11/19/2026 | Press release | Distributed by Public on 11/19/2026 10:38
SOUTHFIELD, Mich. - As the Restore the Reuther I-696 project between M-10 and I-75 gets closer to completion, the eastbound lanes are close to reopening sometime this weekend. Punch list work remains; sign installation, pavement marking removal and replacement, etc., are being wrapped up this week. The work is weather dependent.
To allow crews to safely remove and replace pavement markings approaching the current detour route of eastbound I-696 near M-10 and US-24 (Telegraph Road), traffic will need to be reduced to one lane. During this work, once traffic is east of M-10, then eastbound I-696 will reopen completely to I-75.
Drivers should expect the following:
8 a.m. - 5 p.m. Saturday, Nov. 21:
5 p.m. Saturday, Nov. 21 - mid-December:
This final phase of the $250 million Restore the Reuther project (involving replacing 8 miles of pavement, improving 60 bridges and rebuilding the Church Street plaza) will resume in early 2027 with major road work to be performed between I-75 and Dequindre Road. That work includes pavement improvements, roadway rebuilding, bridge improvements and drainage structures.
Project information is available at DrivingOakland.com.