Starting Wednesday night, November 18, the Rhode Island Department of Transportation (RIDOT) is scheduled to begin a series of traffic pattern changes as part of the ongoing reconstruction of the I-95/Route 10 interchange in Cranston and Providence. These changes are temporary and may require additional travel time.
A summary of the upcoming changes and expected schedules is as follows:
November 18: Route 10 North coming from Park Avenue will shift to the left just prior to Elmwood Avenue. This will move traffic onto a newly constructed bridge over Elmwood Avenue.
This change affects the lanes drivers will use to their next destination:
� To access I-95 North (Exit 1B), drivers must use the right lane. � To access I-95 South (Exit 1C) or to continue driving north on Route 10 toward Providence, drivers must use the left lane.
The same lane selection will be required of drivers coming onto Route 10 from Elmwood Avenue. RIDOT will install additional signs and pavement markings to clearly show which lane drivers should use. This change will be in place until spring 2027.
November 20: As previously announced, a lane split will be installed on I-95 South beginning about one-half mile before the Jefferson Boulevard off-ramp (Exit 31C) on the Cranston/Warwick line. The lane split is necessary for phased replacement of the bridges that carry I-95 over the Pawtuxet River and Jefferson Boulevard.
December 4: The on-ramp to Route 10 North from I-95 North (Exit 33A) will shift slightly to the left as it passes over I-95 as RIDOT shifts traffic onto a newly constructed bridge. Future shifts are planned as RIDOT reconstructs the ramp itself.
December 6: A section of Route 10 South will shift to the left between Elmwood Avenue and Park Avenue for median barrier construction. This section is being rebuilt as a boulevard style street instead of a highway. The road will shift back to its current alignment by the end of the year.
Mid-December: RIDOT will conduct another weekend overnight closure of I-95 at the Route 10 (Exit 33) interchange. The closures are necessary for demolition work over the highway. Some ramps to and from Route 10 also will be closed. During the closures, RIDOT strongly advises motorists to seek alternate routes, such as I-295 and Route 10, to avoid delays and extended travel times. RIDOT will announce more details in advance once the schedule has been confirmed.
These improvements are part of the I-95 15 Bridges project, which is removing 15 bridges from the state's backlog of poor and fair to poor condition bridges along I-95 and Route 10 between Providence and Warwick. Nine of the 15 bridges are structurally deficient. Three are rated among the top five most traveled structurally deficient bridges in Rhode Island. At the Huntington Viaduct, RIDOT is redesigning the entire interchange of Route 10 with I-95. More details are available at www.ridot.net/The-I-95-15.
All construction projects are subject to changes in schedule and scope depending on needs, circumstances, findings, and weather.