The City of Fort Lauderdale is implementing traffic calming improvements on NE 16th Court between NE 5th Terrace and Old Dixie Highway. Improvements will include, but are not limited to:
• Installation of a median west of NE 7th Ave
• Construction of a semi-roundabout at NE 9th Ave
• Milling and resurfacing
• Concrete curb
• Sod installation
• New pavement markings
Construction will begin on Monday, August 4, 2025, and is expected to be completed by early October. Work will take place Monday through Friday, between 8 a.m. and 6 p.m. This schedule is subject to change based on inclement weather or other unforeseen circumstances.
Traffic impacts:
We appreciate your patience and cooperation as we work to enhance these public spaces.
Kristin Thompson, Acting Deputy Director, Transportation and Mobility
954-828-3722 or [email protected]