SAN FRANCISCO COUNTY - Caltrans is scheduled to begin the second and final phase of the 19th Avenue Rehabilitation Project in spring 2026, after the successful completion of the first phase in January 2026. The second phase will repave all northbound and southbound lanes of 19th Avenue (State Route 1) between Lincoln Way and Holloway Avenue, approximately 18.8 lane miles, and Park Presidio Boulevard and the California Street intersection.
Organizing the work in three weekend closures will reduce impact on the public from 40 to nine days.
For all three closures, two lanes are scheduled to be fully closed with one lane open for public transit, emergency responders and local access.
The schedule is as follows:
The second phase of the project includes resurfacing the existing asphalt pavement on SR-1 from Holloway Avenue to Lincoln Way. California Street/Park Presidio intersection will be repaved later during the summer. The schedule also includes upgrading the traffic detection system. Parking on 19th Avenue will be restricted to work zones during weekend closures; parking is permitted on side streets.
Even though one lane will always remain open to traffic while repaving is underway, motorists are encouraged to use alternative routes.
Alternate route for the April 24 weekend for Junipero Serra Boulevard
Alternate route for the April 24 weekend for Brotherhood Way
For more on the 19th Avenue project, see https://bit.ly/3PKYF2v
For 24/7 traffic updates, please visit 511.org: https://x.com/511SFBay
For real-time information, visit Caltrans QuickMap: https://quickmap.dot.ca.gov
Follow us on X: https://x.com/CaltransD4
Or call 1-800-472-7623, 1-800-427-ROAD for state highway conditions statewide.