San Francisco County - Caltrans is scheduled to begin the third weekend closure for the 19th Avenue Rehabilitation Project from Friday, May 22 to Monday, May 25. This is the second phase of the project as the first phase was completed in January 2026.
The schedule for the final weekends is a 75-hour closure from Friday, May 22 from 7 a.m. until Monday, May 25 at 10 a.m. on Southbound/Northbound 19th Avenue from Sloat Boulevard to Holloway Avenue.
Two lanes will be closed with one lane open for public transit, emergency responders, and local access.
Organizing the work in three weekend closures will reduce impact on the public from 40 to 10 days.
The second phase of this project repaves all northbound and southbound lanes of 19th Avenue (also known as State Route 1) between Lincoln Way and Holloway Avenue, approximately 18.8 lane miles, and the Park Presidio Boulevard and the California Street intersection.
The California Street/Park Presidio intersection will be repaved later during the summer. The schedule also includes upgrading the traffic detection system.
Parking on 19th Avenue will be restricted to work zones during weekend closures; parking is permitted on side streets.
Even though one lane will always remain open to traffic while repaving is underway, motorists are encouraged to use alternative routes.
For more on the 19th Avenue project, see https://bit.ly/3PKYF2v
Photos and videos of the weekend work progression are available at https://www.sfhighwayprojects.com
For real-time traffic, click on CaltransQuickMap: http://quickmap.dot.ca.gov/
For 24/7 traffic updates, follow 511.org: https://twitter.com/511SFBay
| CleanCA.com | #BeWorkZoneAlert | Twitter | Facebook | YouTube |