directions from LM .21 to LM 7.16: BRADLEY COUNTY SR-40 (Water level HWY) Utility Work both directions at LM 2.69 through LM 3.32: Flagger-assisted lane closures on SR- 40 (Water level HWY) between Rose Lane and HWY 40 on ramp. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present 7/30/2026 through 09/30/2026, from 9 am to 2 pm [2026-089)
POLK COUNTY SR-68 over SR-40 the construction of bridges: During this reporting period, the contractor will continue construction on the SR-68 South bridge. All SR-68 traffic will use the newly constructed SR-68 North bridge while construction occurs on the new SR-68 South bridge. All SR-40/SR-68 interchange traffic will utilize the SR-68 North interchange ramps. A temporary 3-way stop has been implemented at the intersection of the SR-40 interchange ramp and SR-68. Motorists are encouraged to slow down when entering the construction zone and look out for new stop signs on SR-68 near the SR-40/SR-68 interchange. [Wright Brothers Construction Company, Inc./Cleveland/CNZ042]
PUTNAM COUNTY I-40 [303.6-304.2] from MM 303.6 to MM 304.2 bridge repair and resurfacing: The contractor continues nighttime work on I-40. Temporary lane closures will be utilized throughout the project limits for the proposed work on the shoulders. Traffic has been shifted along the project route. Typical work times are Sunday night through Friday morning from 7 PM to 6 AM. Motorists should use caution in the area. [Rogers Group, Inc./Crossville/CNZ290]
PUTNAM COUNTY SR-136 construction from north of the SR-111 interchange to south of the I-40 interchange: The contractor will continue normal working activities throughout the project limits. During this work, temporary lane closures are possible, and flaggers will be present. Pigeon Roost Creek Road is closed at the intersection of SR-136 with detour signs to utilize Bunker Hill Road. Motorists are encouraged to use caution while traveling through the work zone and should be aware of construction equipment adjacent to the roadway. [Rogers Group, Inc./Cookeville/CNV284]
PUTNAM COUNTY SR-136 [2.27-4.15] from I-40 Eastbound Ramps to SR-24 resurfacing: The City of Cookeville is performing valve adjustments throughout the project limits, and during this work, one lane in each direction will be closed. Motorists should be prepared to stop as they approach the work zone, and they should be aware of construction equipment adjacent to the roadway.
[Vulcan Construction Materials, LLC/Cookeville/CNZ293]
PUTNAM COUNTY SR-24 (CROSSVILLE HWY.) Utility Work both directions from LM 35.55 to LM 38.09: Eastbound and westbound lane closures on SR-24 (Crossville Hwy.) between E. Wilder Ave. and Walker Farm Rd. Motorists should reduce speed and be prepared to stop. Arrow board/message boards, flaggers, and barrels/cones will be present, 11/06/25 through 05/06/2026 from 9 am - 2 pm. [2025-521]
REGION 2 Dynamic Message Sign (DMS) Life Cycle Replacement: No lane closures this week. There will be periodic shoulder closures at locations on I-24 East and West in Marion Co., I-24 East and West in Hamilton Co., I-75 North and South in Hamilton Co., I-75 North in Bradley Co., I-75 South in McMinn Co., SR-29 South in Hamilton Co., and SR-153 North and South in Hamilton Co. this week 8pm - 5am. [Davis H. Elliot Construction Company, Inc./Chattanooga East/CNX413]
REGION 2 Interstate and state route thermoplastic marking re-tracing: The contractor will be placing thermoplastic pavement markings along SR-28 (LM 14.971 - 17.810) and SR101 (LM 18.030 - 26.600) in Cumberland County, Dekalb County SR-26 (LM 6.100 - 10.880), Fentress County SR-28 (LM 10.395 - 16.400), Overton County SR-52 (LM 6.500 - 10.155) and SR-111 (LM 0.000 - 9.370), Putnam County SR-24 (LM 15.710 - 23.723) and SR-135 (LM 7.380 - 9.750), and White County SR-1 (LM 7.700 - 8.700). During this work the contractor will be utilizing a mobile operation and motorists should expect a delay. Motorists should exercise caution when crews are present and be aware of wet edge lines. [Mullen's Markings, Inc/Cookeville/262003]
REGION 2 the drain cleaning on various Interstate and State Routes: Drain cleaning operations are planned on I-75, SR-153 and I-24 in Hamilton County. These operations are mobile along the inside shoulders with impacts to adjacent traffic lanes and will occur at night between 8 PM and 6 AM. [Sweeping Corporation of America, Inc./Chattanooga West/CNZ286]
REGION 2 The on-call cable barrier repair on various Interstate and State Routes: The contractor will have short-term shoulder and/or lane closures in order to perform cable barrier rail repair. These closures will take place daily, Monday through Friday, during daylight hours on the interstates and some major divided highway state routes. There may also be nightly Sunday through Thursday from 7 PM to 6 AM, rarely and only as needed. At least one travel lane will remain open to traffic at all times. Typically, only a shoulder closure will be used in the median, but lane closures will be employed as needed. [LU, Inc./McMinnville/CNZ205]
REGION 2 The on-call guardrail repair and new guardrail installation on various Interstate and State Routes: The contractor will have short-term shoulder and/or lane closures in order to perform guardrail repair. These closures will take place on the interstate nightly Sunday through Thursday from 7 PM to 6 AM and daily Monday through Friday on state routes. At least one travel lane will remain open to traffic at all times on the interstate, and flaggers will be present on state routes during any work that is performed. [Reynolds Fence and Guardrail, Inc./McMinnville/CNZ112]
REGION 2 the sweeping on various Interstate and State Routes: Sweeping operations are planned throughout Region 2 this reporting period. Sweeping operations are mobile operations along the inside and outside shoulders with impacts to adjacent traffic lanes. These operations will occur at night between 8 PM and 6 AM for interstates and high traffic state routes, while daytime sweeping can be anticipated between 9 AM to 3 PM for lower traffic state routes.
[Spears-Hopkins Paving Co., LLC/Chattanooga West/CNZ248]
REGION 2 Thermoplastic retracing on various interstate and state routes: The contractor will be on site in Rhea County on SR-30 at SR-303, Clay County SR-51 at SR-52, SR-58 LM 17.430 - 17.830, Hamilton County SR-17 at LM 8.73, Hamilton County SR-317 at LM 0.517, Hamilton County SR-317 at SR-153 Interchange, Hamilton County SR-317 at LM 0.971, Hamilton County SR-317 at LM 1.308, Hamilton County SR-317 at LM 1.573 - 1.794, Rhea County SR-30 from SR-29 to Cottonport Road. During this work, the contractor will utilize a mobile operation with mobile message boards and an attenuator truck. Motorists are encouraged to slow down as they approach work and should be aware of the potential of stopped or slowing traffic. [Reynolds Sealing and Striping, Inc./Cookeville/CNZ054]
VAN BUREN COUNTY SR-111 [14.87-19.54] from Sparta Street to White County Line micro-surfacing: The contractor will have occasional lane closures during daylight hours from 6 AM to 7 PM for micro-surfacing-related operations. Additionally, lane closures on this multi-lane highway will occasionally carry through nighttime hours (24-hour lane closures) with proper signage for curing of concrete and other bridge-related setup as needed on infrequent occasions.
[Asphalt Paving Systems, Inc./McMinnville/CNZ177]
WHITE COUNTY SR-1 [0-7.7] from Van Buren County Line to SR-111 resurfacing: The contractor is scheduled to begin installing construction signs on 04/24/26. Once the signs are installed, the contractor will begin removing existing pavement markings and will start micro-surface paving. During this work, one lane will be closed in each direction and workers will be present on the roadway. Motorists are encouraged to use caution as they approach the work zone, and they should be prepared to stop as they may encounter slow moving traffic. [Asphalt Paving Systems, Inc./Cookeville/262014]
WHITE COUNTY SR-111 [15.25-16.25] from O'Connor Rd to Old Kentucky Rd culvert replacement: The contractor will be continuing work on installation of a box culvert. During this work, traffic will remain in one lane, and two-way traffic will be running on the northbound section of SR-111. Motorists are encouraged to use caution as they approach the work zone, and they should be prepared to stop. Motorists should also be aware of the speed limit reduction in place and follow all signs displayed. [Rogers Group, Inc./Cookeville/CNZ902]
RESTRICTIONS
CAMPBELL, COFFEE, DAVIDSON, DICKSON, GILES, GREENE, HAYWOOD, KNOX, MCMINN, SHELBY, AND WILLIAMSON COUNTY - CNX913:
CUMBERLAND COUNTY - CNZ206: Both lanes of SR-24 are closed at LM 15.06 to LM 15.6.
###