Anderson County
Palestine crews are scheduled to repair edges and potholes at various locations throughout the county.
Anderson County construction projects updates:
US 175 Widening Project
Traffic is currently being switched to the new pavement on the westbound lane, while the contractor works on the eastbound lane. The contractor is constructing driveways and ditches in area. The contractor will also continue setting panels and rail on the new eastbound bridge, as well as finalize ditches and slopes. The project consists of expansion to a four-lane roadway with new bridges across the Neches River.
US 79 Truck Parking Area
The contractor is awaiting final acceptance. The project includes concrete curb and gutter, earthwork, and drainage improvements.
Gus Engeling Texas Parks and Wildlife
The contractor is awaiting final acceptance. The project includes surface treatment, pavement striping, and drainage improvements.
----------------------------------------
Cherokee County
Jacksonville and Rusk crews will be performing work at the maintenance yards.
Cherokee County construction projects updates:
US 175 Widening Project
The following county road intersections will be closed within the project limits:
The contractor will continue work through Cuney on the eastbound side. Preparation of the right of way has started on the westbound side of the highway, beginning from the Jacksonville end of the project. The contractor will also continue working on bridge elements, setting deck panels, clearing utility items, and building storm drain systems. Motorists should use caution when traveling through the area. The speed limit is reduced to 55 mph throughout the project limits. The project consists of expansion to a four-lane roadway with new bridges, grading, asphalt, drainage structures, pavement markings, and signage. (This project is located in Cherokee County but is managed by the Athens Area Office.)
SH 204
This week, the contractor is scheduled to begin one-course surface treatment, placing topsoil, and seeding. Crews will also continue SW3P operations. Motorists should drive with caution in the work zone. Lane closures are anticipated. This project consists of adding a super-two highway section.
US 79
The contractor is scheduled to begin laying hot mix. Lane closures are expected. Speed limit has been reduced to 55 mph throughout the project limits. This project consists of rehabilitation of the existing road, including pavement repair, resurfacing, metal beam guard fence, and pavement markings.
SH 110
No work scheduled this week. This project is a change order to a bridge preventative maintenance project that consists of installing a temporary soil nail wall and a permanent retaining wall to address slope failure on SH 110. Motorists should drive with caution when work is in progress.
US 69 and FM 2493 Grade Separated Interchange Realignment
The contractor is scheduled to work on curb and gutter at various locations throughout the project limits. Work will be on both the east and westbound sides. Also, the contractor is scheduled to lay some topsoil and perform dirt work on the US 69 northbound frontage roads. No lane closures are expected, but motorists should still drive with caution. The project consists of a grade separated interchange and realignment of FM 2493 West of US 69.
US 69 Safety Improvement
The contractor will be on US 69 in Alto, working on the metal beam guard rail for the southbound lanes. Motorists should drive with caution. Lane closures are anticipated. The project consists of safety improvements consisting of the installation of a median cable and concrete barrier.
----------------------------------------
Gregg County
Gregg County construction projects updates:
US 80
This week, the contractor will be milling and patching base failures. The project consists of removing four inches of existing surface and replacing with new hot mix. The project will also include striping and pavement markings.
Young St. - City of Longview
This week, the project will be clearing right of way and pouring concrete for the sidewalk on the north side of the street. This project consists of constructing sidewalks and handicap accessible ramps on both sides of Mobberly Ave.
SH 135 - Kilgore Traffic Circle
This week, crews are scheduled to place the final striping and work on punch list items. This project involves rebuilding the traffic circle and the entire width of the roadway to the Rusk County line.
I-20 Resurfacing
This week, the contractor is scheduled to lay asphalt beginning Sunday, Aug. 24. Motorists should expect alternating east and westbound lane closures. Work will be done at night. This project consists of milling asphalt off of the surface and placing new asphalt.
----------------------------------------
Henderson County
Athens crews are scheduled to perform ditch maintenance at various locations. Expect lane closures with flaggers controlling traffic. Additional crews will be conducting bridge channel maintenance at various locations.
Henderson County construction projects updates:
SH 198 Bridge Project
The contractor is awaiting final acceptance. The project includes replacing bridges and approaches, grading, structures, base and surface work, retaining walls, curbs and gutters, fencing, and striping.
FM 316 Rehabilitation
The project is in time suspension and awaiting final acceptance. The project includes pavement reconstruction, structures, pavement markings and signs.
FM 315 Rehabilitation
The contractor currently performing edge work at various locations throughout the project limits. There should be no impact to traffic. The project includes pavement reconstruction, structures, pavement markings and signs.
BUS 19 Sidewalks
The contractor is placing concrete for the sidewalks and driveways on the west side of the road. Motorists should expect lane closures while work is in progress. This project includes sidewalk and pedestrian lane improvements.
SH 19 Super 2 Project
The contractor has begun cement treating for roadway widening in the southbound lane. The speed limit is reduced to 60 mph throughout the project limits. This project includes adding a passing lane in each direction at multiple locations. It also includes grading, drainage structures, pavement markings, and signage.
BUS 31 Rehabilitation
Nighttime operations are scheduled to continue this week. Motorists should expect lane closures. The project includes removal of current surface, base repairs, resurfacing, striping, and signage. Traffic should use caution when traveling through the work zone at night and expect pavement striping operations during the day.
SH 31 at Sawmill Rd.
The contractor will install striping at the new traffic signal. Traffic should use caution while traveling through the work zone. This project consists of installing a traffic control signal and pedestrian signal.
----------------------------------------
Rusk County
Henderson crews are scheduled to repair edges on FM 2753 and repair potholes at various locations. Motorists should expect lane closures with flaggers controlling traffic. Also, contractor crews will be striping on FM 1971. Motorists should expect lane closures with flaggers controlling traffic.
Rusk County construction projects updates:
US 84 - FM 225 East to CR 3155
This week, the contractor is scheduled to cement treat the subgrade and applying oil coat. Motorists should expect alternating lane closures while work is in progress. This project consists of reconstructing US 84, extended structures, hot mix asphalt surface, new signs, and striping.
SH 315
This week, the contractor is scheduled to lay asphalt. Motorists should expect alternating lane closures. Crews will also perform striping and guard fence installation. This project consists of widening pavement edges and installing space between the traffic lanes to separate opposing traffic for safety. Work will also include adding one passing lane in each direction of travel.
FM 2658
This week, the contractor is scheduled place sealcoat. This project consists of reconstructing FM 2658 completely, from CR 344 to FM 1251. Work includes a new guard fence, treating subgrade, base material, seal coat, and striping.
US 79 N
This week, the contractor will be working on punch list items. Work will mostly be off of the roadway. This project consists of repairing slope failure in the TxDOT right of way. The site will be excavated, and a new embankment will be placed.
SH 43
This week, the contractor is scheduled place final striping and working on the edge of the pavement. Expect lane closures with flaggers controlling traffic. This project consists of milling approximately six inches off the surface and replacing it with new hot mix. The project also includes clearing the right of way, replacing driveway pipes, and striping.
----------------------------------------
Smith County
Smith County crews are scheduled to work on drainage and ditch complaints throughout the county.
Smith County construction projects updates:
US 69 Rehab Existing Road and Restricted Crossing U-Turn (R-Cut)
The contractor is scheduled to clean and seal the bridge joints at the Mudd Creek bridge. Crews are also scheduled to perform concrete work on the bridge. This work will be done during daytime hours. Lane closures are expected. This project consists of rehabilitating existing roadway and installing a restricted crossing U-turn (R-Cut) at FM 2813 intersection.
SH 31 Safety Improvement
The contractor is working on the US 69 portion of this project in Cherokee County. This project consists of safety improvements consisting of backfill and topsoil operations. No lane closures are expected.
FM 2493 Widen Non-Freeway
The contractor has closed the entrance to CR 172. The closure is scheduled to last approximately four weeks. Motorists are asked to use the detour at CR 177 to access CR 172. Detour signs are in place. This project consists of widening the existing non-freeway roadway.
I-20 Bridge Maintenance
The contractor has no work scheduled this week. This project is bridge maintenance, consisting of cleaning and painting existing steel bridge superstructures.
Pedestrian Sidewalks & Curb Ramps
The contractor is scheduled to complete the ramps at the directional islands and sidewalk ramps. The contractor is also scheduled to set signs and will prepare to move to the 5th Street and Beckham intersection. Motorists should drive with caution. Lane closures are possible. The project consists of upgrading pedestrian safety measures at various intersections.
Smith County Bridge Rehabilitation
The contractor is scheduled to conduct final repairs to the US 79 bridge at the Trinity River. Striping will soon follow. The contractor also plans to fill an existing cavity beneath the bridge at FM 2699 and Running Creek. Crews will also continue bridge deck prep for surface overlay. Lane closures are expected. Motorists should drive with caution. The project consists of cleaning and sealing the existing bridge joints, asphalt work, resurfacing the bridge deck, installation of new metal beam guard fence, steel and concrete repairs.
I-20 Bridge Maintenance
The contractor is scheduled to begin installing cables for work at the CR 496 bridge at I-20. There will be temporary traffic signals installed on CR 496 for both the north and southbound traffic. This project is bridge maintenance consisting of cleaning and painting the existing steel bridge structures.
FM 16 Widening and Realignment
The project consists of grading, asphalt base, asphalt surface overlay paving, storm drain, bridge, and culvert structures, signing, pavement markings, and signals. A traffic shift is currently in place through town. Traffic will be in two lanes during this phase of construction. Embankment installation is ongoing. The contractor is scheduled to install curb and gutter and sidewalk sections at various locations. Crews will also work on storm drain installation. Bridge work will continue throughout the project limits. (This project is located in Smith County but is managed by the Mineola Area Office.)
SH 31 Resurfacing
The contractor is scheduled to continue overlay operations in the east and westbound lanes. Also, the contractor will be repairing the base at the Spur 364 and SH 31 intersection. Traffic will be rerouted to FM 206 during operations. The project includes prep row, base repairs, resurfacing, striping, and signage. Motorists should use caution when traveling through area and expect delays. (This project is located in Smith County but is managed by the Athens Area Office.)
---------------------------------------
Van Zandt County
This week, Canton crews are scheduled to address pavement issues throughout the county.
Van Zandt County construction projects updates:
FM 17, FM 47, and FM 859 Bridge Replacement
This project is for the construction of a new bridge and approaches, grading, base and surface, and metal beam guard fence installation. Motorists should expect work zone speed limit reductions and shoulder width reductions on the I-20 main lanes. Motorists should also expect work zone speed limit reductions and shoulder width reductions on the I-20 frontage roads. On FM 17, crews are scheduled to perform paving operations. On FM 47, crews are scheduled to install concrete median and begin asphalt paving operations. On FM 859, crews are scheduled to install the concrete barrier.
FM 1255 Rehabilitate Existing Roadway
This project is for the rehabilitation of the existing roadway consisting of roadway widening, grading, rework base material, cement treatment, flex base, TCST, resurfacing intersections & driveways, extending cross structures, signs, and pavement markings. The project will be completed under traffic. Right of way prep and tree trimming are ongoing. Roadway rehabilitation operations and cross structure installation are ongoing pending weather. This work also consists of milling the existing roadway. Lane closures and speed zone reductions are expected. Motorists should expect delays.
I-20 WB Exit Ramp at SH 19
This project consists of ramp improvements. Crews have begun construction on the drainage structures and frontage road alignment. Crews are scheduled to prepare for sealcoat operations, followed by striping operations. This is expected to start within the next couple of weeks. Closeout items will follow.
SH 64 at I-20 and SH 155 at I-20 Traffic Signal Installation
The project includes the construction and installation of traffic control devices including pedestrian signals. The SH 64 intersection striping layout has been completed. SH 155 intersection signals are complete and functioning. The frontage roads between SH 155 and Lawhon Ave. have been converted to one-way travel only. Major items and punch list items have been addressed. Project is awaiting final acceptance.
FM 1651 Rehabilitate Existing Roadway
Construction is on-going for the cross structures and headwalls. The project is for the rehabilitation of the existing roadway, including widening, base repairs, signage, and striping. Subgrade work will be completed in one-mile segments. Lane closures and speed zone reductions are expected. Motorists should expect delays. (This project is located in Van Zandt County but is managed by the Athens Area Office.)
FM 279 Rehabilitation
The contractor is scheduled to pave driveways and striping operations. Motorists should expect delays and use caution when traveling through the area. Lane closures are in place. The project consists of pavement repair, grading ditches, drainage structures, asphalt, striping, and signage. (This project is located in Van Zandt County but is managed by the Athens Area Office.)
E Tyler St. at Mill Creek Bridge
This project is for bridge replacement, new approaches, grading, and base repairs. The contractor is scheduled to perform seeding and embankment work. E. Tyler Street is closed to through traffic.
---------------------------------------
Wood County
This week, crews are scheduled to perform ditch maintenance at various locations in Wood County. Expect lane closures with flaggers and a pilot car controlling traffic. Also, crews will apply herbicide at various locations throughout the county. Crews will also perform bridge inspections and maintenance at various locations.
Wood County construction projects updates:
US 69 Hot mix overlay
This project consists of milling, level-up, surface repair, structures, signs, and pavement markings. Project closeout is ongoing.
US 69 Grade-Separated Interchange
This project consists of grading, base, asphalt, drainage, structures, overpass, signing, and striping. There will also be curb and gutter work on the frontage road sections. Also, crews are preparing foundations for the retaining wall. Crews are scheduled to work on the retaining walls. Motorists should be cautious of large equipment in the work zone. Lane closures are expected. Motorists should expect delays.
----------------------------------------
I-20 Total Maintenance Contract