Quarterly Report for Quarter Ending September 30, 2026 (Form 10-Q)

Management's Discussion and Analysis of Financial Condition and Results of Operations
The following discussion and analysis of our financial condition and results of operations for the three and nine months ended September 30, 2026 and 2025, should be read together with our unaudited condensed consolidated financial statements and related notes included elsewhere in this Quarterly Report and in conjunction with the audited consolidated financial statements and notes thereto included in our Annual Report on Form 10-K for the fiscal year ended December 31, 2025. The following discussion contains "forward-looking statements" that reflect our future plans, estimates, beliefs, and expected performance. Our actual results may differ materially from those currently anticipated and expressed in such forward-looking statements as a result of a number of factors. We caution that assumptions, expectations, projections, intentions, or beliefs about future events may, and often do, vary from actual results and the differences can be material. Please see "Special Note Regarding Forward-Looking Statements."
Overview
Oklo was founded in 2013 with the goal of developing a novel model to generate and distribute nuclear energy at scale. Our sodium-cooled Aurora powerhouses are at the center, within an integrated business that includes fuel fabrication, fuel recycling, and isotope production. We are building fast reactors that can meet the needs of individual customers, broader power grids, and the U.S.'s rapidly growing demand for electricity. Our ambition is to build a nuclear ecosystem within Oklo: power generation that creates additional demand for fuel, fuel fabrication, and recycling that enable powerhouse deployment at scale, and isotope production for valuable medical and industrial uses that generates reliable revenue and supports the continuing development of the entire business. Our business model allows us to learn at each step so that we may continually improve our designs, operations, and strategy.
Oklo stands apart from the legacy nuclear industry - we will primarily own and operate our powerhouses and directly sell our power to customers, rather than licensing our designs for others to build and operate. We are incentivized to design, build, and operate more efficiently because we will bear the costs of creating and operating our powerhouses. The opportunity for iterative improvement is inherent in our business model. The Aurora Powerhouse product line is expected not just to broaden our customer base, but also to provide shorter construction cycles and more frequent deployments - each an opportunity to learn and improve with the next project. Despite the distinct technical requirements across our suite of projects, there can be significant learnings related to construction, procurement, instrumentation, regulatory licensing pathways, and nuclear and non-nuclear operations.
Our fuel strategy is fundamental to our business plan. Aurora is designed to use fresh, recycled, and down-blended nuclear fuels, allowing us to pursue a diversified fuel strategy that can adapt to changing market conditions and use bridge solutions rather than depend on a single fuel type or supply chain. To enable our first deployment, we have secured five metric tons of HALEU produced from recovered uranium from previously irradiated EBR-II fuel. To enable future deployments, we are securing HALEU supply commitments from large uranium enrichers and partnering with early stage companies who are researching and developing innovative new enrichment methods. At the same time, we are building our fuel fabrication capabilities and actively investigating other paths to fueling, including potential government partnerships. We are also developing fuel recycling technology and aim to build facilities that can unlock the abundant residual energy in the U.S.'s large stock of used nuclear fuel, while also potentially recovering valuable isotope materials.
Our business advances in stages and we aim to develop this ecosystem through investments that build on each other. We believe that a strong ecosystem for nuclear energy will enable each of power, fuel fabrication, recycling and isotopes to achieve their respective business objectives. Our early facilities establish capabilities and lessons for later deployments within and across fields. Through the Groves Isotope Test Reactor, we have already gained valuable construction, siting, regulatory, and operating know-how. This is knowledge that can't be gained from design alone and is informing subsequent isotope, powerhouse, fuel fabrication, and fuel recycling development. Oklo is pursuing an integrated nuclear business of lasting commercial value: the technology to supply power, the fuel to sustain growth, and the experience to continually improve - all in service of making nuclear energy available at the scale the U.S. needs.
Power
The fast fission reactor technology we are commercializing was demonstrated by the Experimental Breeder Reactor-II ("EBR-II"), a fast fission plant that was operated by the U.S. government for 30 years. Our powerhouse product line, called the "Aurora," builds on this legacy of proven and demonstrated technology. Our Aurora powerhouse product line is designed with embedded safety features, to be able to run on fresh, recycled, or down-blended fuel, and to initially produce 15-75 megawatts electric ("MWe"), with the potential to expand powerhouse size to produce 100 MWe and higher.
Because the Aurora powerhouses are designed to operate by utilizing the power of high-energy, or "fast," neutrons, they will be able to tap into the vast energy reserves remaining in existing used nuclear fuel from conventional nuclear power generation facilities, which only use approximately 5% of the energy potential in the nuclear fuel before needing to refuel. The U.S. nuclear power industry has produced approximately 20% of U.S. electricity over the last 30 years and generated over 90,000 metric tons of used nuclear fuel. We estimate that the existing energy reserves contained in the used nuclear fuel in the U.S. that could be made accessible through our fast fission reactor technology. Because fission is an energy-dense process, producing approximately 50 million times more energy than combustion, these potentially recoverable energy reserves are equivalent to approximately 1.2 trillion barrels of oil equivalent (BOE), nearly five times the oil reserves of Saudi Arabia.
Development Milestones
We have achieved several significant deployment and regulatory milestones for our first Aurora powerhouse. Notably, we secured a site use permit from the U.S. Department of Energy ("DOE") for the Idaho National Laboratory ("INL") site and received a fuel award of five metric tons of HALEU produced from recovered uranium from previously irradiated EBR-II fuel from INL for a commercial Aurora powerhouse in Idaho ("Aurora-ID"). Since that time, we have secured and characterized DOE land at INL, and achieved further milestones, including:
•August 2025: Selected for DOE's Reactor Pilot Program ("RPP")
•September 2025: DOE approval for non-nuclear construction and Aurora-ID groundbreaking
•February 2026: Execution of Other Transaction Agreement ("OTA") with DOE for Aurora-ID
•February 2026: Approval of Nuclear Safety Design Agreement ("NSDA") by DOE
•April 2026: NRC Approval of Principal Design Criteria report
•June 2026: Approval of Preliminary Documented Safety Analysis ("PDSA")

The NSDA and PDSA represent two of five steps in the DOE regulatory pathway for nuclear facility operation. The PDSA approval for the Aurora-ID is an important milestone. It is comparable to an NRC construction permit in that it serves as a key regulatory review point for the project's preliminary design and safety analysis, supporting the advancement of safety-related construction and procurement while helping reduce the risk of significant safety-driven design changes later in development. Other regulatory approvals, including the OTA and receipt of the Environmental Compliance Permit, have further advanced our plans to deliver the first commercial advanced fission power plant in the U.S.
Commercialization Developments
Our robust pipeline of potential customer engagements spans a number of industries. For example, we have signed non-binding letters of intent with Equinix, Inc. ("Equinix"), Diamondback E&P LLC ("Diamondback Energy"), and Prometheus Hyperscale (formerly Wyoming Hyperscale White Box LLC) ("Prometheus Hyperscale"). In December 2024, we signed a 12 gigawatt ("GW") Master Power Agreement with Switch, Ltd. ("Switch"), one of the largest corporate PPAs in history.
On January 5, 2026, we entered into a prepayment agreement (the "Prepayment Agreement") with Meta Platforms, Inc. ("Meta") that advances plans to develop a 1.2 gigawatt power campus in Pike County, Ohio, to support Meta's data centers. The Prepayment Agreement provides a framework for Meta to prepay for power and provide funding to advance powerhouse deployment.
In addition to our Aurora-ID development, in June 2025, we were issued a Notice of Intent to Award by the Defense Logistics Agency-Energy on behalf of the Department of the Air Force, tentatively selecting Oklo to provide electricity and heat to Eielson Air Force Base outside of Fairbanks, Alaska. An Aurora-derived powerhouse is planned for the base and will be designed to integrate electric power and steam delivery, including at least 5 MWe.
Fuel Supply, Logistics, and Collaborations
In June 2026, we entered into a letter of intent with Centrus Energy Corp. ("Centrus") under which Centrus would supply sufficient domestically produced HALEU to support multiple years of fuel requirements for up to five Aurora powerhouses, with deliveries expected to begin in 2029. The letter of intent contemplates the negotiation and execution of a definitive supply agreement and could include prepayments by us to Centrus to support fuel supply for our planned 1.2-GW power campus in southern Ohio.
On September 30, 2026, in connection with the Prepayment Agreement, we entered into a HALEU supply agreement with Centrus to support the deployment of powerhouses for Meta, subject to certain conditions. On November 2, 2026, an initial funding amount from Meta was released from escrow and paid directly to Centrus as a credit towards fuel orders. We
continue to explore, and have engaged in discussions with, additional potential suppliers of HALEU to support our initial powerhouse developments and planned subsequent scaling.
The development of our Aurora powerhouses requires complex engineering design, manufacturing, and construction solutions. To this end, the Company is expanding its capabilities in precision manufacturing, prototyping, and chemical process engineering through recent acquisitions in support of its power projects, as well as its fuel and isotopes projects. For more information about the Company's recent acquisitions, see Note 3-Business Combination-2026 Acquisitions.
During the three months ended June 30, 2026, Oklo announced two collaborations in support of the federal government's Genesis Mission focused on applying artificial intelligence to advanced reactor and nuclear fuel development. In April 2026, we announced an agreement with NVIDIA Corporation and Los Alamos National Laboratory ("Los Alamos") to advance AI-enabled modeling, simulation, digital twins, materials science, and fuel validation activities for plutonium-bearing fuels, as well as power generation, grid reliability, redundancy, and stabilization studies supporting potential nuclear-powered AI infrastructure at Los Alamos. In May 2026, we announced a strategic partnership project with Battelle Energy Alliance, the management and operating contractor for INL, to integrate INL's Prometheus AI platform with our multiphysics design and analysis infrastructure to support AI-enabled engineering workflows, model benchmarking and validation, technical documentation, and development of Pluto. Pluto is our reactor system designed to use plutonium-bearing fuels and is part of the DOE's RPP. These collaborations are intended to improve engineering efficiency and advance our reactor and fuel-system development activities while supporting the broader objectives of the Genesis Mission.
Fuel
Our fuel strategy is intended to combine external supply arrangements with the development of our own fuel fabrication and recycling capabilities. We believe that this strategy can provide the fuel supply needed for our initial development, as well as longer-term sources that will support the scaled deployment of our powerhouses, and could potentially provide products and services for other nuclear companies. Alongside our efforts to secure external sources of HALEU and government-held nuclear materials (including surplus plutonium), we have designed our powerhouses to use alternate fuels (including recycled and down-blended fuels), and are developing in-house fabrication capabilities to convert fuel materials into finished fuel products usable in our reactors and recycling capabilities to recover usable materials from spent nuclear fuel. We have made significant progress in implementing this strategy, including securing external fuel (see above, "Power - Fuel Supply, Logistics and Collaboration") and in advancing our nuclear fuel recycling and fuel fabrication efforts.
The DOE has reviewed and approved our Safety Design Strategy, Conceptual Safety Design Report, NSDA, and PDSA for the Aurora Fuel Fabrication Facility at INL-all key milestones as we advance toward our goal of utilizing recovered nuclear material to fuel our first commercial Aurora powerhouse. Our Aurora Fuel Fabrication Facility was also selected under the DOE Fuel Line Pilot Program ("FLPP"). The FLPP allows for acceleration of permitting, construction, and operation of nuclear fuel production lines for research, development, and demonstration purposes, supporting a fast-track approach to commercial licensing.
In addition, we successfully completed the first end-to-end demonstration of the key stages of our advanced fuel recycling process, in collaboration with Argonne and INL. This marks a significant step forward in scaling up fuel recycling capabilities and deploying a commercial-scale recycling facility.
In September 2025, we announced plans to design, build, and operate a fuel recycling facility in Tennessee as the first phase of an advanced fuel center (the "Advanced Fuel Center") to recycle used nuclear fuel into fuel for fast reactors, including our Aurora powerhouse line. The facility, which includes a roadmap of up to $1.68 billion in investment, will be the first of its kind in the U.S. and we estimate that it has the potential to create more than 800 high-quality jobs. We have completed a licensing project plan for the fuel recycling facility with the NRC and are currently in pre-application engagement with the regulator's staff. In June 2026, we entered into a non-binding memorandum of understanding with Standard Nuclear, Inc. to explore their potential purchases of our recycled nuclear fuel materials to support our advanced reactor fuel supply. The contemplated offtake arrangement remains subject to further diligence, negotiation, and execution of definitive agreements.
We are exploring opportunities with the Tennessee Valley Authority ("TVA") to recycle the utility's used fuel at a new facility and to evaluate potential power sales from future Oklo powerhouses in the region to TVA. The market interest in our solutions exemplifies the potential demand for the size range of the Aurora powerhouse product line and our differentiated business model.
Fuel is a significant input to enable us to build and operate our powerhouses at scale and generate expected returns. The cost environment for various sources of fuel (including HALEU) has increased significantly in recent years, which is why we are implementing a diversified fuel strategy. Tariffs, supply chain constraints, inflation, and evolving sanctions have impacted the market dynamics around fuel costs and availability. Beyond developing recycling and fuel fabrication
facilities, we are evaluating the use of alternative fuel materials, including plutonium currently designated for the DOE's dilute-and-dispose programs, that may be made available by the U.S. government for use in advanced reactor applications. Plutonium represents a potential near-term fuel option within a DOE-managed framework that complements Oklo's use of HALEU and longer-term fuel recycling strategy, providing additional flexibility as fuel markets evolve and supporting continued progress toward deployment in alignment with U.S. national priorities.
In December 2025, we completed a fast-spectrum plutonium criticality experiment in collaboration with Los Alamos National Laboratory. During the experiment, the plutonium-fueled system reached criticality and operated through controlled power maneuvers and transients, enabling the collection of operating data related to reactivity feedback and power response. This work places Oklo among a limited number of organizations with modern, experimental operating data for plutonium-fueled fast-spectrum reactor systems, providing valuable insight into key safety and performance characteristics.
In May 2026, we announced that Oklo had been selected by the DOE for advanced negotiations under the DOE's Surplus Plutonium Utilization Program. The program aims to make designated surplus plutonium material available to industry participants and enable the conversion of those materials into fuel for advanced nuclear reactors. Any potential use of such material would be subject to DOE authorization, applicable regulatory approvals, U.S. security, safeguards and material accountability requirements, applicable cost recovery requirements, and programmatic determinations regarding material availability. We believe that having multiple options for fueling our powerhouses, as well as developing optionality around fuel sources (including plutonium), will allow us to better navigate varying levels of regulatory oversight, fuel costs, and operational complexities with the purpose of strengthening our ability to navigate the shifting fuel landscape.
Isotopes
We are developing capabilities to produce and process radioisotopes used in cancer diagnosis and treatment and other medical and industrial applications. These efforts are part of our integrated nuclear strategy, creating opportunities to supply valuable products while building capabilities that support our power and fuel projects. Achieving first criticality at our Groves Isotope Test Reactor, as described below, marked a significant step toward isotope production and has already provided practical experience in nuclear construction, regulatory authorization, and operations that have informed development across Oklo.
On January 7, 2026, we announced the execution of a DOE Other Transaction Agreement ("OTA") to support the design, construction, and operation of the Groves Isotope Test Reactor located in Lockhart, Texas, under the DOE RPP. The execution of the OTA marked the transition from project selection and planning into active execution under DOE authorization. The project subsequently advanced through a series of DOE safety and authorization milestones, including approval of the NSDA on March 17, 2026, approval of the PDSA on May 27, 2026, and approval of the Documented Safety Analysis on June 30, 2026.
On July 23, 2026, the DOE granted startup authorization for our Groves Isotope Test Reactor under the DOE RPP, completing the DOE authorization process and allowing us to proceed with fuel loading, startup testing, and reactor operations. On August 5, 2026, the Groves Isotope Test Reactor achieved first criticality. The Groves Isotope Test Reactor is a low-power test reactor designed to demonstrate reactor design, construction, and operations and to help establish experience for future isotope production facilities. The Groves Isotope Test Reactor was developed on privately owned land, financed with private capital, and executed using full-scale systems, components, and fuel that were commercially sourced or manufactured by Oklo under DOE safety oversight. The Groves Isotope Test Reactor was the first reactor under the DOE RPP to reach criticality on private land.
The Groves Isotope Test Reactor is intended to support the testing and validation of radioisotope production methods and to inform the planning and execution of future commercial radioisotope production facilities. The project also required us to build and exercise capabilities across private-site development, nuclear safety analysis, quality assurance, commercial procurement, construction, commissioning, operator training and qualification, radiation protection, security, emergency preparedness, DOE readiness review, startup, and operations. Although each future facility will require project-specific engineering, safety analysis, licensing, and execution, the Groves Isotope Test Reactor provides an established organizational and operational foundation from which those projects can advance.
In parallel, our isotope business received a materials license from the NRC authorizing our radiochemistry laboratory in Idaho ("Idaho Radiochemistry Laboratory") to handle, process, and distribute licensed radioactive materials, supporting initial commercial isotope processing and supply activities. Together, the Groves Isotope Test Reactor and the Idaho Radiochemistry Laboratory support a staged commercialization strategy, with the Groves Isotope Test Reactor providing
deployment, authorization, and operating experience and the Idaho Radiochemistry Laboratory supporting initial commercial processing, customer supply, and further development of domestic isotope capabilities.
Our Business Model
In our differentiated build, own, and operate business model, we plan to sell power in the forms of electricity and heat directly to customers, which we believe can allow for fast-tracked customer adoption and broader market opportunities. In addition, we are a leader in the nuclear industry in the development of advanced fuel recycling, which can unlock the energy content of used nuclear fuel; we also believe this aspect of our business can complement our market position by vertically integrating and securing our fuel supply chain. In addition to our powerhouse and fuel recycling development, we are progressing construction of a pilot scale fuel fabrication facility and building plans for a first-of-a-kind new commercial scale fuel fabrication facility. Through our isotope business, we are combining our growing expertise in building and operating powerhouses and nuclear fuel recycling with our isotope business's expertise in radioisotope production. Together, we aim to meet the increasing demands for radioisotopes in medical, energy, industry, defense, and artificial intelligence applications.
The primary product for our power business will be the energy produced from our Aurora powerhouses once operational. Our primary business model is to sell the energy to customers through PPAs, as opposed to selling our powerhouse designs. This business model allows for recurring revenue, provides the opportunity to capture profitability of an Aurora powerhouse upon improved operational efficiency, and enables project financing structures. This business model sets us apart from the traditional nuclear power industry, which typically sells reactor design and engineering services to large scale utility customers and not power. Selling power through PPAs is a common practice within the renewable energy and utility sectors and indicates that this business model could be feasible for power plants within the size range targeted by our Aurora product line (i.e., 15 MWe-75 MWe, and ranging upward to potential sizes of 100 MWe and higher).
The traditional nuclear power industry comprises developers of large (ranging from approximately 600 MWe to over 1,000 MWe) light water reactors that sell or license their reactor designs to large utilities that then construct and operate the nuclear power plant. The developer's focus on regulatory approval of the design may lock in certain lifecycle regulatory costs that are realized by the owner-operator during construction and operations. As a result, lifecycle cost implications are generally not addressed cohesively between the developer and the owner-operator, and the regulatory strategy does not holistically implement the lifecycle benefits of the technology's inherent safety characteristics. The advanced fission industry has largely followed the historical blueprint of developers seeking design certifications or approvals, and utilities bearing the future burden of licensing for construction and operations. While there are a number of advanced reactor designers developing smaller sized reactors than those traditionally used in the nuclear power industry, many of these developers are generally pursuing regulatory approval of groupings of these smaller reactors as part of singular larger plants, sizes of 200 MWe and up to 1,000 MWe.
We plan to be the designer, builder, owner, and operator of our powerhouses and plan to focus on small-scale powerhouses (15 MWe-75 MWe, and potentially 100 MWe and higher). As a result, we have an incentive to relentlessly focus on the full lifecycle of a safe, well-maintained, cost-effective powerhouse and holistically implement the benefits of an inherently safe, simple design. We expect this approach to enable us to reduce and manage lifecycle regulatory and operating costs in an integrated fashion over time, as opposed to the historical model used in the nuclear power industry, which divides the incentives and responsibilities between the developer and the utility.
Additionally, this modular and scalable approach enables us to better deal with the inherent uncertainties, costs, and inefficiencies of the many service providers, manufacturers, fuel providers, and other third parties that we will rely on to build our powerhouses. While we expect that individual powerhouses may, and our first few powerhouses likely will, experience challenges that require us to manage unexpected costs and possible construction delays, our business model allows us to take the learnings from constructing those powerhouses and make improvements with future projects.
In particular, we expect the construction of our first powerhouse projects, including the Aurora-ID, to include investments that support both initial deployment and the development of our broader powerhouse fleet. These include enhanced fuel and core testing capabilities, as well as initial engineering, construction planning, and supply-chain development activities. Certain investments are specific to the capabilities planned for INL and are not expected to be required at each subsequent powerhouse, while other costs are expected to decline as we reuse designs, refine construction methods, and apply experience from initial deployments. The enhanced testing capabilities planned for Aurora-ID are intended to generate information on fuel and reactor performance that can inform future design and operating decisions. Although these capabilities add cost and complexity to the initial project, we expect them to support improvements in subsequent
deployments. We also expect opportunities to reduce costs through design optimization and standardization, repeat procurement, and more efficient construction execution. The extent and timing of these reductions will depend on deployment experience, site-specific requirements, supply-chain conditions, and the incorporation of lessons learned.
Selling electricity under PPAs follows an established revenue model in global power markets. While this model is more typically used for renewable energy solutions, we believe it is a compelling model for us because of the relatively small size and the lower expected capital costs of our powerhouses, when compared with other nuclear power plants. In addition, our model is designed to generate recurring revenue in a way that the traditional licensing model does not. Our powerhouses could be operating cash flow positive from the first year of operation due to our anticipated favorable unit economics. We also believe this approach will drive unit growth and allow us to ultimately launch higher output versions of our powerhouses. As our technology matures, we intend to offer customers flexibility in business model and deployment solutions to meet their needs, providing us with the largest target customer base possible. Given our growth stage, we continue to develop and evaluate our overall cost and potential pricing structure as we evaluate our unit economics, which we expect to be subject to market and extrinsic forces such as the impact of construction costs as a result of tariffs, supply chain pressures, and other macroeconomic factors.
In addition to selling power under PPAs, we are taking steps to enhance our mission with our fuel fabrication projects and advanced nuclear fuel recycling technology as well as executing targeted acquisitions to build capabilities to support our businesses. We are actively developing nuclear fuel recycling capabilities with the goal of deploying a commercial-scale fuel recycling facility in the U.S. by the early 2030s. Used nuclear fuel still contains approximately 95% of its energy content, and it has been estimated there is enough energy in the form of used nuclear fuel in the U.S. to power the expected electrical needs in the U.S. for 100 years with fast fission power plants. According to the DOE, more than 90,000 metric tons of used nuclear fuel have been generated since 1950, and an additional 2,000 metric tons are generated every year. Currently, other countries recycle used nuclear fuel, but the U.S. does not, and hence there is an enormous opportunity to do so.
Our reactors are specifically designed to run on fresh, recycled, or down-blended nuclear fuel, and nuclear fuel recycling and down-blending federal government materials could provide future margin uplift for our power sales business, as well as the potential for new revenue streams. We continue to evaluate the overall cost and timeline to be able to receive any potential benefit from this embedded opportunity. We are also evaluating the potential use of alternative fuel materials, including plutonium designated for dilute-and-dispose programs, that could be made available by the U.S. government for use in advanced reactors. This initiative complements our recycling work and supports the development of a resilient and diversified domestic fuel supply chain.
Recent Developments
Groves-2 Forge Selected for Nuclear Energy Launch Pad Initiative
On October 13, 2026, we announced plans to advance Groves-2 Forge, an isotope production and processing pilot facility, through the DOE's National Reactor Innovation Center Nuclear Energy Launch Pad initiative. The initiative provides selected participants with a prioritized pathway to the DOE authorization process and access to technical expertise and regulatory support. Groves-2 Forge is planned to build on our experience developing and operating the Groves Isotope Test Reactor under DOE authorization by integrating reactor irradiation with hot-cell processing, including isotope separation and product recovery, and capabilities for packaging and transportation. The facility is expected to focus initially on lutetium-177 and other therapeutic isotopes used in manufacturing radiopharmaceutical treatments. We intend to use these integrated capabilities to prepare isotope products and generate operating experience to support the planned transition of Groves-2 Forge from pilot operations to commercial-scale production, subject to obtaining the appropriate NRC licenses for commercial operation.
ARPA-E FORGE Program Award
On October 29, 2026, Oklo was awarded $6.8 million by ARPA-E towards our Fabrication of Optimized Recycled Fuel for Gen IV reactors from Electrorefiner Product ("FORGE") program. Through our FORGE program, Oklo will work alongside INL to develop metal fuel containing uranium, transuranic elements, and zirconium from recycled nuclear
materials. The effort will support our future development of recycled fuel for Oklo's Aurora powerhouses and other sodium-cooled reactors.
U.S. Forged Rings Strategic Manufacturing Agreement
In October 2026, Oklo entered into a strategic manufacturing agreement with U.S. Forged Rings, Inc. ("USFR") to support the deployment of our Aurora powerhouses. The agreement reserves USFR's planned domestic capacity for manufacturing large reactor components, including reactor vessels, lids, supporting structures, and other large stainless steel components The agreement contemplates initial finished component deliveries in 2030, with capacity reserved through 2035, and with certain options to expand the amount of capacity reserved.
Key Factors Affecting Our Performance
We believe that our future success and financial performance depend on a number of factors that present significant opportunities for our business, but also pose risks and challenges. As a result, we are subject to continuing risks and uncertainties. For additional information, see the section titled "Risk Factors" in Part II, Item 1A of this Quarterly Report and in Part I, Item 1A of Oklo's Annual Report on Form 10-K for the fiscal year ended December 31, 2025.
Product Development Plan
We plan to leverage the next-generation fast fission powerhouses that we are developing in order to sell power to a variety of potential customers, including data centers, military and other government facilities, factories, industrial customers, off-grid and remote communities, commercial and institutional campuses, and utilities.
Commercial deployment of any advanced fission power plant requires obtaining regulatory approvals for design, construction, and operation. For Aurora-ID, we are pursuing DOE authorization as the primary pathway to support construction, commissioning, and operations under DOE oversight. On June 11, 2026, we announced that the DOE approved the PDSA for the Aurora-ID under the DOE's RPP. The PDSA establishes the preliminary safety basis for the facility, including the hazard analysis, accident analysis, safety controls, and design commitments that support continued advancement of final design and construction.
We continue to engage with the NRC and advance activities that may support an NRC license for Aurora-ID and future commercial deployments. We are evaluating the timing and form of future NRC applications in light of evolving federal policy, NRC rulemaking, and implementation guidance, including the recently finalized Part 53 framework and proposed Part 57 framework. This approach allows Aurora-ID to continue progressing toward operations under DOE authorization while preserving NRC licensing optionality for Aurora-ID and our broader commercial fleet.
On October 26, 2026, the NRC published a final rule, effective November 25, 2026, establishing an additional framework for using relevant information from previously DOE-authorized reactors that have been tested and demonstrated the ability to function safely to support NRC licensing applications. We intend to use applicable safety analyses, testing results, and operating experience developed through the DOE authorization and operation of Aurora-ID to support subsequent NRC licensing of Aurora-ID and future Aurora deployments. We believe this framework could reduce duplicative technical reviews and improve licensing efficiency. Its application will depend on demonstrating the relevance of that information to the proposed NRC-licensed facility, addressing differences in design, operating conditions, and site characteristics, and satisfying applicable NRC requirements. The NRC retains independent review and licensing authority.
In July 2025, we completed a Phase I pre-application readiness assessment with the NRC to evaluate the maturity of our siting and environmental approach and our overall readiness to submit those parts of a combined license application. The assessment concluded with no significant gaps identified that would hinder acceptance of the application, marking a key milestone in our licensing strategy. It is uncertain when, if at all, we will obtain NRC approvals for the design, construction, and operation of any of our powerhouses. Our financial condition, commercial plans, and results of operations are likely to be materially and adversely affected if we do not obtain such approvals or if this process takes significantly longer or costs more than we expect.
Alongside ongoing NRC progress, on August 13, 2025, Oklo and Atomic Alchemy were selected by the DOE for three of the eleven projects awarded under the newly established RPP. Oklo was selected for two projects, and Atomic Alchemy for one project. Among these, the Aurora-INL powerhouse was approved to proceed under DOE purview, granting access to the DOE authorization pathway-a regulatory framework that provides full authority to construct and operate the
powerhouse while maintaining high safety standards. This designation supports deployment of the Aurora-INL powerhouse by streamlining federal review and providing a platform for demonstration of the Aurora powerhouse design to support future NRC licensing.
In August 2025, the NRC accepted for review our principal design criteria ("PDC") topical report for Aurora-ID, which establishes a regulatory framework that defines the fundamental safety, reliability, and performance requirements to guide future reactor licensing and design activities. The NRC accepted our PDC topical report under an accelerated timeline and approved the PDC topical report in April 2026.
Additionally, we plan to be the designer, builder, owner, and operator of our powerhouses and plan to focus on small-scale powerhouses (15 MWe, 75 MWe, and potentially 100 MWe and higher designs). As a result, we have an incentive to relentlessly focus on the full lifecycle of a safe, well-maintained, cost-effective powerhouse and holistically implement the benefits of an inherently safe, simple design. We expect this approach to enable us to reduce and manage lifecycle regulatory and operating costs in an integrated fashion, as opposed to the historical model used in the nuclear power industry, which divides the incentives and responsibilities between the developer and the utility. However, this model exposes us directly to the costs of building, owning, and operating our powerhouses. Our cost projections and timelines are heavily dependent upon fuel, raw materials (such as steel), equipment, and technical and construction service providers (such as engineering, procurement, and construction firms). The global supply chain on which we will rely (including for HALEU), has been significantly impacted in recent years by inflation, instability in the banking sector, war and other hostilities, and other economic uncertainties, resulting in potential significant delays and cost fluctuations. Similar developments in the future may impact our performance from both a deployment and cost perspective. Our initial assets in operation will represent the first deployment of our Aurora design and, as such, will be subject to risk around both cost and time associated with first-of-a-kind capital project delivery. In particular, we expect the construction of our first powerhouse at INL to include additional, unique costs as compared to the costs expected for future powerhouse projects. Such additional costs will result, in part, from design decisions to include enhanced fuel and core testing capabilities, which will be more costly and complex to design and build. We expect future powerhouses to benefit from substantial cost reductions as compared to our first reactor deployment.
Plan of Operations
To further our ambitious target of deploying our first powerhouse in 2028-2029 and support subsequent powerhouse deployments and the development of our fuel and isotope businesses, amidst a range of supply chain, geopolitical, macroeconomic, and design complexities, we plan to pursue the following key initiatives:
•Progressing regulatory approval for powerhouse deployments with both the DOE and the NRC.
•Progressing regulatory pre-application related activities with the NRC for licensing of commercial fuel fabrication.
•Continuing work and regulatory activities related to fuel recycling, such as pre-application regulatory alignment efforts with the NRC, and research and development, both independently and in conjunction with the DOE, focused on facility and process design for the Oklo fuel recycling facility.
•Working with INL on fuel manufacturing, including preparation of documentation for regulatory review, finalization of the facility design, and expected construction activities.
•Negotiating and executing fuel supply agreements with uranium enrichment counterparties to secure future supplies of HALEU for Aurora powerhouse deployments, while advancing fuel fabrication and related procurement arrangements to support our broader fuel supply strategy.
•Advancing DOE authorization and related design activities for the Aurora Fuel Fabrication Facility at INL, which is intended to fabricate fuel for Oklo's first commercial-scale Aurora powerhouse, the Aurora-ID.
•Advancing plans for our Advanced Fuel Center in Oak Ridge, Tennessee-beginning with a proposed fuel recycling facility-to support fuel recycling and fabrication capabilities.
•Evaluating the potential use of alternative U.S. government fuel materials, including plutonium for use in advanced reactor applications, in support of Oklo's multi-pronged fuel strategy and domestic fuel supply chain development.
•Executing on key non-fuel elements of our supply chain, including reactor module systems, refueling systems, steam turbine generators, structural steel, and other critical construction inputs.
•Progressing engineering procurement and construction activities in support of the construction of Aurora powerhouses.
•Working with Kiewit Nuclear Solutions Co. ("Kiewit"), who was selected as the lead constructor for our first Aurora powerhouse in Idaho, a major milestone toward project delivery and execution.
•Continuing and initiating site preparation for announced power facilities at INL and Pike County, Ohio, respectively. We will begin site preparation for other announced projects based on prioritization, potentially including prospective customers such as Meta, Equinix, Diamondback Energy, Prometheus Hyperscale, Switch, and other future projects.
•Exploring activities related to, or in support of, various Executive Orders that look to accelerate the deployment of domestic, advanced nuclear energy.
•Negotiating and executing additional letters of intent, memoranda of understanding, and master partnership agreements and converting such preliminary agreements into PPAs with multiple potential customers.
•Negotiating term sheets and binding PPAs with customers who have previously signed nonbinding agreements such as letters of intent to purchase power.
•Pursuing potential isotope sales opportunities, including evaluating customer interest, commercial structures, and related agreements to support future commercial opportunities.
•Continuing to hire additional personnel and implement processes and systems necessary to deliver our business strategy.
•Progressing production of radioisotopes by our isotope business, assessing options to scale production, and developing and executing plans to grow this business, including developing plans for our Groves-2 Forge project.
•Evaluating potential acquisition opportunities to strategically accelerate our business and enhance our capability to execute on our business plans.
•Evaluating opportunities across the nuclear space sector, including potential applications involving radioisotope power systems and related technologies, in light of recent customer interest, industry procurement activity, and market demand.
•Continuing to pursue activities, such as our ATM Program, to raise capital at the corporate and asset levels.
For the nine months ended September 30, 2026 and the year ended December 31, 2025, our total operating expenses were $209.7 million and $139.3 million, respectively.
We expect our total cash used in operating activities for 2026 to be in the range of $120 million to $150 million and our total cash used for purchases of property, plant and equipment to be in the range of $400 million to $500 million.
Nuclear Energy Industry
The nuclear energy industry operates in a politically sensitive environment, and the successful execution of our business model is dependent upon public support for nuclear power in the U.S. and other countries. The U.S. government has in recent years consistently indicated through bipartisan action that it recognizes the importance of nuclear power in meeting the United States' growing energy needs. As an example, the ADVANCE Act, which was signed into law on July 9, 2024
with significant bipartisan support, streamlines licensing, reduces costs, and boosts U.S. leadership in advanced nuclear energy by modernizing regulations, supporting fuel innovation, and expanding global competitiveness.
On May 23, 2025, four Executive Orders directed federal agencies to streamline licensing at the NRC, accelerate advanced reactor deployment at DOE and U.S. Department of Defense sites for national security and AI and data-center needs, overhaul the domestic nuclear fuel cycle, and strengthen the U.S. nuclear industrial base. These Executive Orders, together with proposed legislation, reflect sustained federal interest in strengthening domestic energy security, supporting growth in electricity demand, including demand associated with AI and data-center infrastructure, and promoting advanced nuclear deployment. The timing and scale of electricity demand associated with AI and data-center development remain uncertain and are subject to changing customer investment priorities, technological developments, public and political scrutiny, and regulatory and permitting constraints. Ongoing DOE initiatives, including the RPP and FLPP, further demonstrate federal focus on developing a resilient nuclear fuel cycle and advancing advanced reactor technologies.
Additionally, opponents of advanced nuclear deployments in the U.S. and intervenors in regulatory proceedings could delay the licensing that our business model requires. As a result, our performance will depend in part on factors generally affecting the views and policies regulating the nuclear energy industry, which we cannot predict over the long term.
Key Components of Results of Operations
Revenue
In June 2026, we completed the acquisitions of two advanced engineering companies, ARMEC and CEI. These two highly specialized teams bring precision manufacturing and mechanical engineering expertise specializing in high-precision machining and prototyping, and mechanical engineering services and chemical process engineering expertise in sodium and alkali-metal systems, both for the nuclear industry, to expand Oklo's engineering capabilities. Both of these newly acquired subsidiaries continue to provide engineering services to an established group of customers. Revenue is generated from contracts with government agencies and commercial counterparties for engineering, design, licensing support, technical consulting, research and development activities, and other services related to advanced nuclear technology development.
Operating Expenses
Operating expenses consist of cost of sales, research and development, and general and administrative expenses.
Cost of Sales
Cost of sales includes direct costs incurred in satisfying performance obligations under customer contracts.
Research and Development
Research and development ("R&D") expenses represent costs incurred to develop our technologies. These costs consist of personnel costs, including salaries, employee benefit costs, bonuses, and stock-based compensation expenses, software costs, computing costs, hardware and experimental supplies, and expenses for outside engineering contractors for analytical work and consulting costs. We expense all R&D costs in the periods in which they are incurred; however, occasionally, reimbursements could be received in a subsequent period.
We have several recycling technology projects awarded as R&D cost-share projects (the "cost-share projects") through the DOE's Advanced Research Projects Agency - Energy ("ARPA-E") and the DOE Technology Commercialization Fund ("TCF"). The ARPA-E and TCF projects involve cost-sharing of project costs as well as reimbursement of certain qualifying expenditures to us. A budget was initially approved for each of these cost-share projects, and as certain expenses and capital expenditures for equipment are incurred, such expenses or capital expenditures are reported to ARPA-E, and then a pre-determined percentage of such expenses or capital expenditures are reimbursed by ARPA-E back to us. The expenses are categorized as R&D expenses, which are then partially reimbursed.
General and Administrative
General and administrative ("G&A") expenses primarily comprise various components not related to R&D, such as personnel costs, regulatory fees, promotional and marketing expenses, costs associated with maintaining and filing intellectual property, meals and entertainment expenses, travel expenses, and other expenditures related to external professional services including legal, engineering, human resources, procurement, audit, finance, consulting, and
accounting services. Personnel costs include salaries, benefits, and stock-based compensation expenses. As we continue to grow and expand our workforce and operations, and in light of the increased costs associated with operating as a public company, we anticipate that our G&A expenses will rise for the foreseeable future.
Gain on Sale of Asset
Gain on sale of asset relates to the sale of land to a third-party.
Other Income
Other income consists of interest and dividend income, unrealized gain on investments, net, and other nonoperating income and expenses incurred.
Interest and Dividend Income, Net
Interest and dividend income, net, relates primarily to fixed-income interest or dividend payments from our marketable securities balances.
Unrealized Gain on Investments, Net
Unrealized gain on investments, net, relates to changes in the fair value of publicly traded equity securities held by the Company.
Income Taxes
Income taxes consist of income taxes in jurisdictions in which we conduct business. We have a full valuation allowance for deferred tax assets, including net operating loss carryforwards and tax credits related primarily to R&D. Federal and state income taxes may be incurred as a result of our revenue and interest income from investments, after available tax deductions and tax attribute carry-overs.
Results of Operations
The following tables set forth our condensed consolidated results of operations for the periods indicated. The period-over-period comparison of financial results is not necessarily indicative of future results.
Comparison of the Three Months Ended September 30, 2026 and 2025
The following table sets forth our historical results for the periods indicated, and the changes between periods:
Three Months Ended September 30, 2026 versus 2025
(in thousands)
2026 2025 $ Change % Change
Revenue $ 1,861 $ - $ 1,861 NM
Operating expenses
Cost of sales 1,089 - 1,089 NM
Research and development 41,645 14,945 26,700 178.7 %
General and administrative 41,574 21,364 20,210 94.6 %
Gain on sale of asset 11,430 - 11,430 NM
Other income (expense)
Interest and dividend income, net 27,885 7,118 20,767 291.8 %
Unrealized gain on investments, net 2,034 - 2,034 NM
Other non-operating expenses (491) - (491) NM
Income tax (expense) benefit (157) (531) 374 (70.4) %
Percentage changes that are considered not meaningful are denoted with "NM."
Revenue
Revenue during the three months ended September 30, 2026 primarily resulted from the June 2026 acquisitions of ARMEC and CEI .
Cost of Sales
Cost of sales during the three months ended September 30, 2026 resulted from the June 2026 acquisitions of ARMEC and CEI .
Research and Development
R&D expenses increased by $26.7 million from 2025 to 2026 as presented above, primarily driven by increases in employee compensation expenses, consisting of an increase in payroll and employee benefits costs of $9.9 million and stock-based compensation costs of $4.1 million. Increases in employee compensation expenses were primarily driven by an increase in average headcount of approximately 155 employees compared with the prior year period. In addition, professional services increased by $8.3 million, driven by an increase in costs from third-party service providers for engineering consulting and professional services.
General and Administrative
G&A expenses increased by $20.2 million from 2025 to 2026 as presented above, primarily driven by increases in employee compensation expenses, consisting of an increase in payroll and employee benefits costs of $5.2 million and stock-based compensation costs of $6.0 million. Increases in employee compensation expenses were primarily attributable to an increase in average headcount of approximately 85 employees compared with the same period in 2025. In addition, IT-related costs increased by $1.5 million, travel expenses increased by $1.1 million, occupancy expenses increased $0.9 million, and professional services increased by $0.5 million, driven primarily by net changes in costs associated with accounting, consulting, marketing services.
Gain on Sale of Asset
Gain on sale of asset of $11.4 million in the period ending September 30, 2026 arose from the sale of land in the ordinary course of business.
Other Income
Interest and dividend income increased by $20.8 million from 2025 to 2026 as presented above, primarily driven by an increase in our cash, cash equivalents and marketable debt securities balances from the prior year period as a result of equity issuances. In addition, unrealized gain on investments, net, increased by $2.0 million from 2025 to 2026 as certain investments held by the Company were reported at fair value as of September 30, 2026, whereas no such investments were reported at fair value as of September 30, 2025. Refer to Note 4-Balance Sheet Components for additional information.
Income Taxes
Income tax expense increased by 0.4 million from 2025 to 2026 as presented above, primarily driven by a change in the estimated accrual for state income tax during the period.
Comparison of the Nine Months Ended September 30, 2026 and 2025
The following table sets forth our historical results for the periods indicated, and the changes between periods:
Nine Months Ended September 30, 2026 versus 2025
(in thousands) 2026 2025 $ Change % Change
Revenue $ 3,071 $ - $ 3,071 NM
Operating expenses
Cost of sales 1,810 - 1,810 NM
Research and development 108,168 34,259 73,909 215.7 %
General and administrative 99,706 47,939 51,767 108.0 %
Gain on sale of asset 11,430 - 11,430 NM
Other income (expense)
Interest and dividend income, net 72,433 14,532 57,901 398.4 %
Unrealized gain on investments, net 2,034 - 2,034 NM
Other non-operating expenses (2,472) - (2,472) NM
Income tax (expense) benefit (159) 3,449 (3,608) NM
Percentage changes that are considered not meaningful are denoted with "NM."
Revenue
Revenue during the nine months ended September 30, 2026 primarily resulted from the June 2026 acquisitions of ARMEC and CEI.
Cost of Sales
Cost of sales during the nine months ended September 30, 2026 resulted from the June 2026 acquisitions of ARMEC and CEI .
Research and Development
R&D expenses increased by $73.9 million from 2025 to 2026 as presented above, primarily driven by increases in employee compensation expenses, consisting of an increase in payroll and employee benefits costs of $22.8 million and stock-based compensation costs of $13.0 million. Increases in employee compensation expenses were primarily driven by an increase in average headcount of approximately 113 employees compared with the same period in 2025. In addition, professional services increased by $29.2 million, driven by an increase in costs from third-party service providers for engineering consulting and professional services.
General and Administrative
G&A expenses increased by $51.8 million from 2025 to 2026 as presented above, primarily driven by increases in employee compensation expenses, consisting of an increase in payroll and employee benefit costs of $15.2 million and stock-based compensation costs of $13.3 million. Increases in employee compensation expenses were primarily driven by an increase in average headcount of approximately 64 employees compared with the prior year period. In addition, professional services increased by $9.7 million, driven primarily by net changes in costs associated with accounting, consulting, and marketing services, travel expenses increased by $3.0 million, IT-related costs increased $2.8 million, and occupancy expenses increased $1.6 million.
Gain on Sale of Asset
Gain on sale of asset of $11.4 million in the nine months ended September 30, 2026 arose from the sale of land in the ordinary course of business.
Other Income
Interest and dividend income increased by $57.9 million from 2025 to 2026 as presented above, primarily due to an increase in our cash, cash equivalents and marketable debt securities balances from the prior year period as a result of equity issuances. In addition, unrealized gain on investments, net, increased by $2.0 million from 2025 to 2026 as certain investments held by the Company were reported at fair value as of September 30, 2026, whereas no such investments were reported at fair value as of September 30, 2025. Refer to Note 4-Balance Sheet Components for additional information.
Income Taxes
Income tax benefit decreased by $3.6 million from 2025 to 2026 as presented above, primarily driven by the decrease of an income tax benefit of $3.4 million related primarily to discrete items recognized in connection with the acquisition of Atomic Alchemy in the prior period.
Liquidity and Capital Resources
As of September 30, 2026, our cash, cash equivalents, and marketable debt securities were $3,130.8 million. In addition, the Company has restricted cash of $81,900 as of September 30, 2026. We continue to incur significant operating losses. For the nine months ended September 30, 2026, we had a net loss of $123.3 million, loss from operations of $195.2 million, and net cash used in operating activities of $110.9 million. As of September 30, 2026, we had an accumulated deficit of $364.1 million. Management expects that significant on-going operating and capital expenditures will be necessary to successfully implement our business plan, develop our powerhouses, fuel recycling facilities and fuel fabrication technology, acquire fuel for those powerhouses and recycling facilities, and expand our radioisotope business.
We will utilize our existing cash, cash equivalents, and marketable debt securities to fund our powerhouses, radioisotopes and fuel businesses, operations, and growth plans, and we believe that our existing cash, cash equivalents, and marketable debt securities will be sufficient to fund our operations for the one-year period following the issuance date of the accompanying unaudited condensed consolidated financial statements as of and for the nine months ended September 30, 2026.
Off-Balance Sheet Arrangements
We did not have any off-balance sheet arrangements as of September 30, 2026.
Commitments and Contractual Obligations
We did not have any material commitments or contractual obligations as of September 30, 2026.
Cash Flows Comparison
A summary of our consolidated sources and uses of cash and cash equivalents was as follows:
Nine Months Ended September 30,
(in thousands) 2026 2025
Net cash used in operating activities $ (110,941) $ (48,745)
Net cash used in investing activities (1,298,582) (605,906)
Net cash provided by financing activities 2,253,039 967,560
Net increase in cash, cash equivalents and restricted cash $ 843,516 $ 312,909
Cash, cash equivalents, and restricted cash, end of period $ 1,631,961 $ 410,041
Operating Activities
Net cash used in operating activities was $110.9 million in 2026, compared to $48.7 million in 2025. The $62.2 million increase in net cash used in operating activities from 2025 to 2026 was primarily driven by operating expenses as we continue to scale our operations.The activity during the current period consists of $58.5 million cash used for payroll and employee benefits of personnel and $126.7 million in other costs, primarily relating to professional services for consulting on research and development activities, and legal and accounting fees on general and administrative activities. These cash outflows during the period were partially offset by $70.0 million in higher cash interest and dividend income, resulting from our increased balance of cash, cash equivalents and marketable debt securities.
Investing Activities
Net cash used in investing activities was $1,298.6 million in 2026 compared to net cash used in investing activities of $605.9 million in 2025. The increase in net cash used in investing activities of $692.7 million from 2025 to 2026. The activity during the current period primarily relates to cash used for the purchase of marketable debt securities, offset from proceeds from redemptions, netting to $965.1 million, capital expenditures related to deployment of our planned facilities,
including capital expenditure prepayments of $280.9 million, other investments of $26.5 million, and cash used for acquisition of businesses of $25.7 million.
Financing Activities
Net cash provided by financing activities was $2,253.0 million in 2026 compared to net cash provided by financing activities of $967.6 million in 2025. The increase in net cash provided by financing activities was $1,285.4 million from 2025 to 2026. The activity during the current period primarily relates to proceeds from the issuance and sale of shares of our common stock in connection with our ATM programs of $2,254.3 million.
Critical Accounting Estimates
Part II, Item 7, Management's Discussion and Analysis of Financial Condition and Results of Operations in our Annual Report on Form 10-K for the fiscal year ended December 31, 2025 provides a more complete discussion of our critical accounting policies and estimates.
Emerging Growth Company Status
The Company is classified as an emerging growth company ("EGC"), as defined under the Jumpstart Our Business Startups Act (the "JOBS Act"). Therefore, we are eligible to utilize certain exemptions from various reporting requirements that are applicable to other public companies that are not EGCs. We will retain EGC status until December 31, 2026.
Further, Section 102(b)(1) of the JOBS Act exempts EGCs from being required to comply with new or revised financial accounting standards until private companies (that is, those that have not had a Securities Act registration statement declared effective or do not have a class of securities registered under the Exchange Act) are required to comply with the new or revised financial accounting standards. The JOBS Act provides that a company can elect to opt out of the extended transition period and comply with the requirements that apply to non-EGCs, but any such election to opt out is irrevocable. We intend to take advantage of the benefits of this extended transition period.
Recent Accounting Pronouncements
See Note 2-Summary of Significant Accounting Policies of the notes to our unaudited condensed consolidated financial statements included in Part I, Item 1 of this Quarterly Report for additional information regarding recently adopted accounting standards and recently issued and not adopted accounting standards as of the date of this report.
Oklo Inc. published this content on November 06, 2026, and is solely responsible for the information contained herein. Distributed via EDGAR on November 06, 2026 at 12:33 UTC. If you believe the information included in the content is inaccurate or outdated and requires editing or removal, please contact us at [email protected]